← Back
Two family brick
1861 LURTING AVENUE
BRONX · Morris Park · BIN 2045519
💬 Discuss this project
1935Year Built
1.5Stories
B1Building Class
R4AZoning
2,523 sfGross Floor Area
2Units
3 Open Violations ▸FDNY Report ↗
Two family brick · 2,500 sf lot · 1.01 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingGeneral
Basement1p · 1 filing · 10 docs
Sub-Basement3p · 1 filing · 10 docs
Filed — no permit issued11p · 1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
J&R DESIGN AND INSPECTION CORP.202/01/2023
ST DESIGN & CONSULTING INC.111/27/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
HIGH QUALITY 338403/21/2026
R H DRUMMOND EXP203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AMERICAN STANDARD P&H CORORP.Plumbing307/08/2026
ALL WAYS ELECTRIC CORP.WElectrical103/22/2026
ISLAND ELECTRIC CORPElectrical103/22/2026
JEFFREY MARINELLOElectrical103/21/2026
RICHARD ESPOSITOElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
J&R DESIGN AND INSPECTION6637202/01/2023
Building Lifecycle
All (56)Filed (3)Permit Issued (2)Violation (4)Inspection (6)Objection (28)Special Inspection (13)
11/17/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/06/2023
Objection raised — Other
04/04/2023
Objection resolved — Addressed
03/31/2023
Objection resolved — Addressed
03/31/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
03/22/2023
Objection resolved — Addressed
03/16/2023
Objection resolved — Addressed
03/16/2023
Objection resolved — Addressed
03/16/2023
Objection resolved — Addressed
03/16/2023
Objection resolved — Addressed
03/16/2023
Objection resolved — Addressed
03/16/2023
Objection resolved — Addressed
02/21/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/21/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/13/2023
Objection resolved — Addressed
02/13/2023
Objection resolved — Addressed
02/13/2023
Objection resolved — Addressed
02/13/2023
Objection resolved — Addressed
02/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Truskosky
02/03/2023
Special inspection requirement — Energy Code Compliance Inspections
Robert Truskosky
02/01/2023
Filed — Alteration
FILE TO PLUMBING WORK AS PER PLAN , NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00581011-P1
01/19/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Robert Truskosky
01/19/2023
Special inspection requirement — Energy Code Compliance Inspections
Robert Truskosky
01/06/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/27/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
11/30/2022
Objection raised — Zoning
11/30/2022
Objection raised — Zoning
11/30/2022
Objection raised — Structural
11/30/2022
Objection raised — Energy
11/30/2022
Objection raised — Structural
11/30/2022
Objection raised — Zoning
11/30/2022
Objection raised — Fire_Protection
11/30/2022
Objection raised — Scope
11/30/2022
Objection raised — Inspections
11/30/2022
Objection raised — Zoning
11/29/2022
Objection raised — Zoning
11/29/2022
Objection raised — Zoning
11/29/2022
Objection raised — Zoning
11/29/2022
Objection raised — Zoning
11/27/2022
Filed — Alteration
X08020570-I1
11/18/2022
Inspection — No Access-Final PL - Up to 3 Requested Floors
No Access
View inspection ↗
11/02/2022
Permit issued — Plumbing
X00581011-I1-PL
10/14/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/14/2022
Special inspection requirement — Fenestration areas
10/14/2022
Special inspection requirement — Interior lighting power
10/14/2022
Special inspection requirement — Insulation placement and R values
10/14/2022
Special inspection requirement — Masonry
10/14/2022
Special inspection requirement — Fenestration air leakage
10/14/2022
Special inspection requirement — Air barrier - visual inspection
10/14/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
10/20/2021
Permit issued — Plumbing
X00581011-I1-PL
08/30/2021
Filed — Alteration
FILE TO PLUMBING WORK AS PER PLAN , NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X00581011-I1
02/22/2012
Violation issued (HPD, open)
B
02/22/2012
Violation issued (HPD, open)
B
02/22/2012
Violation issued (HPD, open)
B
03/18/2007
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedAMERICAN STANDARD P&H CORORP.11/02/2022
DOB NOWPlumbingPermit IssuedAMERICAN STANDARD P&H CORORP.10/20/2021
BISOTISSUEDPRO CUSTOM SOLAR LLC08/29/2023
BISOTISSUEDCENTURION SOLAR ENERGY06/03/2022
2 projects · most recent 10/24/2023
FiledStatusContractorScope
10/24/2023CompleteISLAND ELECTRIC CORP—
11/27/2019Permit IssuedALL WAYS ELECTRIC CORP.W—
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
11/17/2023Pass-Final CND-Occupancy InspectionPassView ↗
02/21/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/21/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
01/06/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/27/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
11/18/2022No Access-Final PL - Up to 3 Requested FloorsNo AccessView ↗
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
03/31/2023Structural Stability – Alterations of existing buildings—special
02/03/2023Fire-Resistant Penetrations and JointsRobert Truskoskyspecial
02/03/2023Energy Code Compliance InspectionsRobert Truskoskyprogress
01/19/2023Fire-Resistant Penetrations and JointsRobert Truskoskyspecial
01/19/2023Energy Code Compliance InspectionsRobert Truskoskyprogress
10/14/2022Fire-Resistant Penetrations and Joints—special
10/14/2022Fenestration areas—energy_progress
10/14/2022Interior lighting power—energy_progress
10/14/2022Insulation placement and R values—energy_progress
10/14/2022Masonry—special
10/14/2022Fenestration air leakage—energy_progress
10/14/2022Air barrier - visual inspection—energy_progress
10/14/2022Fenestration and door U-factor and product ratings—energy_progress
▾Documents — 53 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/23/2026X08020570-I1Request digital key ↗
08/23/2026X00581011-I1Request digital key ↗
08/23/2026X00581011-P1Request digital key ↗
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸BISWORK PERMIT APPLICATION2
08/29/2023240354086Open ↗
06/03/2022240330085Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026X08020570-I1Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/23/2026X08020570-I1Open ↗
08/13/2026X00581011-P1Open ↗
08/13/2026X00581011-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/31/2026X00581011-I1Open ↗
08/28/2026X00581011-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/31/2026X00581011-I1Open ↗
08/28/2026X00581011-P1Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026X08020570-I1Open ↗
▸Safety & Tenant Protection2
▸BISTPP1: TENANT PROTECTION PLAN2
08/29/2023240354086Open ↗
06/02/2022240330085Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/23/2026X08020570-I1Open ↗
08/13/2026X00581011-P1Open ↗
08/13/2026X00581011-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
12/05/2023240354086Open ↗
08/25/2023240354086Open ↗
06/02/2022240330085Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS2
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)2
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/05/2023240354086Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
12/06/2023240354086Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY4
12/05/2023240354086Open ↗
08/25/2023240354086Open ↗
06/02/2022240330085Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs2
▸BISLETTERS - SUPPORTING DOCUMENTATION1
12/06/2023240354086Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
12/06/2023240354086Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
12/05/2023240354086Open ↗
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET2
08/25/2023240354086Open ↗
06/01/2022240330085Open ↗
▸Other Documents3
▸DOB NOWSite Survey: Initial1
08/13/2026X08020570-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026X08020570-I1Open ↗
▸DOB NOWPlot Diagram1
08/13/2026X08020570-I1Open ↗