| Owner | Filings | Most Recent |
|---|---|---|
| HECAN CONSTRUCTION | 15 | 04/09/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/19/2025 | $1.3M | — | Private party → Private party | $697/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LU ENGINEERING SERVICE PC | 4 | 07/03/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| H Z BUILDING NY | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| TRI STATE PLBG & HTG INC | Plumbing | 3 | 07/08/2026 |
| GOODALL ELECTRIC CORP | Electrical | 2 | 03/22/2026 |
| HECAN CONSTRUCTION CORP | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LU ENGINEERING SERVICE PC | 6575 | 4 | 07/03/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 10/01/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 09/08/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 05/22/2025 |
| DOB NOW | Mechanical Systems | Signed-off | HECAN CONSTRUCTION CORP | 05/21/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/16/2025 | Complete | GOODALL ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/21/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/14/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 11/12/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/11/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/11/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/26/2025 | HVAC-R and service water heating equipment | DONGSHENG LU | energy_progress |
| 08/26/2025 | Interior lighting power | DONGSHENG LU | energy_progress |
| 08/26/2025 | HVAC-R and service water piping design and insulation | DONGSHENG LU | energy_progress |
| 08/26/2025 | Fenestration and door U-factor and product ratings | DONGSHENG LU | energy_progress |
| 08/26/2025 | Fenestration areas | DONGSHENG LU | energy_progress |
| 08/26/2025 | Insulation placement and R values | DONGSHENG LU | energy_progress |
| 08/26/2025 | HVAC-R and service water heating system controls | DONGSHENG LU | energy_progress |
| 08/26/2025 | Air barrier - visual inspection | DONGSHENG LU | energy_progress |
| 08/26/2025 | Fenestration air leakage | DONGSHENG LU | energy_progress |
| 08/26/2025 | Structural Stability – Alterations of existing buildings | DONGSHENG LU | special |
| 08/26/2025 | Concrete - Cast-In-Place | DONGSHENG LU | special |
| 08/26/2025 | Mechanical Systems | DONGSHENG LU | special |
| 08/26/2025 | Fire-Resistant Penetrations and Joints | DONGSHENG LU | special |
| 08/26/2025 | Energy Code Compliance Inspections | DONGSHENG LU | progress |
| 08/26/2025 | Final | Fran Huang | progress |
| 08/26/2025 | Fire-Resistance Rated Construction | DONGSHENG LU | progress |
| 06/27/2025 | Concrete - Cast-In-Place | DONGSHENG LU | special |
| 06/27/2025 | Fire-Resistant Penetrations and Joints | DONGSHENG LU | special |
| 06/27/2025 | Mechanical Systems | DONGSHENG LU | special |
| 06/27/2025 | Structural Stability – Alterations of existing buildings | DONGSHENG LU | special |
| 06/27/2025 | Energy Code Compliance Inspections | DONGSHENG LU | progress |
| 06/27/2025 | Final | Fran Huang | progress |
| 06/27/2025 | Fire-Resistance Rated Construction | DONGSHENG LU | progress |
| 06/27/2025 | Air barrier - visual inspection | DONGSHENG LU | energy_progress |
| 06/27/2025 | Fenestration and door U-factor and product ratings | DONGSHENG LU | energy_progress |