| Owner | Filings | Most Recent |
|---|---|---|
| 1929 84TH STREET | 21 | 07/08/2026 |
| HKS CONSTRUCTION | 5 | 07/08/2026 |
| PAUL TOTH EXCAVATING, INC. | 5 | 03/22/2026 |
| STELLAR CONTRACTING | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/28/2020 | $2.5M | — | 1929 84TH STREET LLC → Private party | $661/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BRICOLAGE DESIGNS | 2 | 08/15/2018 |
| ENTHINK ENGINEERS LLC | 1 | 02/15/2018 |
| WILLIAM MONTAGUE ENGINEER | 1 | 12/18/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| BRICOLAGE DESIGNS | 2 | 03/21/2026 |
| HAIDER ENGINEERING, P.E. | 1 | 03/21/2026 |
| HAIDER ENGINEERING P E | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| STELLAR CONTRACTING LLC | General Contractor | 6 | 07/08/2026 |
| BRICOLAGE DESIGNS | General Contractor | 2 | 03/22/2026 |
| PAUL TOTH EXCAVATION INC | General Contractor | 2 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| HKS CONSTRUCTION CORP | General Contractor | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | STELLAR CONTRACTING LLC | 03/02/2020 |
| DOB NOW | Curb Cut | Signed-off | STELLAR CONTRACTING LLC | 02/25/2020 |
| DOB NOW | Construction Fence | Signed-off | STELLAR CONTRACTING LLC | 08/22/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | HKS CONSTRUCTION CORP | 02/15/2018 |
| DOB NOW | Construction Fence | Signed-off | PAUL TOTH EXCAVATION INC | 01/12/2018 |
| BIS | OT | ISSUED | SUNRUN INSTALLATION SVC | 06/23/2021 |
| BIS | PL | ISSUED | A.G.M. P & H INC | 03/19/2019 |
| BIS | — | ISSUED | STELLAR CONTRACTING LLC | 08/23/2018 |
| BIS | OT | ISSUED | STELLAR CONTRACTING LLC | 06/27/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/06/2019 | Complete | AROUND ELECTRIC CORP. | General Wiring |
| 02/14/2018 | Complete | RICHARD NEU | — |