1920Year Built
2.75Stories
B2Building Class
R3-2Zoning
2,366 sfGross Floor Area
2Units
3 Open Violations ▸FDNY Report ↗
Two family frame · 4,000 sf lot · 0.59 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralPlumbingFire ProtectionCivilGeneral
Permit Issued — active, not yet Signed-off
AtticUnder Construction18p · 1 filing · 20 docs
Floor 2Under Construction31p · 1 filing · 20 docs
Floor 1Under Construction22p · 1 filing · 20 docs
CellarUnder Construction30p · 1 filing · 20 docs
Site & exteriorUnder Construction35p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/18/2019$1.6M—Private party → Private party$676/sf building
05/14/2018$1.5M—— → —$647/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MISTER EXPEDITER603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
M.N.C. GENERAL CONTR CORPGeneral Contractor1107/08/2026
NESS MECHANICAL P & H INCPlumbing707/08/2026
LEONID SIMKINElectrical103/21/2026
QUALITY PIPING, INCFire Protection106/28/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MSM ENGINEERING SERVICES,8449203/12/2025
M. INT'L ENGINEERING PLLC3129312/06/2023
Building Lifecycle
All (60)Filed (6)Permit Issued (10)Violation (4)Inspection (7)Objection (24)Special Inspection (9)
07/28/2026
Violation issued (ECB, open)
Unknown
02/27/2026
Permit issued — Construction Fence
B00595991-S2-FN
02/27/2026
Permit issued — General Construction
B00595991-I1-GC
02/27/2026
Violation issued (ECB, open)
Unknown
02/27/2026
Violation issued (ECB, open)
Construction
01/17/2026
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/09/2025
Permit issued — Sprinklers
B00595991-S6-EW-SP
03/25/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/12/2025
Filed — Alteration CO
INSTALL FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13D 2016 EDIT, AS MODIFIED BYNYC BC CHAPTER 903.1.2 AND APPENDIX Q103 AS PER PLAN
B00595991-S6
02/26/2025
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
02/25/2025
Inspection — Certified StandPipe-SD-Fixtures-Finish-SD
Certified
View inspection ↗
02/07/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
12/16/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
12/16/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/10/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
12/06/2024
Special inspection requirement — Sprinkler Systems
MOHAMED MAHMOUD
10/07/2024
Permit issued — Plumbing
B00595991-S1-PL
07/26/2024
Filed — Alteration CO
INSTALL FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13D 2016 EDIT, AS MODIFIED BYNYC BC CHAPTER 903.1.2 AND APPENDIX Q103 AS PER PLAN
B00595991-S1
07/16/2024
Permit issued — General Construction
B00595991-I1-GC
07/16/2024
Permit issued — Construction Fence
B00595991-S2-FN
07/15/2024
Special inspection requirement — Energy Code Compliance Inspections
MOHAMED MAHMOUD
07/15/2024
Special inspection requirement — HVAC-R and service water heating system controls
MOHAMED MAHMOUD
07/15/2024
Special inspection requirement — HVAC-R and service water heating equipment
MOHAMED MAHMOUD
07/15/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
MOHAMED MAHMOUD
07/15/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
MOHAMED MAHMOUD
12/22/2023
Permit issued — Structural
B00595991-S3-ST
12/22/2023
Permit issued — Foundation
B00595991-S5-FO
12/06/2023
Filed — Alteration CO
INSTALL FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13D 2016 EDIT, AS MODIFIED BYNYC BC CHAPTER 903.1.2 AND APPENDIX Q103 AS PER PLAN
B00595991-S5
11/17/2023
Objection resolved — Addressed
11/17/2023
Objection resolved — Addressed
11/17/2023
Objection resolved — Addressed
11/17/2023
Objection resolved — Addressed
11/14/2023
Objection resolved — Addressed
10/25/2023
Objection raised — Inspections
10/25/2023
Objection raised — Structural
10/25/2023
Objection raised — Other
10/25/2023
Objection raised — Other
10/25/2023
Objection raised — Inspections
10/19/2023
Filed — Alteration CO
INSTALL FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13D 2016 EDIT, AS MODIFIED BYNYC BC CHAPTER 903.1.2 AND APPENDIX Q103 AS PER PLAN
B00595991-S3
10/17/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
NANIK MASSAND
08/16/2023
Permit issued — General Construction
B00595991-I1-GC
08/14/2023
Permit issued — Construction Fence
B00595991-S2-FN
08/03/2023
Filed — Alteration CO
INSTALL FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13D 2016 EDIT, AS MODIFIED BYNYC BC CHAPTER 903.1.2 AND APPENDIX Q103 AS PER PLAN
B00595991-S2
07/06/2023
Objection resolved — Addressed
07/06/2023
Objection resolved — Addressed
06/26/2023
Objection resolved — Addressed
06/26/2023
Special inspection requirement — Footing and Foundation
NANIK MASSAND
06/26/2023
Special inspection requirement — Final
Kevin McCray
06/21/2023
Objection resolved — Addressed
04/27/2023
Objection resolved — Addressed
04/27/2023
Objection resolved — Addressed
04/27/2023
Objection resolved — Addressed
10/17/2021
Objection raised — Other
10/08/2021
Objection raised — Other
10/08/2021
Objection raised — Other
10/08/2021
Objection raised — Other
10/08/2021
Objection raised — Other
10/08/2021
Objection raised — Other
10/08/2021
Objection raised — Other
10/01/2021
Filed — Alteration CO
INSTALL FIRE SPRINKLER SYSTEM IN THE ENTIRE BUILDING I.A.W. NFPA 13D 2016 EDIT, AS MODIFIED BYNYC BC CHAPTER 903.1.2 AND APPENDIX Q103 AS PER PLAN
B00595991-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedMNC GENERAL CONTR CORP02/27/2026
DOB NOWGeneral ConstructionPermit IssuedMNC GENERAL CONTR CORP02/27/2026
DOB NOWSprinklersPermit IssuedQUALITY PIPING, INC05/09/2025
DOB NOWPlumbingPermit IssuedNESS MECHANICAL P & H INC10/07/2024
DOB NOWGeneral ConstructionPermit IssuedMNC GENERAL CONTR CORP07/16/2024
DOB NOWConstruction FencePermit IssuedMNC GENERAL CONTR CORP07/16/2024
DOB NOWStructuralPermit IssuedMNC GENERAL CONTR CORP12/22/2023
DOB NOWFoundationPermit IssuedMNC GENERAL CONTR CORP12/22/2023
DOB NOWGeneral ConstructionPermit IssuedMNC GENERAL CONTR CORP08/16/2023
DOB NOWConstruction FencePermit IssuedMNC GENERAL CONTR CORP08/14/2023
1 project · most recent 03/12/2025
FiledStatusContractorScope
03/12/2025Permit IssuedQUALITY PIPING, INC41 heads
1 project · most recent 07/01/2025
General Wiring
FiledStatusContractorScope
07/01/2025Permit IssuedLENS ELECTRIC, INCGeneral Wiring
1 project · most recent 03/12/2025
Concrete Wood
FiledStatusContractorScope
03/12/2025Permit IssuedMNC GENERAL CONTR CORPConcrete, Wood
1 project · most recent 03/12/2025
Fence
FiledStatusContractorScope
03/12/2025Permit IssuedMNC GENERAL CONTR CORPFence
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
03/25/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/26/2025Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
02/25/2025Certified StandPipe-SD-Fixtures-Finish-SDCertifiedView ↗
02/07/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
12/16/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/16/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/10/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 9
DateRequirementInspectorRole
12/06/2024Sprinkler SystemsMOHAMED MAHMOUDspecial
07/15/2024Energy Code Compliance InspectionsMOHAMED MAHMOUDprogress
07/15/2024HVAC-R and service water heating system controlsMOHAMED MAHMOUDenergy_progress
07/15/2024HVAC-R and service water heating equipmentMOHAMED MAHMOUDenergy_progress
07/15/2024HVAC-R and service water piping design and insulationMOHAMED MAHMOUDenergy_progress
07/15/2024Fire-Resistant Penetrations and JointsMOHAMED MAHMOUDspecial
10/17/2023Structural Stability – Alterations of existing buildingsNANIK MASSANDspecial
06/26/2023Footing and FoundationNANIK MASSANDprogress
06/26/2023FinalKevin McCrayprogress
▾Documents — 34 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/22/2026B00595991-S6Request digital key ↗
08/22/2026B00595991-S5Request digital key ↗
08/22/2026B00595991-S2Request digital key ↗
Showing 3 of 6 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B00595991-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B00595991-I1Open ↗
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/22/2026B00595991-S6Open ↗
08/22/2026B00595991-S5Open ↗
08/22/2026B00595991-S3Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/25/2026B00595991-S5Open ↗
09/25/2026B00595991-S5Open ↗
08/29/2026B00595991-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/25/2026B00595991-S5Open ↗
08/29/2026B00595991-S1Open ↗
08/29/2026B00595991-S6Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B00595991-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/15/2026B00595991-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/22/2026B00595991-S6Open ↗
08/22/2026B00595991-S5Open ↗
08/22/2026B00595991-S2Open ↗
Showing 3 of 6 on file for this type
▸Inspections & Test Reports1
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026B00595991-S5Open ↗
▸Other Documents4
▸DOB NOWPlot Diagram2
08/13/2026B00595991-I1Open ↗
08/13/2026B00595991-S5Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B00595991-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/15/2026B00595991-I1Open ↗