| Owner | Filings | Most Recent |
|---|---|---|
| OWNERS REP | 8 | 07/08/2026 |
| LINDSAY PARK HGS CORP | 1 | 03/22/2026 |
| UNIQUE DEVELOPERS | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/19/2016 | $4.0M | — | 52 BUILDING CO., LLC → 194-196 FREEMAN LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| BAILEYS ENGINEERING PC | 2 | 02/01/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 13 | 07/08/2026 |
| UNIQUE DEVELOPERS HOLDING | General Contractor | 3 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 2 | 03/22/2026 |
| FLANDER JULIEN P E | General Contractor | 1 | 03/22/2026 |
| PRIME PIPING HEATING IN | Plumbing | 1 | 03/22/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/12/2018 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/09/2018 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 02/02/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 11/29/2017 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 11/11/2017 |
| BIS | EQ | ISSUED | PILKU CONSTRUCTION SERVIC | 08/07/2017 |
| BIS | EQ | ISSUED | PILKU CONSTRUCTION SERVIC | 08/27/2016 |
| BIS | PL | ISSUED | SCHULTZ & SHAPIRO CORP | 11/18/1991 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/29/2018 | Complete | HIGH STANDARD ELECTRIC | General Wiring |
| 12/20/2017 | Complete | TUXEDO ELEC'L CONTR'G INC | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/30/2017 | Final | PAUL BAILEY | progress |