| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/18/2026 | Permit Issued | RENEWAL CONSTRUCTION SERV | Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2026 | Signed-off | RUGOVA GROUP LLC | Gas, Storm, Water/Sanitary |
| 07/17/2025 | — | — | Storm |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/21/2026 | Permit Issued | LIT MODE ELECL CONTG INC | — |
| 05/21/2026 | Complete | ASCUATECH ELECTRICAL CORP | — |
| 02/11/2026 | Complete | RND ELECTRIC CORP | — |
| 11/20/2025 | Complete | LAURA ELEC'L LIGHTING & | — |
| 11/14/2025 | Permit Issued | HIGH QUALITY ELEC.OF NYC | — |
| 10/03/2024 | Permit Issued | ZIGGY'S ELECL CONTNG CORP | — |
| 04/22/2024 | Complete | ARCADIA ELECT'L CO. INC. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/17/2025 | Permit Issued | RENEWAL CONSTRUCTION SERV | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2026 | Permit Issued | P & K CONTRACTING INC | Scaffold |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/06/2025 | — | — | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| NW BRONX OZ HOUSING PRESERVATION EXPERIENCE LP | 6 | 07/08/2026 |
| NYCHA | 26 | 07/08/2026 |
| UNION HOUSING PRESERVATION | 14 | 04/09/2026 |
| NEW YORK CITY HOUSING AUTHORITY | 10 | 04/09/2026 |
| NYC HOUSING AUTHORITY | 3 | 03/22/2026 |
| NYCHA 99 | 1 | 03/22/2026 |
| GUARDSMAN ELEVATOR CO., INC. | 1 | 03/22/2026 |
| NYC HOUSING | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AUFGANG ARCHITECTS | 4 | 06/18/2026 |
| AK CONSULTING SERVICES, INC | 1 | 05/14/2026 |
| LORING CONSULTING ENGINEERS, INC. | 7 | 02/20/2026 |
| KZ ENGINEERING, P.C | 1 | 10/21/2025 |
| ROSENWASSER/GROSSMAN CONSULTING ENG | 3 | 09/13/2024 |
| PURCELL EVERETT ARCHITECTS, P.C | 3 | 08/02/2024 |
| JOEL PHAGOO P.E. PLLC | 3 | 07/31/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| PURCELL EVERETT ARCHITECTS | 12 | 03/21/2026 |
| W J PROFESSIONAL EXPEDITING | 20 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RAVEN CONSTRUCTION SERVIC | General Contractor | 9 | 03/21/2026 |
| RENEWAL CONSTRUCTION SERVICES | General Contractor | 9 | 07/08/2026 |
| ADAM'S EUROPEAN CONTRACTING | General Contractor | 6 | 07/08/2026 |
| VEMA GROUP LLC | General Contractor | 4 | 04/09/2026 |
| RUGOVA GROUP LLC | Plumbing | 2 | 06/28/2026 |
| P & K CONTRACTING INC | General Contractor | 1 | 07/08/2026 |
| ASCUATECH ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SANDEEP GUNNALA ENGINEERI | 8482 | 10 | 06/18/2026 |
| AK CONSULTING SERVICES, I | 6198 | 1 | 05/14/2026 |
| 20/20 INSPECTIONS INC | 1471 | 4 | 07/17/2025 |
| JOEL PHAGOO ,PE, PLLC | 2416 | 1 | 07/31/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | RENEWAL CONSTRUCTION SERVICES | 07/06/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | P & K CONTRACTING INC | 05/15/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | VEMA GROUP LLC | 02/19/2026 |
| DOB NOW | General Construction | Permit Issued | RENEWAL CONSTRUCTION SERV | 02/09/2026 |
| DOB NOW | General Construction | Permit Issued | RENEWAL CONSTRUCTION SERV | 02/09/2026 |
| DOB NOW | Structural | Permit Issued | RENEWAL CONSTRUCTION SERV | 02/09/2026 |
| DOB NOW | Structural | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 12/29/2025 |
| DOB NOW | General Construction | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 12/29/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | VEMA GROUP LLC | 10/22/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | VEMA GROUP LLC | 10/17/2025 |
| DOB NOW | General Construction | Permit Issued | VEMA GROUP LLC | 10/16/2025 |
| DOB NOW | Structural | Permit Issued | VEMA GROUP LLC | 10/10/2025 |
| DOB NOW | Structural | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 09/22/2025 |
| DOB NOW | Boiler Equipment | Signed-off | RUGOVA GROUP LLC | 07/22/2025 |
| DOB NOW | Plumbing | Signed-off | RUGOVA GROUP LLC | 07/22/2025 |
| DOB NOW | General Construction | Permit Issued | RENEWAL CONSTRUCTION SERV | 06/25/2025 |
| DOB NOW | Structural | Permit Issued | RENEWAL CONSTRUCTION SERV | 06/24/2025 |
| DOB NOW | General Construction | Permit Issued | RENEWAL CONSTRUCTION SERV | 06/11/2025 |
| DOB NOW | General Construction | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 10/04/2024 |
| DOB NOW | Structural | Permit Issued | ADAM'S EUROPEAN CONTRACTING | 10/03/2024 |
| DOB NOW | Supported Scaffold | Signed-off | RAVEN CONSTRUCTION SERVIC | 08/02/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | RAVEN CONSTRUCTION SERVIC | 05/03/2024 |
| DOB NOW | Construction Fence | Signed-off | RAVEN CONSTRUCTION SERVIC | 05/03/2024 |
| BIS | EQ | ISSUED | M.S.T GENERAL CONTRACTING | 06/22/2006 |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/26/2026 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 02/18/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/17/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/17/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/03/2026 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 02/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/16/2026 | Fenestration air leakage | Sandeep Gunnala | energy_progress |
| 06/16/2026 | Air barrier - visual inspection | Sandeep Gunnala | energy_progress |
| 06/16/2026 | Fenestration and door U-factor and product ratings | Sandeep Gunnala | energy_progress |
| 06/16/2026 | Energy Code Compliance Inspections | Sandeep Gunnala | progress |
| 06/16/2026 | Tenant Protection Plan Compliance | Sandeep Gunnala | special |
| 04/13/2026 | Post-installed Anchors | WALIUR RAHMAN | special |
| 02/20/2026 | Tenant Protection Plan Compliance | — | special |
| 02/20/2026 | HVAC-R and service water heating equipment | Sandeep Gunnala | energy_progress |
| 02/20/2026 | HVAC-R and service water heating system controls | Sandeep Gunnala | energy_progress |
| 02/20/2026 | Electrical motors and elevators | Sandeep Gunnala | energy_progress |
| 02/20/2026 | Final | Sandeep Gunnala | progress |
| 02/20/2026 | Mechanical Systems | Sandeep Gunnala | special |
| 02/20/2026 | Fire-Resistant Penetrations and Joints | Sandeep Gunnala | special |
| 02/20/2026 | HVAC-R and service water piping design and insulation | Sandeep Gunnala | energy_progress |
| 02/20/2026 | Shutoff dampers | Sandeep Gunnala | energy_progress |
| 12/17/2025 | Fire-Resistant Penetrations and Joints | Sandeep Gunnala | special |
| 12/17/2025 | Tenant Protection Plan Compliance | — | special |
| 12/17/2025 | HVAC-R and service water heating equipment | Sandeep Gunnala | energy_progress |
| 12/17/2025 | HVAC-R and service water heating system controls | Sandeep Gunnala | energy_progress |
| 12/17/2025 | HVAC-R and service water piping design and insulation | Sandeep Gunnala | energy_progress |
| 10/29/2025 | HVAC-R and service water piping design and insulation | Sandeep Gunnala | energy_progress |
| 10/29/2025 | Fire-Resistant Penetrations and Joints | Sandeep Gunnala | special |
| 10/29/2025 | Tenant Protection Plan Compliance | — | special |
| 10/29/2025 | HVAC-R and service water heating system controls | Sandeep Gunnala | energy_progress |
| 10/29/2025 | HVAC-R and service water heating equipment | Sandeep Gunnala | energy_progress |