Two family converted from one family · 4,000 sf lot · 0.52 FAR built · Flood zone X
Locations of Work
Electrical
Roof2 filings · 10 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/20/2024$1.3M—Private party → Private party$607/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MINA MAKAR208/11/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281208/11/2026
Building Lifecycle
All (9)Filed (2)Permit Issued (2)Special Inspection (5)
08/17/2026
Permit issued — Solar
Q01443893-I1-SL
08/11/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 13 modules, 5.33 KW
Q01443893-I1
08/11/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
08/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
08/11/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
08/11/2026
Special inspection requirement — Final
Mina Makar
08/11/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
09/02/2025
Permit issued — Solar
Q01277728-I1-SL
08/26/2025
Filed — Alteration
Q01277728-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR08/17/2026
DOB NOWSolarPermit IssuedMOMENTUM SOLAR09/02/2025
2 projects · most recent 08/11/2026
FiledStatusContractorScope
08/11/2026Permit IssuedISLAND ELECTRIC CORP—
10/23/2025Permit IssuedISLAND ELECTRIC CORP—
1 project · most recent 08/11/2026
FiledStatusContractorScope
08/11/2026Permit IssuedMOMENTUM SOLAR26 panels, 10.66 kw, 4,000 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
08/11/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
08/11/2026Fire-Resistant Penetrations and JointsMina Makarspecial
08/11/2026Energy Code Compliance InspectionsMina Makarprogress
08/11/2026FinalMina Makarprogress
08/11/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/19/2026Q01277728-I1Request digital key ↗
08/16/2026Q01443893-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/19/2026Q01277728-I1Open ↗
08/16/2026Q01443893-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026Q01443893-I1Open ↗
08/27/2026Q01443893-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/27/2026Q01443893-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
09/28/2026Q01443893-I1Open ↗
08/19/2026Q01277728-I1Open ↗