DOB08/02/2023FEU OBSERVED FRONT DRIVEWAY EXCAVATED NEAR EXP4.UNDERPININGWORK WITHOUT PERMIT WAS.OBSERVED ALONG EXP 1,2,3,4 WALLS.IMMED COMPLY W/ COMMISSIONER'S ORDER#343090(080223FEU31201ZT) TO REPAIR THE BUILDING UNDER PERMIT
DOB01/25/2023V-DOB VIOLATION - ACTIVE
DOB01/25/2023V-DOB VIOLATION - ACTIVE
DOB01/25/2023V-DOB VIOLATION - ACTIVE
DOB01/12/2023PROVIDE APPROXIMATELY 80 CUBIC YARDS OF BACKFILL MATERIAL. BACKFILL TO THE TOP OF ORIGINAL FOUNDATION ELEVATION AND EXTERIOR GRADE ELEVATION EARTH RETENTION SYSTEM DESIGNED BY A REGISTERED NYS PE TO BE PROVIDED TO FACILITATE BACKFILL AT DIFFERING ELEVATIONS.PROVIDE APPROX.20 LFOF FENCING AT EXP#1,+/- 25LF ALONG EXP#2& =/-25 LF ALONG EXP#4 TO ENCLOSE
DOB01/11/2023IMMEDIATELY SHORE THE FIRST FLOOR FRAMING JOISTS
DOB01/11/2023PROVIDE APPROXIMATELY 80 CUBIC YARDS OF BACKFILL MATERIAL. BACKFILL TO THE TOP OF ORIGINAL FOUNDATION ELEVATION AND EXTERIOR GRADE ELEVATION PROVIDE APPROX. 20 LINEAR FEET OF FENCING AT EXPOSURE 1 TO ENCLOSE THE UNPROTECTED SITE
DOB01/10/2023WORK WITHOUT A PERMIT. NOTED : OBSERVED ON THE RIGHT SIDE OF THE FRONT YARD, AND CELLAR EXCAVATION WORK IS BEING DONE . IN THE CELLAR THE DUG APPROXIMATELY 3FEET OF SOIL OUT,ALSO REMOVING PART OF THE LOAD BEARING WALL,AND IN THE YARD APPROXIMATELY 7 FEET OF SOIL WAS DUG UP. THERE IS NO JOB FILING IN DOB NOW, OR BIS ,
ECB01/17/2023UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER: AT TIME OF INSPECTION RENOVATIONS WERE PERFORMED CONTRARY TO PSWO VIO23-00059 ISSUED ON 01/10/23 IN EFFECT. THE 22' FT IN LENGTH X 5'FT WIDE X 6'FNothing owed — awaiting certificate of correction
ECB07/23/2008WORK W/O A PERMIT CREATED CURB CUT APPROX 10' LONG IN PUBLIC SIDEWALK FOR ACCESS TO ILLEGAL PARKING PAD AT FRONT YARD. REMEDY: OBTAIN ALL NECESSARY PERMITS OR RESTORE PROPERTY TO ITS PRIOR LEGAL CONDITION.Nothing owed — awaiting certificate of correction
Two family converted from one family · 1,800 sf lot · 0.86 FAR built · Flood zone X