← Back
Miscellaneous two family
184 KENT STREET
BROOKLYN · Greenpoint · BIN 3064755
💬 Discuss this project
1899Year Built
3Stories
B9Building Class
R6BZoning
2,384 sfGross Floor Area
2Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Miscellaneous two family · 2,500 sf lot · 0.95 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbing
Roof3p · 2 filings · 14 docs
Bulkhead1p · 1 filing · 3 docs
Penthouse4p · 1 filing · 11 docs
Floor 51p · 1 filing · 3 docs
Floor 41p · 1 filing · 3 docs
Floor 33p · 2 filings · 14 docs
Floor 21p · 1 filing · 3 docs
Floor 11p · 1 filing · 3 docs
Cellar2p · 1 filing · 11 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/06/2024$2.2M—— → —$944/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CO.DE CONSULTING AND DESIGN, INC.306/26/2025
KZ ENGINEERING, P.C103/18/2020
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
BIGMAN BROS., INC.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
KZ ENGINEERING, P.C.4665103/18/2020
Building Lifecycle
All (55)Filed (4)Violation (16)Objection (10)Special Inspection (25)
05/05/2026
Violation issued (HPD, closed)
A
07/07/2025
Objection raised — Scope
07/07/2025
Objection raised — Scope
06/26/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HORIZONTAL AND VERTICAL ENLARGEMENT OF EXISTING 3 STORY BUILDING, PROPOSED 4 STORY AND PENTHOUSE.
B01228434-S3
06/26/2025
Objection raised — Cost
06/26/2025
Objection resolved — Addressed
06/26/2025
Objection raised — Scope
06/26/2025
Objection raised — Fire_Protection
06/26/2025
Objection raised — Structural
06/26/2025
Objection raised — Scope
06/26/2025
Objection raised — Structural
06/26/2025
Objection raised — Scope
06/17/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HORIZONTAL AND VERTICAL ENLARGEMENT OF EXISTING 3 STORY BUILDING, PROPOSED 4 STORY AND PENTHOUSE.
B01228434-S2
06/17/2025
Special inspection requirement — HVAC-R and service water heating system controls
Wieslawa Jasiulewicz Majran
06/17/2025
Special inspection requirement — HVAC-R and service water heating equipment
Wieslawa Jasiulewicz Majran
06/17/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Wieslawa Jasiulewicz Majran
06/17/2025
Special inspection requirement — Shutoff dampers
Wieslawa Jasiulewicz Majran
06/16/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HORIZONTAL AND VERTICAL ENLARGEMENT OF EXISTING 3 STORY BUILDING, PROPOSED 4 STORY AND PENTHOUSE.
B01228434-I1
06/10/2025
Violation issued (HPD, closed)
A
06/10/2025
Special inspection requirement — Final
06/10/2025
Special inspection requirement — Mechanical Systems
06/09/2025
Special inspection requirement — Fire-Resistance Rated Construction
06/09/2025
Special inspection requirement — Lowest Floor Elevation
06/09/2025
Special inspection requirement — Protection of exposed foundation insulation
Wieslawa Jasiulewicz Majran
06/09/2025
Special inspection requirement — Concrete - Cast-In-Place
06/09/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
06/09/2025
Special inspection requirement — Masonry
06/09/2025
Special inspection requirement — Subgrade Inspections
06/09/2025
Special inspection requirement — Energy Code Compliance Inspections
06/09/2025
Special inspection requirement — Maintenance information
Wieslawa Jasiulewicz Majran
06/09/2025
Special inspection requirement — Air barrier continuity plan testing
Wieslawa Jasiulewicz Majran
06/09/2025
Special inspection requirement — Interior lighting power
Wieslawa Jasiulewicz Majran
06/09/2025
Special inspection requirement — Lighting in dwelling units
Wieslawa Jasiulewicz Majran
06/09/2025
Special inspection requirement — Metering
Wieslawa Jasiulewicz Majran
06/09/2025
Special inspection requirement — Exterior lighting power
Wieslawa Jasiulewicz Majran
05/23/2025
Special inspection requirement — Air barrier - visual inspection
Wieslawa Jasiulewicz Majran
05/23/2025
Special inspection requirement — Fenestration areas
Wieslawa Jasiulewicz Majran
05/23/2025
Special inspection requirement — Insulation placement and R values
Wieslawa Jasiulewicz Majran
05/23/2025
Special inspection requirement — Fenestration air leakage
Wieslawa Jasiulewicz Majran
05/23/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Wieslawa Jasiulewicz Majran
03/23/2023
Violation issued (HPD, closed)
A
11/10/2022
Violation issued (HPD, closed)
I
02/25/2022
Violation issued (HPD, closed)
A
04/09/2021
Violation issued (HPD, closed)
A
03/18/2020
Filed — Alteration
B00250568-I1
10/18/2018
Violation issued (HPD, closed)
I
11/24/2017
Violation issued (HPD, closed)
I
11/10/2016
Violation issued (HPD, closed)
I
10/09/2015
Violation issued (HPD, closed)
I
02/23/2015
Violation issued (HPD, closed)
I
11/17/2010
Violation issued (FDNY_NOV, closed)
03/03/2006
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
04/11/1997
Violation issued (HPD, closed)
A
05/07/1982
Violation issued (HPD, closed)
A
01/20/1982
Violation issued (HPD, closed)
A
Nothing on file for this building.
1 project · most recent 06/26/2025
Air Conditioning Systems Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
06/26/2025——Air Conditioning Systems, Heating Systems, Ventilation Systems
Cooling
Mitsubishi Electric MXZ-4C36NAHZ2 36,000 BTU · Heat Pump Outdoor ×4
MXZ-3C24NAHZ2 22,000 BTU · Heat Pump Outdoor ×3
Heating
Mitsubishi Electric MXZ-4C36NAHZ2 45,000 BTU ×4
MXZ-3C24NAHZ2 25,000 BTU ×3
1 project · most recent 06/26/2025
Storm Water/Sanitary
FiledStatusContractorScope
06/26/2025——Storm, Water/Sanitary
1 project · most recent 05/06/2024
General Wiring
FiledStatusContractorScope
05/06/2024CancelledBIGMAN BROS., INC.General Wiring
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
06/17/2025HVAC-R and service water heating system controlsWieslawa Jasiulewicz Majranenergy_progress
06/17/2025HVAC-R and service water heating equipmentWieslawa Jasiulewicz Majranenergy_progress
06/17/2025HVAC-R and service water piping design and insulationWieslawa Jasiulewicz Majranenergy_progress
06/17/2025Shutoff dampersWieslawa Jasiulewicz Majranenergy_progress
06/10/2025Final—progress
06/10/2025Mechanical Systems—special
06/09/2025Fire-Resistance Rated Construction—progress
06/09/2025Lowest Floor Elevation—progress
06/09/2025Protection of exposed foundation insulationWieslawa Jasiulewicz Majranenergy_progress
06/09/2025Concrete - Cast-In-Place—special
06/09/2025Fire-Resistant Penetrations and Joints—special
06/09/2025Masonry—special
06/09/2025Subgrade Inspections—special
06/09/2025Energy Code Compliance Inspections—progress
06/09/2025Maintenance informationWieslawa Jasiulewicz Majranenergy_progress
06/09/2025Air barrier continuity plan testingWieslawa Jasiulewicz Majranenergy_progress
06/09/2025Interior lighting powerWieslawa Jasiulewicz Majranenergy_progress
06/09/2025Lighting in dwelling unitsWieslawa Jasiulewicz Majranenergy_progress
06/09/2025MeteringWieslawa Jasiulewicz Majranenergy_progress
06/09/2025Exterior lighting powerWieslawa Jasiulewicz Majranenergy_progress
05/23/2025Air barrier - visual inspectionWieslawa Jasiulewicz Majranenergy_progress
05/23/2025Fenestration areasWieslawa Jasiulewicz Majranenergy_progress
05/23/2025Insulation placement and R valuesWieslawa Jasiulewicz Majranenergy_progress
05/23/2025Fenestration air leakageWieslawa Jasiulewicz Majranenergy_progress
05/23/2025Fenestration and door U-factor and product ratingsWieslawa Jasiulewicz Majranenergy_progress
▾Documents — 35 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch3
08/21/2026B01228434-S3Request digital key ↗
08/21/2026B01228434-S2Request digital key ↗
08/21/2026B01228434-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
09/02/2026B00250568-I1Request digital key ↗
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION3
12/11/2020321999799Open ↗
03/02/2020321999799Open ↗
12/09/2019321999799Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
01/02/2021321999799Open ↗
▸Zoning, Tax Lot & Property Records4
▸BISZONING DIAGRAM2
01/02/2021321999799Open ↗
01/02/2021321999799Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
01/02/2021321999799Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01228434-I1Open ↗
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/13/2026B01228434-I1Open ↗
08/13/2026B01228434-S2Open ↗
08/13/2026B01228434-S3Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/27/2026B01228434-I1Open ↗
08/23/2026B01228434-S3Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
12/09/2019321999799Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
12/09/2019321999799Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026B00250568-I1Open ↗
08/13/2026B01228434-S2Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
12/09/2019321999799Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/09/2019321999799Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
01/02/2021321999799Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
01/02/2021321999799Open ↗
01/02/2021321999799Open ↗
▸Approvals, Objections & Sign-offs3
▸BISSCHEDULE A - OCCUPANCY / USE2
12/11/2020321999799Open ↗
12/09/2019321999799Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
01/02/2021321999799Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
12/09/2019321999799Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
03/02/2020321999799Open ↗
12/09/2019321999799Open ↗
▸Other Documents2
▸BISPLOT DIAGRAM1
01/02/2021321999799Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01228434-I1Open ↗