| Owner | Filings | Most Recent |
|---|---|---|
| 19 FILLMORE | 9 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| MCHENERY TESTING LAB | 1 | 04/02/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MANELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| ELITE BROWNSTONE RES INC | General Contractor | 1 | 04/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Permit Issued | ELITE BROWNSTONE RES INC | 04/03/2026 |
| BIS | SP | ISSUED | J. CAIAZZO PLBG & HTG CORP | 09/07/2022 |
| BIS | PL | ISSUED | J. CAIAZZO PLBG & HTG COR | 10/21/2021 |
| BIS | PL | ISSUED | J. CAIAZZO PLBG & HTG COR | 10/26/2020 |
| BIS | PL | ISSUED | J. CAIAZZO PLBG & HTG COR | 12/11/2019 |
| BIS | — | ISSUED | NACCARATO CONTRACTING INC | 12/06/2019 |
| BIS | — | ISSUED | NACCARATO CONTRACTING INC | 12/06/2019 |
| BIS | SP | ISSUED | TOMKAT PLUMBING HEATING LLC | 11/18/2019 |
| BIS | — | ISSUED | NACCARATO CONTRACTING INC | 12/05/2018 |
| BIS | — | ISSUED | NACCARATO CONTRACTING INC | 12/05/2018 |
| BIS | PL | ISSUED | J. CAIAZZO PLBG & HTG COR | 05/25/2018 |
| BIS | — | ISSUED | NACCARATO CONTRACTING INC | 05/03/2018 |
| BIS | — | ISSUED | NACCARATO CONTRACTING INC | 05/01/2018 |
| BIS | EQ | ISSUED | NACCARATO CONTRACTING INC | 04/27/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/29/2024 | Complete | EMPIRE STATE ELECTL CORP | General Wiring |
| 05/29/2018 | Complete | MANELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2026 | Permit Issued | ELITE BROWNSTONE RES INC | Scaffold |