| Owner | Filings | Most Recent |
|---|---|---|
| RIKARD VUKA 1 | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/18/2020 | $2.1M | — | Private party → Private party | $1,282/sf building |
| 06/23/2017 | $1.5M | — | Private party → Private party | $936/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ARCHIMUSE | 3 | 10/04/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| DOMINION EXPEDITING | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FOUR SEASONS SOLAR PRODUCTS LLC | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHOI ENGINEERING PLLC | 2264 | 2 | 10/04/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | FOUR SEASONS SOLAR PRODUC | 08/13/2024 |
| BIS | OT | ISSUED | RIKARD VUKA | 10/26/2018 |
| BIS | EQ | ISSUED | RIKARD VUKA | 10/26/2018 |
| BIS | OT | ISSUED | BROOKLYN SOLARWORKS LLC | 04/23/2018 |
| BIS | PL | ISSUED | TAP PLUMBING CORP | 03/14/2018 |
| BIS | MH | ISSUED | RIKARD VUKA | 09/22/2017 |
| BIS | EQ | ISSUED | RIKARD VUKA | 09/22/2017 |
| BIS | OT | ISSUED | RIKARD VUKA | 09/22/2017 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/30/2024 | Complete | A.C.M. ELEC'L CONTR'G COR | General Wiring |
| 01/15/2020 | Permit Issued | DUDLEY & ASSOC. LIC. ELEC | General Wiring |
| 12/17/2019 | Permit Issued | DUDLEY & ASSOC. LIC. ELEC | General Wiring |
| 05/01/2018 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/04/2024 | Permit Issued | FOUR SEASONS SOLAR PRODUC | Wood |
| 02/12/2024 | — | — | Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/21/2024 | Fenestration air leakage | Eugene Choi | energy_progress |
| 10/21/2024 | Concrete - Cast-In-Place | Eugene Choi | special |
| 10/21/2024 | Structural Stability – Alterations of existing buildings | Eugene Choi | special |
| 10/21/2024 | Fire-Resistant Penetrations and Joints | Eugene Choi | special |
| 10/21/2024 | Structural Cold-Formed Steel | Eugene Choi | special |
| 10/21/2024 | Subgrade Inspections | — | special |
| 10/21/2024 | Structural Steel - Welding | Eugene Choi | special |
| 10/21/2024 | Structural Steel - High Strength Bolting | — | special |
| 10/21/2024 | Final | Eugene Choi | progress |
| 10/21/2024 | Fire-Resistance Rated Construction | Eugene Choi | progress |
| 10/21/2024 | Air barrier - visual inspection | Eugene Choi | energy_progress |
| 10/21/2024 | Fenestration and door U-factor and product ratings | Eugene Choi | energy_progress |
| 10/21/2024 | Fenestration areas | Eugene Choi | energy_progress |
| 10/21/2024 | Post-installed Anchors | Eugene Choi | special |
| 02/12/2024 | Structural Steel - Welding | — | special |
| 01/15/2024 | Fire-Resistant Penetrations and Joints | — | special |
| 01/15/2024 | Post-installed Anchors | — | special |
| 01/15/2024 | Structural Cold-Formed Steel | — | special |
| 01/15/2024 | Structural Stability – Alterations of existing buildings | — | special |
| 01/15/2024 | Concrete - Cast-In-Place | — | special |
| 01/15/2024 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 01/15/2024 | Fenestration air leakage | — | energy_progress |
| 01/15/2024 | Air barrier - visual inspection | — | energy_progress |
| 01/15/2024 | Fenestration areas | — | energy_progress |
| 01/15/2024 | Fire-Resistance Rated Construction | — | progress |