| Owner | Filings | Most Recent |
|---|---|---|
| 3861 REALTY | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/11/2023 | $657K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| EDWARD LUI ARCHITECT PLLC | 10 | 08/28/2025 |
| SYNERGIC DESIGN ARCHITECTS | 1 | 08/15/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| EXCELLENT METROPOLITAN | General Contractor | 7 | 07/08/2026 |
| TLS CONSTRUCTION GROUP I* | General Contractor | 4 | 04/08/2026 |
| KJK ELECTRIC INC | Electrical | 2 | 03/22/2026 |
| CROWN PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| ACCORD POWER INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| G ENGINEERING PC | 7778 | 8 | 08/28/2025 |
| TRIANGLE INSPECTION & TES | 7495 | 4 | 01/22/2025 |
| SYNERGIC DESIGN LLC | 8561 | 1 | 08/15/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | EXCELLENT METROPOLITAN | 03/03/2025 |
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 09/04/2024 |
| DOB NOW | Plumbing | Signed-off | CROWN PLUMBING INC | 08/12/2024 |
| DOB NOW | Earth Work | Permit Issued | EXCELLENT METROPOLITAN | 08/02/2024 |
| DOB NOW | Construction Fence | Signed-off | EXCELLENT METROPOLITAN | 08/01/2024 |
| DOB NOW | Plumbing | Signed-off | CROWN PLUMBING INC | 04/12/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | TLS CONSTRUCTION GROUP I* | 11/30/2023 |
| DOB NOW | Construction Fence | Signed-off | TLS CONSTRUCTION GROUP I* | 11/28/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/28/2025 | Signed-off | EXCELLENT METROPOLITAN | Air Conditioning Systems, Heating and Air Conditioning Systems, Ventilation Systems | Cooling Goodman GOODMAN GSX1604481F 45,500 BTU · Condensing Unit ×2 Heat / Cool Mitsubishi Electric MXZ-3C36NA4 36,000 BTU · Split System ×1 MXZ-4C30NA4 30,000 BTU · Split System ×1 MXZ-3C30NA4 30,000 BTU · Split System ×2 MXZ-4C36NA4 36,000 BTU · Split System ×2 MUZ-HM12NA 12,000 BTU · Split System ×4 MXZ-3C24NA2 24,000 BTU · Split System ×1 Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/28/2025 | — | — | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/28/2025 | Signed-off | CROWN PLUMBING INC | Gas, Plumbing-Sprinkler, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/30/2024 | Complete | KJK ELECTRIC INC | General Wiring |
| 09/03/2024 | Complete | POWER SURGE ELECTRIC, INC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/28/2025 | Signed-off | EXCELLENT METROPOLITAN | Steel, Concrete, Masonry, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/28/2025 | Signed-off | EXCELLENT METROPOLITAN | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/10/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 03/12/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/10/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 12/12/2024 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 09/13/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/16/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/10/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/28/2025 | Structural Wood Frame | XIONGCAI GU | progress |
| 08/28/2025 | Masonry | XIONGCAI GU | special |
| 08/28/2025 | Mechanical Systems | XIONGCAI GU | special |
| 08/28/2025 | Structural Steel - Details | XIONGCAI GU | special |
| 08/28/2025 | Structural Steel - High Strength Bolting | XIONGCAI GU | special |
| 08/28/2025 | Structural Steel - Welding | XIONGCAI GU | special |
| 08/28/2025 | Subgrade Inspections | XIONGCAI GU | special |
| 08/28/2025 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 08/28/2025 | Energy Code Compliance Inspections | XIONGCAI GU | progress |
| 08/28/2025 | Final | SAAD-ELDIN ELBEDWIHY | progress |
| 08/28/2025 | Fire-Resistance Rated Construction | XIONGCAI GU | progress |
| 08/28/2025 | Footing and Foundation | XIONGCAI GU | progress |
| 08/28/2025 | Duct leakage testing, insulation and design | XIONGCAI GU | energy_progress |
| 08/28/2025 | HVAC-R and service water heating equipment | XIONGCAI GU | energy_progress |
| 08/28/2025 | Permanent certificate | XIONGCAI GU | energy_progress |
| 08/28/2025 | HVAC-R and service water piping design and insulation | XIONGCAI GU | energy_progress |
| 08/28/2025 | Interior lighting power | XIONGCAI GU | energy_progress |
| 08/28/2025 | Insulation placement and R values | XIONGCAI GU | energy_progress |
| 08/28/2025 | HVAC-R and service water heating system controls | XIONGCAI GU | energy_progress |
| 08/28/2025 | Fenestration air leakage | XIONGCAI GU | energy_progress |
| 08/28/2025 | Electric vehicle service equipment requirements | XIONGCAI GU | energy_progress |
| 08/28/2025 | Air barrier — testing | XIONGCAI GU | energy_progress |
| 08/28/2025 | Air barrier - visual inspection | XIONGCAI GU | energy_progress |
| 08/28/2025 | Metering | XIONGCAI GU | energy_progress |
| 08/28/2025 | Fenestration and door U-factor and product ratings | XIONGCAI GU | energy_progress |