← Back
Two family brick
189 GRAFTON STREET
BROOKLYN · Brownsville · BIN 3081538
💬 Discuss this project
1930Year Built
2Stories
B1Building Class
R6Zoning
2,080 sfGross Floor Area
2Units
14 Open Violations ▸FDNY Report ↗
Two family brick · Owner of record: 189 GRAFTON LLC · 4,866 sf lot · 0.43 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction53p · 1 filing · 20 docs
PenthouseUnder Construction47p · 1 filing · 20 docs
Floor 4Under Construction52p · 1 filing · 20 docs
Floor 3Under Construction52p · 1 filing · 20 docs
Floor 2Under Construction53p · 1 filing · 20 docs
Floor 1Under Construction53p · 1 filing · 20 docs
CellarUnder Construction54p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
1130 FTELEY AVE3208/27/2026
RELIABLE ENTERPRISES108/26/2026
ARKENSTONE BUILDERS103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/28/2024$999K—Private party → 189 GRAFTON LLC$480/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MCHENERY TESTING LAB108/04/2026
GERALD CALIENDO ARCHITECTS1112/10/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GERALD J. CALIENDO R.A., P.C.903/21/2026
GERALD J CALIENDO ARCHITECTS RA203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ARKENSTONE BUILDERS INCGeneral Contractor608/27/2026
RELIABLE ENTERPRISES INCGeneral Contractor108/26/2026
YAFE MEOD CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616512/10/2025
Building Lifecycle
All (97)Filed (12)Permit Issued (8)Violation (11)Objection (36)Special Inspection (30)
08/26/2026
Permit issued — General Construction
B01115741-I1-GC
08/04/2026
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01439300-I1
08/04/2026
Permit issued — Sidewalk Shed
B01439300-I1-SH
04/10/2026
Special inspection requirement — Post-installed Anchors
SHAHRIAR QUAYYUM
04/10/2026
Special inspection requirement — Subgrade Inspections
SHAHRIAR QUAYYUM
04/10/2026
Special inspection requirement — Structural Steel - High Strength Bolting
SHAHRIAR QUAYYUM
04/10/2026
Special inspection requirement — Concrete - Cast-In-Place
SHAHRIAR QUAYYUM
04/10/2026
Special inspection requirement — Masonry
SHAHRIAR QUAYYUM
04/10/2026
Special inspection requirement — Structural Cold-Formed Steel
SHAHRIAR QUAYYUM
04/10/2026
Special inspection requirement — Final
SHAHRIAR QUAYYUM
04/10/2026
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
SHAHRIAR QUAYYUM
04/10/2026
Special inspection requirement — Structural Steel - Details
SHAHRIAR QUAYYUM
04/03/2026
Permit issued — Support of Excavation
B01115741-S9-SE
03/30/2026
Special inspection requirement — Subgrade Inspections
03/30/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
03/30/2026
Special inspection requirement — Concrete - Cast-In-Place
03/30/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
03/30/2026
Special inspection requirement — Underpinning
01/22/2026
Violation issued (ECB, closed)
Construction
01/07/2026
Objection resolved — Addressed
12/16/2025
Objection raised — Scope
12/10/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCE.
B01115741-P1
12/08/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCE.
B01115741-P3
12/08/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
HEREWITH FILE ALTERATION IN ORDER TO ERECT TEMPORARY CONSTRUCTION PLYWOOD FENCE.
B01115741-P2
12/03/2025
Special inspection requirement — Subgrade Inspections
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Concrete - Cast-In-Place
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Masonry
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Post-installed Anchors
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Structural Cold-Formed Steel
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Structural Steel - Details
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Structural Steel - High Strength Bolting
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Final
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Final
SHAHRIAR QUAYYUM
12/03/2025
Special inspection requirement — Footing and Foundation
SHAHRIAR QUAYYUM
11/19/2025
Permit issued — Construction Fence
B01115741-S1-FN
10/29/2025
Permit issued — Structural
B01115741-S5-ST
10/01/2025
Permit issued — Support of Excavation
B01115741-S9-SE
10/01/2025
Permit issued — Foundation
B01115741-S8-FO-EA
08/26/2025
Objection resolved — Addressed
07/30/2025
Objection raised — Other
07/21/2025
Objection resolved — Addressed
07/16/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
06/25/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
SHAHRIAR QUAYYUM
06/25/2025
Special inspection requirement — HVAC-R and service water heating equipment
SHAHRIAR QUAYYUM
06/25/2025
Special inspection requirement — Shutoff dampers
SHAHRIAR QUAYYUM
06/25/2025
Special inspection requirement — HVAC-R and service water heating system controls
SHAHRIAR QUAYYUM
05/14/2025
Objection resolved — Addressed
05/14/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
04/24/2025
Objection resolved — Addressed
Latest 60 of 97 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedARKENSTONE BUILDERS INC08/26/2026
DOB NOWSidewalk ShedPermit IssuedRELIABLE ENTERPRISES INC08/04/2026
DOB NOWSupport of ExcavationPermit IssuedARKENSTONE BUILDERS INC04/03/2026
DOB NOWConstruction FencePermit IssuedARKENSTONE BUILDERS INC11/19/2025
DOB NOWStructuralPermit IssuedARKENSTONE BUILDERS INC10/29/2025
DOB NOWSupport of ExcavationPermit IssuedARKENSTONE BUILDERS INC10/01/2025
DOB NOWFoundationPermit IssuedARKENSTONE BUILDERS INC10/01/2025
DOB NOWConstruction FencePermit IssuedYAFE MEOD CORP11/18/2024
1 project · most recent 12/10/2025
Storm Water/Sanitary
FiledStatusContractorScope
12/10/2025——Storm, Water/Sanitary
1 project · most recent 08/03/2026
FiledStatusContractorScope
08/03/2026Permit IssuedRICHARD NEU—
1 project · most recent 12/10/2025
FiledStatusContractorScope
12/10/2025Permit IssuedARKENSTONE BUILDERS INC3 scope_items
2 projects · most recent 08/04/2026
Sidewalk Shed Fence
FiledStatusContractorScope
08/04/2026Permit IssuedRELIABLE ENTERPRISES INCSidewalk Shed
12/10/2025Permit IssuedARKENSTONE BUILDERS INCFence
▾Special Inspection Requirements (DOB NOW) — 49
DateRequirementInspectorRole
04/10/2026Post-installed AnchorsSHAHRIAR QUAYYUMspecial
04/10/2026Subgrade InspectionsSHAHRIAR QUAYYUMspecial
04/10/2026Structural Steel - High Strength BoltingSHAHRIAR QUAYYUMspecial
04/10/2026Concrete - Cast-In-PlaceSHAHRIAR QUAYYUMspecial
04/10/2026MasonrySHAHRIAR QUAYYUMspecial
04/10/2026Structural Cold-Formed SteelSHAHRIAR QUAYYUMspecial
04/10/2026FinalSHAHRIAR QUAYYUMprogress
04/10/2026Subsurface Conditions – Fill Placement & In-Place DensitySHAHRIAR QUAYYUMspecial
04/10/2026Structural Steel - DetailsSHAHRIAR QUAYYUMspecial
03/30/2026Subgrade Inspections—special
03/30/2026Structural Stability – Alterations of existing buildings—special
03/30/2026Concrete - Cast-In-Place—special
03/30/2026Subsurface Investigations (Borings/Test Pits)—special
03/30/2026Underpinning—special
12/03/2025Subgrade InspectionsSHAHRIAR QUAYYUMspecial
12/03/2025Concrete - Cast-In-PlaceSHAHRIAR QUAYYUMspecial
12/03/2025MasonrySHAHRIAR QUAYYUMspecial
12/03/2025Post-installed AnchorsSHAHRIAR QUAYYUMspecial
12/03/2025Structural Cold-Formed SteelSHAHRIAR QUAYYUMspecial
12/03/2025Structural Steel - DetailsSHAHRIAR QUAYYUMspecial
12/03/2025Structural Steel - High Strength BoltingSHAHRIAR QUAYYUMspecial
12/03/2025Subsurface Conditions – Fill Placement & In-Place DensitySHAHRIAR QUAYYUMspecial
12/03/2025FinalSHAHRIAR QUAYYUMprogress
12/03/2025FinalSHAHRIAR QUAYYUMprogress
12/03/2025Footing and FoundationSHAHRIAR QUAYYUMprogress
Latest 25 of 49.
▾Documents — 74 on file (BIS + DOB NOW)
▸Plans & Drawings12
▸DOB NOWPlans/Sketch12
08/19/2026B01115741-I1Request digital key ↗
08/19/2026B01115741-S9Request digital key ↗
08/19/2026B01115741-P3Request digital key ↗
Showing 3 of 12 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION2
08/16/2024322117589Open ↗
07/30/2024322117589Open ↗
▸Zoning, Tax Lot & Property Records7
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
08/14/2024322117589Open ↗
▸BISEASEMENT AND RESTRICTIVE DECLARATIONS - SUPPPORTING DOCUMENTATION1
08/05/2024322117589Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
08/14/2024322117589Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
08/14/2024322117589Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01115741-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B01115741-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01115741-I1Open ↗
▸Seals & Professional Certifications30
▸DOB NOWDPL-1: Design Professional Seal & Signature15
08/19/2026B01115741-S9Open ↗
08/19/2026B01115741-S8Open ↗
08/19/2026B01115741-S5Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
09/01/2026B01115741-S5Open ↗
08/27/2026B01115741-P3Open ↗
08/26/2026B01115741-S2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/01/2026B01115741-S4Open ↗
09/01/2026B01115741-S5Open ↗
08/26/2026B01115741-S2Open ↗
Showing 3 of 7 on file for this type
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/19/2026B01115741-I1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan2
08/23/2026B01115741-I1Open ↗
08/19/2026B01115741-I1Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form7
08/19/2026B01115741-I1Open ↗
08/13/2026B01115741-S8Open ↗
08/13/2026B01115741-S4Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Completion Form1
08/13/2026B01115741-I1Open ↗
▸Inspections & Test Reports2
▸DOB NOWSOIL REPORT2
08/19/2026B01115741-P3Open ↗
08/19/2026B01115741-S8Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
07/30/2024322117589Open ↗
▸Other Documents9
▸BISSupporting Document: Fee Exempt4
08/20/2024322117589Open ↗
08/05/2024322117589Open ↗
08/05/2024322117589Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAdjoining Owners Notification2
08/13/2026B01115741-S9Open ↗
08/13/2026B01115741-S8Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01115741-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/13/2026B01115741-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01115741-I1Open ↗