| Owner | Filings | Most Recent |
|---|---|---|
| CHOI | 11 | 09/13/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/30/2025 | $800K | — | Private party → Private party | $263/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MADRIAGA ENGINEERING P.C. | 5 | 08/15/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LEBANON CONSTRUCTION INC | General Contractor | 5 | 07/01/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 2 | 08/11/2026 |
| T&I CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| J&R DESIGN AND INSPECTION | 6637 | 5 | 08/15/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | AMERICAN STANDARD P&H CORORP. | 08/10/2026 |
| DOB NOW | General Construction | Permit Issued | LEBANON CONSTRUCTION INC | 06/29/2026 |
| DOB NOW | Structural | Permit Issued | T&I CONSTRUCTION INC | 04/14/2026 |
| DOB NOW | Plumbing | Permit Issued | AMERICAN STANDARD P&H CORORP. | 07/15/2025 |
| DOB NOW | General Construction | Permit Issued | LEBANON CONSTRUCTION INC | 07/01/2025 |
| DOB NOW | General Construction | Permit Issued | LEBANON CONSTRUCTION INC | 06/11/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/15/2026 | Permit Issued | AMERICAN STANDARD P&H COR | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2025 | Permit Issued | KJK ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/15/2026 | Permit Issued | AMERICAN STANDARD P&H COR | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/04/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/18/2026 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 08/18/2026 | Maintenance information | Robert Truskosky | energy_progress |
| 08/18/2026 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 08/18/2026 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 08/18/2026 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 08/07/2026 | HVAC-R and service water piping design and insulation | Robert Truskosky | energy_progress |
| 08/07/2026 | Maintenance information | Robert Truskosky | energy_progress |
| 08/07/2026 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 08/07/2026 | HVAC-R and service water heating system controls | Robert Truskosky | energy_progress |
| 08/07/2026 | HVAC-R and service water heating equipment | Robert Truskosky | energy_progress |
| 07/20/2026 | Structural Stability – Alterations of existing buildings | Robert Truskosky | special |
| 07/20/2026 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 07/20/2026 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 07/20/2026 | Fenestration areas | Robert Truskosky | energy_progress |
| 07/20/2026 | Insulation placement and R values | Robert Truskosky | energy_progress |
| 07/20/2026 | Fenestration air leakage | Robert Truskosky | energy_progress |
| 07/20/2026 | Air barrier - visual inspection | Robert Truskosky | energy_progress |
| 07/07/2026 | Structural Stability – Alterations of existing buildings | Robert Truskosky | special |
| 07/07/2026 | Fenestration areas | Robert Truskosky | energy_progress |
| 07/07/2026 | Insulation placement and R values | Robert Truskosky | energy_progress |
| 07/07/2026 | Air barrier - visual inspection | Robert Truskosky | energy_progress |
| 07/07/2026 | Energy Code Compliance Inspections | Robert Truskosky | progress |
| 07/07/2026 | Fire-Resistant Penetrations and Joints | Robert Truskosky | special |
| 07/07/2026 | Fenestration air leakage | Robert Truskosky | energy_progress |
| 03/04/2026 | Fire-Resistance Rated Construction | Robert Truskosky | progress |