← Back
Community center
1930 RANDALL AVENUE
BRONX · BIN 2090508
💬 Discuss this project
1970Year Built
2Stories
P5Building Class
R5Zoning
44,657 sfGross Floor Area
1Units
15 Open Violations ▸
Community center · 165,109 sf lot · 0.27 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Permit Issued — active, not yet Signed-off
RoofUnder Construction8p · 2 filings · 20 docs
Floor 15p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
URBAN HEALTH PLAN103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM ZONING, LLC.1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
4TL CONSTRUCTION LLCGeneral Contractor1907/08/2026
PARKVIEW P&H INCPlumbing307/08/2026
ANTENUCCI MECHANICAL INCPlumbing207/08/2026
J & L SERVICE NYC INCGeneral Contractor107/08/2026
DM80 SOLUTIONS LLCGeneral Contractor104/09/2026
WILLIAM LAROSAElectrical103/21/2026
PINNACLE ENVIRONMENTAL COElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MJ ENGINEERING & DESIGN5546704/06/2026
VINCENT J. LIOTTA P. E.1974112/23/2024
Building Lifecycle
All (98)Filed (11)Permit Issued (21)Signed Off (6)Violation (19)Inspection (7)Objection (4)Special Inspection (30)
07/09/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/26/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/24/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
05/01/2026
Permit issued — Plumbing
X01154330-S1-PL
04/21/2026
Signed off — Alteration
MECHANICAL WORK AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X08048485-S1
04/20/2026
Special inspection requirement — Mechanical Systems
Magdy Youssef
04/20/2026
Special inspection requirement — Final
Magdy Youssef
04/20/2026
Special inspection requirement — Shutoff dampers
Magdy Youssef
04/20/2026
Special inspection requirement — HVAC-R and service water heating equipment
Magdy Youssef
04/20/2026
Special inspection requirement — Duct leakage testing, insulation and design
Magdy Youssef
04/20/2026
Special inspection requirement — HVAC-R and service water heating system controls
Magdy Youssef
04/20/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Magdy Youssef
04/20/2026
Special inspection requirement — Maintenance information
Magdy Youssef
04/09/2026
Signed off — Alteration
MECHANICAL WORK AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X08048485-S2
04/08/2026
Signed off — Alteration
MECHANICAL WORK AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X08048485-S3
04/08/2026
Signed off — Alteration
MECHANICAL WORK AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X08048485-I1
04/06/2026
Filed — Alteration
MECHANICAL WORK AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X08048485-P3
04/06/2026
Special inspection requirement — Final
Magdy Youssef
04/06/2026
Special inspection requirement — Duct leakage testing, insulation and design
Magdy Youssef
04/06/2026
Special inspection requirement — Shutoff dampers
Magdy Youssef
04/06/2026
Special inspection requirement — Maintenance information
Magdy Youssef
04/06/2026
Special inspection requirement — HVAC-R and service water heating system controls
Magdy Youssef
04/06/2026
Special inspection requirement — HVAC-R and service water heating equipment
Magdy Youssef
04/06/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Magdy Youssef
04/06/2026
Special inspection requirement — Mechanical Systems
Magdy Youssef
03/13/2026
Filed — Alteration
MECHANICAL WORK AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X08048485-P2
03/04/2026
Special inspection requirement — Final
Magdy Youssef
03/04/2026
Special inspection requirement — HVAC-R and service water heating equipment
Magdy Youssef
03/04/2026
Special inspection requirement — HVAC-R and service water heating system controls
Magdy Youssef
03/04/2026
Special inspection requirement — Shutoff dampers
Magdy Youssef
03/04/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Magdy Youssef
03/04/2026
Special inspection requirement — Maintenance information
Magdy Youssef
03/04/2026
Special inspection requirement — Mechanical Systems
Magdy Youssef
03/04/2026
Special inspection requirement — Duct leakage testing, insulation and design
Magdy Youssef
02/13/2026
Signed off — Alteration
DISCONNECT AND REMOVE EXISTING BOILER AND OIL BURNER AS PER PLANS. ABANDON EXISTING MASONRY CHIMNEY. REMOVE TWO (2) AIR HANDLERS, HOT WATER COILS AND ASSOCIATED DUCTWORK WITHIN THE BOILER ROOM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01178135-S1
02/12/2026
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
01/30/2026
Inspection — Administrative Rejection Boiler Certification
Administrative Rejection
View inspection ↗
01/23/2026
Filed — Alteration
MECHANICAL WORK AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
X08048485-P1
01/22/2026
Signed off — Alteration
DISCONNECT AND REMOVE EXISTING BOILER AND OIL BURNER AS PER PLANS. ABANDON EXISTING MASONRY CHIMNEY. REMOVE TWO (2) AIR HANDLERS, HOT WATER COILS AND ASSOCIATED DUCTWORK WITHIN THE BOILER ROOM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01178135-I1
12/09/2025
Permit issued — Plumbing
X01154330-S1-PL
12/09/2025
Permit issued — Mechanical Systems
X01154330-I1-MS
11/12/2025
Filed — Alteration
GAS PIPING IN ASSOCIATION WITH MECHANICAL FILING X01154330-S1.
X01154330-S1
10/28/2025
Permit issued — Boiler Equipment
X01178135-S1-BE
10/20/2025
Permit issued — General Construction
X01178135-I1-GC
10/16/2025
Permit issued — Structural
X08048485-S3-ST
10/16/2025
Permit issued — Mechanical Systems
X08048485-S1-MS
10/16/2025
Permit issued — General Construction
X08048485-I1-GC
08/20/2025
Permit issued — Structural
X08048485-S3-ST
08/20/2025
Permit issued — Mechanical Systems
X08048485-S1-MS
08/20/2025
Permit issued — General Construction
X08048485-I1-GC
08/11/2025
Filed — Alteration
DISCONNECT AND REMOVE EXISTING BOILER AND OIL BURNER AS PER PLANS. ABANDON EXISTING MASONRY CHIMNEY. REMOVE TWO (2) AIR HANDLERS, HOT WATER COILS AND ASSOCIATED DUCTWORK WITHIN THE BOILER ROOM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01178135-S1
08/11/2025
Filed — Alteration
DISCONNECT AND REMOVE EXISTING BOILER AND OIL BURNER AS PER PLANS. ABANDON EXISTING MASONRY CHIMNEY. REMOVE TWO (2) AIR HANDLERS, HOT WATER COILS AND ASSOCIATED DUCTWORK WITHIN THE BOILER ROOM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01178135-I1
12/23/2024
Filed — Alteration
GAS PIPING IN ASSOCIATION WITH MECHANICAL FILING X01154330-S1.
X01154330-I1
12/03/2024
Permit issued — Mechanical Systems
X08048485-S1-MS
12/03/2024
Permit issued — Structural
X08048485-S3-ST
12/03/2024
Permit issued — General Construction
X08048485-I1-GC
10/09/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/14/2023
Permit issued — Structural
X08048485-S3-ST
12/14/2023
Permit issued — Mechanical Systems
X08048485-S1-MS
12/14/2023
Permit issued — General Construction
X08048485-I1-GC
Latest 60 of 98 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedANTENUCCI MECHANICAL INC05/01/2026
DOB NOWPlumbingPermit IssuedANTENUCCI MECHANICAL INC12/09/2025
DOB NOWMechanical SystemsPermit IssuedJ & L SERVICE NYC INC12/09/2025
DOB NOWBoiler EquipmentSigned-offFRANK MOORE10/28/2025
DOB NOWGeneral ConstructionSigned-offDM80 SOLUTIONS LLC10/20/2025
DOB NOWStructuralSigned-off4TL CONSTRUCTION LLC10/16/2025
DOB NOWMechanical SystemsSigned-off4TL CONSTRUCTION LLC10/16/2025
DOB NOWGeneral ConstructionSigned-off4TL CONSTRUCTION LLC10/16/2025
DOB NOWStructuralSigned-off4TL CONSTRUCTION LLC08/20/2025
DOB NOWMechanical SystemsSigned-off4TL CONSTRUCTION LLC08/20/2025
DOB NOWGeneral ConstructionSigned-off4TL CONSTRUCTION LLC08/20/2025
DOB NOWMechanical SystemsSigned-off4TL CONSTRUCTION LLC12/03/2024
DOB NOWStructuralSigned-off4TL CONSTRUCTION LLC12/03/2024
DOB NOWGeneral ConstructionSigned-off4TL CONSTRUCTION LLC12/03/2024
DOB NOWStructuralSigned-off4TL CONSTRUCTION LLC12/14/2023
DOB NOWMechanical SystemsSigned-off4TL CONSTRUCTION LLC12/14/2023
DOB NOWGeneral ConstructionSigned-off4TL CONSTRUCTION LLC12/14/2023
DOB NOWStructuralSigned-off4TL CONSTRUCTION LLC09/11/2023
DOB NOWPlumbingSigned-offPARKVIEW P&H INC09/08/2023
DOB NOWMechanical SystemsSigned-off4TL CONSTRUCTION LLC08/25/2023
DOB NOWGeneral ConstructionSigned-off4TL CONSTRUCTION LLC08/11/2023
BISPLISSUEDJ. CAIAZZO PLBG & HTG COR06/25/2012
BISOTISSUEDCASTLE CONSTRUCTION & MAI06/21/2012
BISMHISSUEDKONG YEUNG'S CORP.12/06/2007
BISMHISSUEDKOON YEUNG'S CORP.04/08/2005
BISOTISSUEDR.M. GENERAL CONTRACTING CROP10/11/2002
BISOTISSUEDRM GENERAL CONTRACTING CORP09/06/2001
BISOTISSUEDRM GENERAL CONTRACTING CORP09/06/2001
BISEQISSUEDROCKLEDGE SCAFFOLD CORP12/07/1998
BIS—ISSUEDR M GENERAL CONTRACTING CORP.12/01/1998
BISOTISSUEDR M GENERAL CONTRACTING CORP09/16/1998
BIS—ISSUEDR M GENERAL CONTRACTING CORP.09/16/1998
BISOTISSUEDR.M. GEN CONTRACTING CORP02/14/1997
BISPLISSUEDROZZA PLUMBING HEATING CORP06/04/1996
BISOTISSUEDR M GENERAL CONTRACTING CORP05/31/1996
BISPLISSUEDMISA PLUMBING, LLC09/26/1995
BISOTISSUEDFRANK J. MISA & SON, INC.09/26/1995
BISFBISSUEDWAY-WOLFF ASSOCIATES02/10/1994
BISMHISSUEDMARTACCK CORP.02/07/1994
BISOTISSUEDMARTACK CORP.08/07/1992
1 project · most recent 04/06/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
04/06/2026Signed-offGTL CONSTRUCTION LLCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric PEFY-P48NMAU-E4 48,000 BTU · Vrf Indoor ×9
PLFY-EP24NEMU-ER1 24,000 BTU · Vrf Indoor ×8
PUHY-P72TNU-A 72,000 BTU · Vrf Outdoor ×5
PUHY-P96TNU-A 96,000 BTU · Vrf Outdoor ×8
MXZ-SM60NAM-U1 60,000 BTU · Condensing Unit ×4
PEFY-P12NMAU-E4 12,000 BTU · Vrf Indoor ×4
PEFY-P36NMAU-E4 36,000 BTU · Vrf Indoor ×7
PVFY-P48NMAU-E1 48,000 BTU · Vrf Indoor ×1
PVFY-P48NAMU-E1 48,000 BTU · Vrf Indoor ×6
Carrier 48FCRN30H3M5-3UBC0 323,000 BTU · Rooftop Unit ×4
Ventilation
N/A N/A 1,070 CFM · Erv ×12
1 project · most recent 11/12/2025
Gas
FiledStatusContractorScope
11/12/2025Permit IssuedANTENUCCI MECHANICAL INCGas
3 projects · most recent 11/01/2024
General Wiring
FiledStatusContractorScope
11/01/2024Permit IssuedNYCOM ELECTRICAL CORPGeneral Wiring
08/17/2023Permit IssuedSCHLESINGER ELECT'L CONTRGeneral Wiring
06/09/2018CompleteLTC ELEC'L CONTR'G LLCGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
07/09/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/26/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/24/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
02/12/2026Pass-Final Boiler Equipment InspectionPassView ↗
01/30/2026Administrative Rejection Boiler CertificationAdministrative RejectionView ↗
10/09/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/19/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 40
DateRequirementInspectorRole
04/20/2026Mechanical SystemsMagdy Youssefspecial
04/20/2026FinalMagdy Youssefprogress
04/20/2026Shutoff dampersMagdy Youssefenergy_progress
04/20/2026HVAC-R and service water heating equipmentMagdy Youssefenergy_progress
04/20/2026Duct leakage testing, insulation and designMagdy Youssefenergy_progress
04/20/2026HVAC-R and service water heating system controlsMagdy Youssefenergy_progress
04/20/2026HVAC-R and service water piping design and insulationMagdy Youssefenergy_progress
04/20/2026Maintenance informationMagdy Youssefenergy_progress
04/06/2026FinalMagdy Youssefprogress
04/06/2026Duct leakage testing, insulation and designMagdy Youssefenergy_progress
04/06/2026Shutoff dampersMagdy Youssefenergy_progress
04/06/2026Maintenance informationMagdy Youssefenergy_progress
04/06/2026HVAC-R and service water heating system controlsMagdy Youssefenergy_progress
04/06/2026HVAC-R and service water heating equipmentMagdy Youssefenergy_progress
04/06/2026HVAC-R and service water piping design and insulationMagdy Youssefenergy_progress
04/06/2026Mechanical SystemsMagdy Youssefspecial
03/04/2026FinalMagdy Youssefprogress
03/04/2026HVAC-R and service water heating equipmentMagdy Youssefenergy_progress
03/04/2026HVAC-R and service water heating system controlsMagdy Youssefenergy_progress
03/04/2026Shutoff dampersMagdy Youssefenergy_progress
03/04/2026HVAC-R and service water piping design and insulationMagdy Youssefenergy_progress
03/04/2026Maintenance informationMagdy Youssefenergy_progress
03/04/2026Mechanical SystemsMagdy Youssefspecial
03/04/2026Duct leakage testing, insulation and designMagdy Youssefenergy_progress
07/11/2023Energy Code Compliance InspectionsMagdy Youssefprogress
Latest 25 of 40.
▾Documents — 108 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch11
08/18/2026X01178135-I1Request digital key ↗
08/18/2026X01178135-S1Request digital key ↗
08/17/2026X01154330-S1Request digital key ↗
Showing 3 of 11 on file for this type
▸Applications & Permits15
▸BISPLAN / WORK APPROVAL APPLICATION12
02/17/2026220696209Open ↗
09/18/2025220704156Open ↗
09/17/2025220704156Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION3
06/27/2012220153205Open ↗
06/21/2012220153205Open ↗
12/06/2007210025088Open ↗
▸Seals & Professional Certifications34
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/17/2026X08048485-P3Open ↗
08/13/2026X08048485-I1Open ↗
08/13/2026X01154330-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/01/2026X08048485-S2Open ↗
08/27/2026X08048485-I1Open ↗
08/27/2026X08048485-I1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
04/03/2019220696209Open ↗
04/03/2019220696209Open ↗
04/03/2019220696209Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/01/2026X08048485-S2Open ↗
08/27/2026X08048485-I1Open ↗
08/24/2026X08048485-P3Open ↗
Showing 3 of 5 on file for this type
▸BISPC FULL REPORT1
12/04/2007210025088Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
12/04/2007210025088Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
12/04/2007210025088Open ↗
▸Trade Schedules & Equipment4
▸BISSCHEDULE B - PLUMBING1
05/10/2012220153205Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
04/03/2019220696209Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
01/31/2008210025088Open ↗
▸BISEQUIPMENT USE PERMITS1
01/31/2008210025088Open ↗
▸Environmental & Asbestos9
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form6
08/13/2026X08048485-S3Open ↗
08/13/2026X08048485-S2Open ↗
08/13/2026X01178135-S1Open ↗
Showing 3 of 6 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
12/04/2007210025088Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
02/08/2013220251073Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026X01154330-S1Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
04/03/2019220696209Open ↗
04/03/2019220696209Open ↗
▸Approvals, Objections & Sign-offs20
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter11
08/17/2026X08048485-P3Open ↗
08/13/2026X08048485-S2Open ↗
08/13/2026X08048485-P1Open ↗
Showing 3 of 11 on file for this type
▸BISADMINISTRATIVE OBJECTIONS4
02/08/2013220251073Open ↗
04/28/2012220153205Open ↗
12/04/2007210025088Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
05/23/2019220704156Open ↗
04/03/2019220696209Open ↗
06/14/2012220153205Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
01/31/2008210025088Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
06/14/2012220153205Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT7
05/23/2019220704156Open ↗
04/03/2019220696209Open ↗
04/03/2019220696209Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms6
▸BISEFILING COVER SHEET6
05/23/2019220704156Open ↗
04/03/2019220696209Open ↗
04/03/2019220696209Open ↗
Showing 3 of 6 on file for this type