← Back
Two family brick
187 BEACH 60 STREET
QUEENS · Rockaway Beach-Arverne-Edgemere · BIN 4536000
💬 Discuss this project
2000Year Built
2Stories
B1Building Class
R6Zoning
2,052 sfGross Floor Area
2Units
Two family brick · 4,170 sf lot · 0.49 FAR built · Flood zone AE
Locations of Work
ArchitectureElectricalGeneral
Roof10p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC107/08/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOLAR CONTRACTING LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854107/08/2025
Building Lifecycle
All (29)Filed (1)Permit Issued (1)Signed Off (1)Objection (22)Special Inspection (4)
04/30/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM.ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THENYC DEPARTMENT OF BUILDINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01252406-I1
12/05/2025
Permit issued — Solar
Q01252406-I1-SL
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
11/03/2025
Objection resolved — Addressed
07/17/2025
Objection raised — Inspections
07/17/2025
Objection raised — Scope
07/17/2025
Objection raised — Structural
07/17/2025
Objection raised — Structural
07/17/2025
Objection raised — Zoning
07/17/2025
Objection raised — Zoning
07/17/2025
Objection raised — Energy
07/17/2025
Objection raised — Structural
07/17/2025
Objection raised — Electrical
07/17/2025
Objection raised — Structural
07/17/2025
Objection raised — Electrical
07/08/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM.ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THENYC DEPARTMENT OF BUILDINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
Q01252406-I1
07/08/2025
Special inspection requirement — Final
TOM PETERSEN
07/08/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
07/08/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
07/08/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSOLAR CONTRACTING LLC12/05/2025
BIS—ISSUEDL. RISO & SONS CO., INC11/01/2000
BISPLISSUEDBLAU MECHANICAL CORP.04/03/2000
BIS—ISSUEDL. RISO & SONS CO., INC11/12/1999
BISPLISSUEDBLAU MECHANICAL CORP10/12/1999
BIS—ISSUEDL. RISO & SONS CO., INC07/20/1999
2 projects · most recent 07/07/2025
FiledStatusContractorScope
07/07/2025CompleteVILLAGE ELECTL CONTRS INC—
07/01/2025Permit IssuedBERGER QUALITY ELEC'L CON—
1 project · most recent 07/08/2025
FiledStatusContractorScope
07/08/2025Signed-offSOLAR CONTRACTING LLC38 panels, 16.14 kw, 399.36 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
07/08/2025FinalTOM PETERSENprogress
07/08/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
07/08/2025Energy Code Compliance InspectionsTOM PETERSENprogress
07/08/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026Q01252406-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWProgress Inspector Seal & Signature3
09/07/2026Q01252406-I1Open ↗
09/07/2026Q01252406-I1Open ↗
09/07/2026Q01252406-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01252406-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/07/2026Q01252406-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/19/2026Q01252406-I1Open ↗