← Back
Two stories - detached, small or mid-size
190-40 103 AVENUE
QUEENS · BIN 4232109
💬 Discuss this project
1920Year Built
2.5Stories
A1Building Class
R2Zoning
—Gross Floor Area
1Units
Two stories - detached, small or mid-size · 0.51 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
1 job · most recent 01/29/2024
FiledStatusContractorScope
01/29/2024CompleteISLAND ELECTRIC CORP—
Building Lifecycle
All (12)Filed (1)Permit Issued (1)Signed Off (1)Objection (4)Special Inspection (5)
12/03/2025
Signed off — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 42 Panels, 16.8 kW
Q00990576-I1
02/15/2024
Permit issued — Solar
Q00990576-I1-SL
02/07/2024
Objection resolved — Addressed
02/07/2024
Objection resolved — Addressed
02/01/2024
Objection raised — Other
02/01/2024
Objection raised — Scope
01/30/2024
Filed — Alteration
Installation of solar panels; Rooftop, Railed, Grid tied, 42 Panels, 16.8 kW
Q00990576-I1
01/15/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/15/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/15/2024
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/15/2024
Special inspection requirement — Final
Mina Makar
01/15/2024
Special inspection requirement — Air barrier - visual inspection
Mina Makar
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR101/30/2024
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281101/30/2024
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR02/15/2024
BISOTISSUEDPRO CUSTOM SOLAR LLC02/21/2024
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
01/15/2024Fire-Resistant Penetrations and JointsMina Makarspecial
01/15/2024Structural Stability – Alterations of existing buildingsMina Makarspecial
01/15/2024Energy Code Compliance InspectionsMina Makarprogress
01/15/2024FinalMina Makarprogress
01/15/2024Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 19 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/23/2026Q00990576-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
02/15/2024440816379Open ↗
▸BISWORK PERMIT APPLICATION1
02/21/2024440816379Open ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026Q00990576-I1Open ↗
08/24/2026Q00990576-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/15/2024440816379Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/15/2024440816379Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/15/2024440816379Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q00990576-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/24/2026Q00990576-I1Open ↗
▸Safety & Tenant Protection1
▸BISTPP1: TENANT PROTECTION PLAN1
02/21/2024440816379Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
02/15/2024440816379Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q00990576-I1Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
02/15/2024440816379Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
02/15/2024440816379Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
02/15/2024440816379Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q00990576-I1Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
02/15/2024440816379Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
02/15/2024440816379Open ↗