| Owner | Filings | Most Recent |
|---|---|---|
| SIERRA CONSTRUCTION NY | 2 | 03/22/2026 |
| SUCESS DEVELOPERS LLC | 1 | 03/22/2026 |
| DEVELOPERS LLC SUCCESS | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/16/2023 | $2.0M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| GRID DRAFTING AND CONSULTING LLC | 1 | 03/07/2024 |
| KZ ENGINEERING, P.C | 4 | 01/29/2024 |
| H & O ENGINEERING, DPC | 1 | 02/22/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SYNERGY BUILDING CONSULTANTS | 4 | 03/21/2026 |
| SUNSHINE PLAZA LLC | 11 | 03/21/2026 |
| SIERRA SAFETY CORP | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUCCESS DEVELOPERS LLC | General Contractor | 20 | 08/26/2026 |
| CS BRIDGE CORP | General Contractor | 5 | 07/08/2026 |
| METFLOW FIRE CONTROL LLC | Fire Protection | 1 | 07/08/2026 |
| CREATIVE PLUMBING IN | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Signed-off | SUCCESS DEVELOPERS LLC | 04/10/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CS BRIDGE CORP | 01/29/2024 |
| DOB NOW | Supported Scaffold | Signed-off | CS BRIDGE CORP | 01/26/2024 |
| DOB NOW | Construction Fence | Signed-off | SUCCESS DEVELOPERS LLC | 12/13/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CS BRIDGE CORP | 06/13/2023 |
| DOB NOW | Construction Fence | Signed-off | SUCCESS DEVELOPERS LLC | 02/23/2023 |
| BIS | — | ISSUED | STAR COMPANIESS LLC | 06/30/2023 |
| BIS | OT | ISSUED | DOMINICK SIANO G'NL CONT | 01/14/1999 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2024 | Complete | M.R. ELEC'L SERVICE LLC | General Wiring |
| 03/14/2024 | Complete | M.R. ELEC'L SERVICE LLC | General Wiring |
| 06/09/2023 | Complete | NASH ELECTRIC SERVICES IN | — |