| Owner | Filings | Most Recent |
|---|---|---|
| SEBCO DEVELOPMENT INC. | 86 | 09/07/2026 |
| OWNERS REP | 26 | 07/08/2026 |
| CROTONA BELMONT HDFC | 5 | 03/21/2026 |
| SEBCO DEVELOPEMNT | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CAMERON ENGINEERING | 17 | 08/26/2026 |
| PAUL PERDEK, PROF. ENG. PLLC | 9 | 12/03/2025 |
| KN3 ENGINEERING LLC | 4 | 02/10/2025 |
| CITYSCAPE ENGINEERING, PLLC | 1 | 12/20/2024 |
| ASHRAF CORP | 5 | 04/30/2024 |
| JAMES STOUT ARCHITECT & ASSOCIATES | 1 | 03/28/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 26 | 03/21/2026 |
| EUROCELT EXPEDITING, INC | 10 | 03/21/2026 |
| CORE CONSULTANTS NYC | 14 | 03/21/2026 |
| SUNKEEPER SOLAR ELECTRIC LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 14 | 07/08/2026 |
| THE J. PILLA GROUP LTD | General Contractor | 9 | 07/08/2026 |
| K&E BUILDERS INC | General Contractor | 8 | 07/08/2026 |
| ASPRO PLUMBING INC | Fire Protection | 8 | 07/08/2026 |
| ASPRO PLUMBING INC | Plumbing | 7 | 07/08/2026 |
| SUNKEEPER SOLAR ELECTRIC | General Contractor | 2 | 07/08/2026 |
| RELIANT ELEC'L CONT'G INC | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CERTIFIED TESTING LABORAT | 396 | 17 | 08/26/2026 |
| JAMES J STOUT ARCHITECTS | 5913 | 1 | 03/28/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | B SOSA ENTERPRISES CORP | 09/28/2026 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 06/25/2026 |
| DOB NOW | Plumbing | Permit Issued | ASPRO PLUMBING INC | 06/25/2026 |
| DOB NOW | Structural | Signed-off | THE J. PILLA GROUP LTD | 10/02/2025 |
| DOB NOW | Construction Fence | Signed-off | THE J. PILLA GROUP LTD | 10/01/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | THE J. PILLA GROUP LTD | 10/01/2025 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 09/29/2025 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 09/26/2025 |
| DOB NOW | Structural | Signed-off | THE J. PILLA GROUP LTD | 08/29/2025 |
| DOB NOW | Supported Scaffold | Signed-off | K&E BUILDERS INC | 06/30/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | K&E BUILDERS INC | 06/30/2025 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 06/13/2025 |
| DOB NOW | Plumbing | Permit Issued | ASPRO PLUMBING INC | 05/23/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/19/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/05/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/04/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/04/2025 |
| DOB NOW | Solar | Signed-off | SUNKEEPER SOLAR ELECTRIC | 02/28/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | THE J. PILLA GROUP LTD | 01/10/2025 |
| DOB NOW | Structural | Signed-off | THE J. PILLA GROUP LTD | 01/10/2025 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 10/18/2024 |
| DOB NOW | Sprinklers | Permit Issued | ASPRO PLUMBING INC | 10/17/2024 |
| DOB NOW | Construction Fence | Signed-off | THE J. PILLA GROUP LTD | 10/16/2024 |
| DOB NOW | Supported Scaffold | Signed-off | K&E BUILDERS INC | 07/23/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | K&E BUILDERS INC | 07/22/2024 |
| DOB NOW | Plumbing | Permit Issued | ASPRO PLUMBING INC | 06/13/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/20/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/10/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/15/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/15/2024 |
| DOB NOW | Solar | Signed-off | SUNKEEPER SOLAR ELECTRIC | 03/28/2024 |
| DOB NOW | Construction Fence | Signed-off | THE J. PILLA GROUP LTD | 12/11/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | K&E BUILDERS INC | 08/02/2023 |
| DOB NOW | Supported Scaffold | Signed-off | K&E BUILDERS INC | 08/02/2023 |
| DOB NOW | Sprinklers | Permit Issued | ASPRO PLUMBING INC | 06/22/2023 |
| DOB NOW | Standpipe | Permit Issued | ASPRO PLUMBING INC | 06/20/2023 |
| DOB NOW | Plumbing | Permit Issued | ASPRO PLUMBING INC | 06/20/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/25/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 05/19/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/26/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/15/2026 | Permit Issued | THE J. PILLA GROUP LTD | Air Conditioning Systems, Associated Ducts and Piping, Heating and Air Conditioning Systems, Heating Systems | Cooling Samsung AM072BXVGFH/AA 81,000 BTU · Vrf Outdoor ×111 AM060MXMDCH/AA 135,000 BTU · Vrf Outdoor ×50 AM036TXMDCH/AA 42,000 BTU · Vrf Outdoor ×28 AM048TXMDCH/AA 54,000 BTU · Vrf Outdoor ×28 AM096BXVGFH/AA 108,000 BTU · Vrf Outdoor ×27 AM120BXVGFH/AA 135,000 BTU · Vrf Outdoor ×3 AMO96BXVGFH/AA 108,000 BTU · Vrf Outdoor ×1 Lg LSU120HSV5 12,000 BTU · Heat Pump Outdoor ×4 ARUM048GSS5 46,681 BTU · Vrf Outdoor ×1 ARUM072BTE5 29,726 BTU · Vrf Outdoor ×1 ARUM096BTE5 93,193 BTU · Vrf Outdoor ×1 Ighvac ARUM072BTES 72,607 BTU ×31 ARUN060GSS4 576,665 BTU · Vrf Outdoor ×17 ARUM144BTES 136,344 BTU · Vrf Outdoor ×2 ARUN048GSS4 41,869 BTU · Vrf Outdoor ×2 ARUNO60GSS4 29,726 BTU · Vrf Outdoor ×1 LSU120HSV4 11,200 BTU ×2 LSU12OHSV4 11,200 BTU ×2 ARUM072BTE5 92,900 BTU · Vrf Outdoor ×2 ARUM036GSS5 38,068 BTU · Vrf Outdoor ×1 ARUN024GSS4 24,000 BTU · Vrf Outdoor ×1 ARUN060GSS5 35,388 BTU · Vrf Outdoor ×1 — AM120BXVGFH/AA 135,000 BTU · Vrf Outdoor ×3 Heating Samsung AM048TXMDCH/AA 81,000 BTU · Vrf Outdoor ×4 Ighvac ARUM072BTES 88,807 BTU ×6 ARUN060GSS4 51,478 BTU · Vrf Outdoor ×4 ARUM121BTES 127,600 BTU · Vrf Outdoor ×2 ARUM144BTES 167,306 BTU · Vrf Outdoor ×2 ARUN048GSS4 50,645 BTU · Vrf Outdoor ×2 Lg AC018BXADCH/AA 12,000 BTU · Vrf Outdoor ×3 Ventilation Valent VPRE-352-50F-120I-A-5GA 18,000 CFM · Erv ×6 VXE-312-74D-30I-Q-D1 9,540 CFM · Erv ×4 ARDE-312-74D-301-Q-D1 9,540 CFM · Erv ×3 Innovent ERU-OU-1600-EH-DX-208 1,600 CFM · Makeup Air ×2 Lennox TSA120S4S-230-3 120,000 BTU · Makeup Air ×2 Refrigeration Samsung AM072BXVGFH/AA 81,000 BTU · Vrf Outdoor ×4 Ighvac ARUM121BTES 105,982 BTU · Vrf Outdoor ×2 Ducts & Piping Samsung AM120BXVGFH/AA 81,000 BTU · Vrf Outdoor ×4 Ighvac ARUN060GSS4 51,477 BTU · Vrf Outdoor ×1 Lg ARUM072BTE5 69,895 BTU · Vrf Outdoor ×1 Heat / Cool Samsung AM060MXMDCH/AA 64,000 BTU · Vrf Outdoor ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/12/2026 | Permit Issued | ASPRO PLUMBING INC | 781 heads, 1 outlets |
| 05/13/2022 | — | — | 1 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2026 | Permit Issued | ASPRO PLUMBING INC | Gas, Storm, Water/Sanitary |
| 05/12/2026 | — | — | — |
| 05/13/2022 | Permit Issued | ASPRO PLUMBING INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2024 | Permit Issued | RELIANT ELEC'L CONT'G INC | General Wiring |
| 03/19/2024 | Complete | TF ELECTRICAL CORP | General Wiring |
| 03/18/2024 | Complete | SUNKEEPER SOLAR LLC | — |
| 04/24/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| 04/10/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| 03/31/2023 | Complete | RELIANT ELEC'L CONT'G INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/03/2025 | Signed-off | CORE SCAFFOLD SYSTEMS INC | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/27/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/20/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/12/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/03/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/24/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/08/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/10/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 12/09/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/25/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/03/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/08/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 08/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/03/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/09/2024 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 07/18/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/05/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2026 | Post-installed Anchors | KIRT DOBBINS | special |
| 08/20/2026 | Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components | KIRT DOBBINS | special |
| 08/20/2026 | Fire-Resistant Penetrations and Joints | KIRT DOBBINS | special |
| 07/16/2026 | Fire-Resistant Penetrations and Joints | Vladimir Sirota | special |
| 07/16/2026 | Mechanical Systems | KIRT DOBBINS | special |
| 07/16/2026 | Heating Systems | KIRT DOBBINS | special |
| 07/16/2026 | Final | KIRT DOBBINS | progress |
| 07/16/2026 | Smoke Control Systems Testing | Vladimir Sirota | special |
| 07/16/2026 | Emergency and Standby Power Systems (Generator) | Vladimir Sirota | special |
| 06/12/2026 | Mechanical Systems | KIRT DOBBINS | special |
| 06/12/2026 | Heating Systems | KIRT DOBBINS | special |
| 06/12/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/12/2026 | Emergency and Standby Power Systems (Generator) | — | special |
| 06/12/2026 | Final | KIRT DOBBINS | progress |
| 06/12/2026 | Smoke Control Systems Testing | — | special |
| 04/29/2026 | Fire-Resistant Penetrations and Joints | KIRT DOBBINS | special |
| 04/29/2026 | Standpipe Systems | KIRT DOBBINS | special |
| 04/29/2026 | Sprinkler Systems | KIRT DOBBINS | special |
| 01/08/2026 | Seismic Resistance of Plumbing, Mechanical, Fuel Gas, and Electrical Components | KIRT DOBBINS | special |
| 01/08/2026 | Post-installed Anchors | KIRT DOBBINS | special |
| 11/06/2025 | Heating Systems | KIRT DOBBINS | special |
| 11/06/2025 | High Temperature Hot Water Piping (Welding) | KIRT DOBBINS | special |
| 11/06/2025 | High-Pressure Fuel-Gas Piping (Welding) | KIRT DOBBINS | special |
| 11/06/2025 | Final | KIRT DOBBINS | progress |
| 11/06/2025 | Fire-Resistant Penetrations and Joints | KIRT DOBBINS | special |