← Back
Miscellaneous one family
1943 TROY AVENUE
BROOKLYN · BIN 3217428
💬 Discuss this project
1930Year Built
2Stories
A9Building Class
R4Zoning
1,280 sfGross Floor Area
1Units
1 Open Violation ▸FDNY Report ↗
Miscellaneous one family · 2,500 sf lot · 0.51 FAR built · Flood zone X
Locations of Work
General
Roof1p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC107/15/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOLAR CONTRACTING LLCGeneral Contractor104/09/2026
TOWER BUIDING GROUP INCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854107/15/2025
Building Lifecycle
All (11)Filed (1)Permit Issued (2)Signed Off (1)Violation (2)Special Inspection (5)
12/29/2025
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM.ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THENYC DEPARTMENT OF BUILDINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B01255857-I1
09/19/2025
Permit issued — Solar
B01255857-I1-SL
08/12/2025
Permit issued — Solar
B01255857-I1-SL
07/15/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM.ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THENYC DEPARTMENT OF BUILDINGS. NO CHANGE TO USE, EGRESS OR OCCUPANCY.
B01255857-I1
07/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
07/15/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
07/15/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
07/15/2025
Special inspection requirement — Final
TOM PETERSEN
07/15/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
02/10/2009
Violation issued (HPD, open)
I
02/03/2009
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offSOLAR CONTRACTING LLC09/19/2025
DOB NOWSolarSigned-offTOWER BUIDING GROUP INC08/12/2025
1 project · most recent 07/14/2025
FiledStatusContractorScope
07/14/2025CompleteVILLAGE ELECTL CONTRS INC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
07/15/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
07/15/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
07/15/2025Energy Code Compliance InspectionsTOM PETERSENprogress
07/15/2025FinalTOM PETERSENprogress
07/15/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/21/2026B01255857-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
09/27/2026B01255857-I1Open ↗
09/27/2026B01255857-I1Open ↗
09/27/2026B01255857-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/27/2026B01255857-I1Open ↗
09/27/2026B01255857-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B01255857-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B01255857-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01255857-I1Open ↗