| Owner | Filings | Most Recent |
|---|---|---|
| URBAN HEALTH PLAN | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GUTH DECONZO CONSULTING ENGINEERS, | 5 | 04/06/2026 |
| VINCENT J. LIOTTA P.E. | 2 | 11/12/2025 |
| BAZINI ENGINEERING, P.C. | 2 | 08/11/2025 |
| OLD STRUCTURES ENGINEERING | 1 | 06/14/2023 |
| ESKW/ARCHITECTS | 1 | 02/01/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM ZONING, LLC. | 12 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| 4TL CONSTRUCTION LLC | General Contractor | 19 | 07/08/2026 |
| PARKVIEW P&H INC | Plumbing | 3 | 07/08/2026 |
| ANTENUCCI MECHANICAL INC | Plumbing | 2 | 07/08/2026 |
| J & L SERVICE NYC INC | General Contractor | 1 | 07/08/2026 |
| DM80 SOLUTIONS LLC | General Contractor | 1 | 04/09/2026 |
| WILLIAM LAROSA | Electrical | 1 | 03/21/2026 |
| PINNACLE ENVIRONMENTAL CO | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MJ ENGINEERING & DESIGN | 5546 | 7 | 04/06/2026 |
| VINCENT J. LIOTTA P. E. | 1974 | 1 | 12/23/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | ANTENUCCI MECHANICAL INC | 05/01/2026 |
| DOB NOW | Plumbing | Permit Issued | ANTENUCCI MECHANICAL INC | 12/09/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | J & L SERVICE NYC INC | 12/09/2025 |
| DOB NOW | Boiler Equipment | Signed-off | FRANK MOORE | 10/28/2025 |
| DOB NOW | General Construction | Signed-off | DM80 SOLUTIONS LLC | 10/20/2025 |
| DOB NOW | Structural | Signed-off | 4TL CONSTRUCTION LLC | 10/16/2025 |
| DOB NOW | Mechanical Systems | Signed-off | 4TL CONSTRUCTION LLC | 10/16/2025 |
| DOB NOW | General Construction | Signed-off | 4TL CONSTRUCTION LLC | 10/16/2025 |
| DOB NOW | Structural | Signed-off | 4TL CONSTRUCTION LLC | 08/20/2025 |
| DOB NOW | Mechanical Systems | Signed-off | 4TL CONSTRUCTION LLC | 08/20/2025 |
| DOB NOW | General Construction | Signed-off | 4TL CONSTRUCTION LLC | 08/20/2025 |
| DOB NOW | Mechanical Systems | Signed-off | 4TL CONSTRUCTION LLC | 12/03/2024 |
| DOB NOW | Structural | Signed-off | 4TL CONSTRUCTION LLC | 12/03/2024 |
| DOB NOW | General Construction | Signed-off | 4TL CONSTRUCTION LLC | 12/03/2024 |
| DOB NOW | Structural | Signed-off | 4TL CONSTRUCTION LLC | 12/14/2023 |
| DOB NOW | Mechanical Systems | Signed-off | 4TL CONSTRUCTION LLC | 12/14/2023 |
| DOB NOW | General Construction | Signed-off | 4TL CONSTRUCTION LLC | 12/14/2023 |
| DOB NOW | Structural | Signed-off | 4TL CONSTRUCTION LLC | 09/11/2023 |
| DOB NOW | Plumbing | Signed-off | PARKVIEW P&H INC | 09/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | 4TL CONSTRUCTION LLC | 08/25/2023 |
| DOB NOW | General Construction | Signed-off | 4TL CONSTRUCTION LLC | 08/11/2023 |
| BIS | PL | ISSUED | J. CAIAZZO PLBG & HTG COR | 06/25/2012 |
| BIS | OT | ISSUED | CASTLE CONSTRUCTION & MAI | 06/21/2012 |
| BIS | MH | ISSUED | KONG YEUNG'S CORP. | 12/06/2007 |
| BIS | MH | ISSUED | KOON YEUNG'S CORP. | 04/08/2005 |
| BIS | OT | ISSUED | R.M. GENERAL CONTRACTING CROP | 10/11/2002 |
| BIS | OT | ISSUED | RM GENERAL CONTRACTING CORP | 09/06/2001 |
| BIS | OT | ISSUED | RM GENERAL CONTRACTING CORP | 09/06/2001 |
| BIS | EQ | ISSUED | ROCKLEDGE SCAFFOLD CORP | 12/07/1998 |
| BIS | — | ISSUED | R M GENERAL CONTRACTING CORP. | 12/01/1998 |
| BIS | OT | ISSUED | R M GENERAL CONTRACTING CORP | 09/16/1998 |
| BIS | — | ISSUED | R M GENERAL CONTRACTING CORP. | 09/16/1998 |
| BIS | OT | ISSUED | R.M. GEN CONTRACTING CORP | 02/14/1997 |
| BIS | PL | ISSUED | ROZZA PLUMBING HEATING CORP | 06/04/1996 |
| BIS | OT | ISSUED | R M GENERAL CONTRACTING CORP | 05/31/1996 |
| BIS | PL | ISSUED | MISA PLUMBING, LLC | 09/26/1995 |
| BIS | OT | ISSUED | FRANK J. MISA & SON, INC. | 09/26/1995 |
| BIS | FB | ISSUED | WAY-WOLFF ASSOCIATES | 02/10/1994 |
| BIS | MH | ISSUED | MARTACCK CORP. | 02/07/1994 |
| BIS | OT | ISSUED | MARTACK CORP. | 08/07/1992 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/06/2026 | Signed-off | GTL CONSTRUCTION LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric PEFY-P48NMAU-E4 48,000 BTU · Vrf Indoor ×9 PLFY-EP24NEMU-ER1 24,000 BTU · Vrf Indoor ×8 PUHY-P72TNU-A 72,000 BTU · Vrf Outdoor ×5 PUHY-P96TNU-A 96,000 BTU · Vrf Outdoor ×8 MXZ-SM60NAM-U1 60,000 BTU · Condensing Unit ×4 PEFY-P12NMAU-E4 12,000 BTU · Vrf Indoor ×4 PEFY-P36NMAU-E4 36,000 BTU · Vrf Indoor ×7 PVFY-P48NMAU-E1 48,000 BTU · Vrf Indoor ×1 PVFY-P48NAMU-E1 48,000 BTU · Vrf Indoor ×6 Carrier 48FCRN30H3M5-3UBC0 323,000 BTU · Rooftop Unit ×4 Ventilation N/A N/A 1,070 CFM · Erv ×12 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/12/2025 | Permit Issued | ANTENUCCI MECHANICAL INC | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2024 | Permit Issued | NYCOM ELECTRICAL CORP | General Wiring |
| 08/17/2023 | Permit Issued | SCHLESINGER ELECT'L CONTR | General Wiring |
| 06/09/2018 | Complete | LTC ELEC'L CONTR'G LLC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/09/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/26/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/24/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 02/12/2026 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 01/30/2026 | Administrative Rejection Boiler Certification | Administrative Rejection | View ↗ |
| 10/09/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/19/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/20/2026 | Mechanical Systems | Magdy Youssef | special |
| 04/20/2026 | Final | Magdy Youssef | progress |
| 04/20/2026 | Shutoff dampers | Magdy Youssef | energy_progress |
| 04/20/2026 | HVAC-R and service water heating equipment | Magdy Youssef | energy_progress |
| 04/20/2026 | Duct leakage testing, insulation and design | Magdy Youssef | energy_progress |
| 04/20/2026 | HVAC-R and service water heating system controls | Magdy Youssef | energy_progress |
| 04/20/2026 | HVAC-R and service water piping design and insulation | Magdy Youssef | energy_progress |
| 04/20/2026 | Maintenance information | Magdy Youssef | energy_progress |
| 04/06/2026 | Final | Magdy Youssef | progress |
| 04/06/2026 | Duct leakage testing, insulation and design | Magdy Youssef | energy_progress |
| 04/06/2026 | Shutoff dampers | Magdy Youssef | energy_progress |
| 04/06/2026 | Maintenance information | Magdy Youssef | energy_progress |
| 04/06/2026 | HVAC-R and service water heating system controls | Magdy Youssef | energy_progress |
| 04/06/2026 | HVAC-R and service water heating equipment | Magdy Youssef | energy_progress |
| 04/06/2026 | HVAC-R and service water piping design and insulation | Magdy Youssef | energy_progress |
| 04/06/2026 | Mechanical Systems | Magdy Youssef | special |
| 03/04/2026 | Final | Magdy Youssef | progress |
| 03/04/2026 | HVAC-R and service water heating equipment | Magdy Youssef | energy_progress |
| 03/04/2026 | HVAC-R and service water heating system controls | Magdy Youssef | energy_progress |
| 03/04/2026 | Shutoff dampers | Magdy Youssef | energy_progress |
| 03/04/2026 | HVAC-R and service water piping design and insulation | Magdy Youssef | energy_progress |
| 03/04/2026 | Maintenance information | Magdy Youssef | energy_progress |
| 03/04/2026 | Mechanical Systems | Magdy Youssef | special |
| 03/04/2026 | Duct leakage testing, insulation and design | Magdy Youssef | energy_progress |
| 07/11/2023 | Energy Code Compliance Inspections | Magdy Youssef | progress |