| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/10/2024 | Permit Issued | SUCCESS DEVELOPERS LLC | Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2024 | Signed-off | METFLOW FIRE CONTROL LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2024 | Permit Issued | SUCCESS DEVELOPERS LLC | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/10/2024 | Permit Issued | SUCCESS DEVELOPERS LLC | Earthwork |
| Firm | Filings | Most Recent |
|---|---|---|
| DIEGO AGUILERA ARCHITECTS P.C. | 2 | 07/10/2024 |
| A&D ENGINEERING, PLLC | 4 | 05/20/2024 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 4 | 09/20/2023 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| REGIONAL TESTING CORP. | 394 | 9 | 07/10/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | SUCCESS DEVELOPERS LLC | 03/14/2024 |
| DOB NOW | General Construction | Permit Issued | SUCCESS DEVELOPERS LLC | 02/27/2024 |
| DOB NOW | Sprinklers | Signed-off | METFLOW FIRE CONTROL LLC | 02/20/2024 |
| DOB NOW | Mechanical Systems | Signed-off | SUCCESS DEVELOPERS LLC | 01/10/2024 |
| DOB NOW | Support of Excavation | Signed-off | SUCCESS DEVELOPERS LLC | 12/14/2023 |
| DOB NOW | Plumbing | Signed-off | AB PLUMBING INC | 11/17/2023 |
| DOB NOW | Structural | Signed-off | SUCCESS DEVELOPERS LLC | 10/19/2023 |
| DOB NOW | Foundation | Signed-off | SUCCESS DEVELOPERS LLC | 10/19/2023 |
| DOB NOW | Support of Excavation | Signed-off | SUCCESS DEVELOPERS LLC | 10/18/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/24/2026 | Pass-Final Construction Permit Withdrawal | Pass | View ↗ |
| 12/18/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/05/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 06/03/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/10/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/15/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 01/19/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 01/09/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 12/05/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/03/2024 | Lighting in dwelling units | Paul Raymond | energy_progress |
| 09/03/2024 | Maintenance information | Paul Raymond | energy_progress |
| 09/03/2024 | Exterior Insulation and Finish Systems (EIFS) | Paul Raymond | special |
| 09/03/2024 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |
| 09/03/2024 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 09/03/2024 | Fire-Resistance Rated Construction | Paul Raymond | progress |
| 09/03/2024 | Air barrier - visual inspection | Paul Raymond | energy_progress |
| 09/03/2024 | Exterior lighting power | Paul Raymond | energy_progress |
| 09/03/2024 | Electrical motors and elevators | Paul Raymond | energy_progress |
| 09/03/2024 | Fenestration areas | Paul Raymond | energy_progress |
| 09/03/2024 | Interior lighting power | Paul Raymond | energy_progress |
| 09/03/2024 | Air barrier — testing | Paul Raymond | energy_progress |
| 09/03/2024 | Lighting controls | Paul Raymond | energy_progress |
| 09/03/2024 | Fenestration and door U-factor and product ratings | Paul Raymond | energy_progress |
| 09/03/2024 | Fenestration air leakage | Paul Raymond | energy_progress |
| 09/03/2024 | Protection of exposed foundation insulation | Paul Raymond | energy_progress |
| 09/03/2024 | Metering | Paul Raymond | energy_progress |
| 09/03/2024 | Insulation placement and R values | Paul Raymond | energy_progress |
| 07/09/2024 | Air barrier - visual inspection | Paul Raymond | energy_progress |
| 07/09/2024 | Exterior Insulation and Finish Systems (EIFS) | Paul Raymond | special |
| 07/09/2024 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |
| 07/09/2024 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 07/09/2024 | Fire-Resistance Rated Construction | Paul Raymond | progress |
| 07/09/2024 | Exterior lighting power | Paul Raymond | energy_progress |
| 07/09/2024 | Fenestration air leakage | Paul Raymond | energy_progress |