← Back
Five to six families
195 HURON STREET
BROOKLYN · BIN 3064204
💬 Discuss this project
1931Year Built
3Stories
C2Building Class
R6BZoning
4,000 sfGross Floor Area
5Units
Rent Stabilized17 Open Violations 15 unresolved · 2 paperwork only ▸FDNY Report ↗
Five to six families · Owner of record: 195 HURON CAPITAL LLC · 2,500 sf lot · 1.6 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction59p · 1 filing · 20 docs
PenthouseUnder Construction30p · 1 filing · 20 docs
Floor 4Under Construction56p · 1 filing · 20 docs
Floor 3Under Construction60p · 1 filing · 20 docs
Floor 2Under Construction56p · 1 filing · 20 docs
Floor 1Under Construction47p · 1 filing · 20 docs
CellarUnder Construction60p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
RAMTOM4209/23/2026
NEW AMERICAN CONSTRUCTION INC707/08/2026
195 HURON CAPITAL LLC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/30/2024$2.1M—— → —$525/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMB BUILDING CONSULTING2603/21/2026
SNR EXPEDITING DESIGN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
GREENWOOD MONITORING LLCGeneral Contractor1009/23/2026
NEW AMERICAN CONSTRUCTION INCGeneral Contractor207/08/2026
PLBG P & H INCPlumbing107/08/2026
QMB PLUMBING & HEATING INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161208/07/2026
Building Lifecycle
All (164)Filed (16)Permit Issued (14)Violation (27)Inspection (12)Objection (65)Special Inspection (30)
09/22/2026
Permit issued — Mechanical Systems
B01175087-S1-MS
09/22/2026
Permit issued — Structural
B01175087-S3-ST
09/22/2026
Permit issued — Support of Excavation
B01175087-S5-SE
09/10/2026
Violation issued (ECB, open)
Construction
09/09/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/27/2026
Objection resolved — Addressed
08/19/2026
Objection raised — Scope
08/07/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
SOE design for 4-story building filed in conjunction with GC # B01175087-I1.
B01175087-P5
08/07/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
08/03/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/17/2026
Permit issued — General Construction
B01175087-I1-GC
07/01/2026
Violation issued (ECB, open)
Site Safety
07/01/2026
Violation issued (ECB, open)
Unknown
05/05/2026
Violation issued (HPD, open)
A
04/15/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/13/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
04/10/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
04/10/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/07/2026
Inspection — Pass-Final SP - Up to 3 Requested Floors
Pass
View inspection ↗
04/03/2026
Permit issued — Sprinklers
B85685559-S2-PL
03/31/2026
Permit issued — Plumbing
B01175087-S2-PL
03/12/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
03/12/2026
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
03/12/2026
Special inspection requirement — Structural Steel - High Strength Bolting
SHAHRIAR QUAYYUM
03/12/2026
Special inspection requirement — Structural Steel - Welding
SHAHRIAR QUAYYUM
03/12/2026
Special inspection requirement — Masonry
SHAHRIAR QUAYYUM
03/12/2026
Special inspection requirement — Structural Steel - Details
SHAHRIAR QUAYYUM
03/12/2026
Special inspection requirement — Final
SHAHRIAR QUAYYUM
03/12/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
SHAHRIAR QUAYYUM
03/11/2026
Objection raised — Structural
02/28/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
SOE design for 4-story building filed in conjunction with GC # B01175087-I1.
B01175087-P4
02/28/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
SOE design for 4-story building filed in conjunction with GC # B01175087-I1.
B01175087-P3
02/26/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Subgrade Inspections
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Structural Steel - Welding
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Final
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Structural Steel - Details
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Final
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Concrete - Cast-In-Place
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Masonry
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
02/26/2026
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Footing and Foundation
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Structural Steel - High Strength Bolting
SHAHRIAR QUAYYUM
02/26/2026
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
12/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
12/17/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
SHAHRIAR QUAYYUM
12/17/2025
Special inspection requirement — Subgrade Inspections
SHAHRIAR QUAYYUM
12/17/2025
Special inspection requirement — Energy Code Compliance Inspections
SHAHRIAR QUAYYUM
12/17/2025
Special inspection requirement — Concrete - Cast-In-Place
SHAHRIAR QUAYYUM
12/09/2025
Objection resolved — Addressed
11/28/2025
Objection raised — Scope
11/21/2025
Permit issued — Sidewalk Shed
B01321821-I1-SH
11/21/2025
Permit issued — Supported Scaffold
B01321825-I1-SF
11/20/2025
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01321821-I1
11/20/2025
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B01321825-I1
Latest 60 of 164 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsPermit IssuedGREENWOOD MONITORING LLC09/22/2026
DOB NOWStructuralPermit IssuedGREENWOOD MONITORING LLC09/22/2026
DOB NOWSupport of ExcavationPermit IssuedGREENWOOD MONITORING LLC09/22/2026
DOB NOWGeneral ConstructionPermit IssuedGREENWOOD MONITORING LLC07/17/2026
DOB NOWSprinklersSigned-offQMB PLUMBING & HEATING INC04/03/2026
DOB NOWPlumbingPermit IssuedPLBG P & H INC03/31/2026
DOB NOWSidewalk ShedPermit IssuedNEW AMERICAN CONSTRUCTION11/21/2025
DOB NOWSupported ScaffoldPermit IssuedNEW AMERICAN CONSTRUCTION11/21/2025
DOB NOWMechanical SystemsPermit IssuedGREENWOOD MONITORING LLC10/14/2025
DOB NOWGeneral ConstructionPermit IssuedGREENWOOD MONITORING LLC10/10/2025
DOB NOWStructuralPermit IssuedGREENWOOD MONITORING LLC10/10/2025
DOB NOWSupport of ExcavationPermit IssuedGREENWOOD MONITORING LLC10/10/2025
DOB NOWFoundationPermit IssuedGREENWOOD MONITORING LLC10/10/2025
DOB NOWConstruction FencePermit IssuedGREENWOOD MONITORING LLC10/08/2025
BISOTISSUEDA-1 AMERICAN ROOFING & CH11/08/2010
BISPLISSUEDJODOM MECHANICAL, INC06/15/2009
BISPLISSUEDJODOM MECHANICAL, INC03/06/2008
BISOTISSUEDA G CONSTRUCTION02/28/2008
BISOTRE-ISSUEDR P S CONST INC10/07/2005
1 project · most recent 08/07/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
08/07/2026Permit IssuedGREENWOOD MONITORING LLCHeating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Cooper & Hunter CH-HYP36MSPH230VO 36,000 BTU · Condensing Unit ×6
CH-HYP28MSPH230VO 28,000 BTU · Condensing Unit ×2
CH-HYP48MSPH230VO 49,000 BTU · Condensing Unit ×1
Ventilation
Greenheck SP-B90 100 CFM · Exhaust Fan ×16
2 projects · most recent 11/20/2025
General Wiring
FiledStatusContractorScope
11/20/2025Permit IssuedRICHARD NEU—
11/20/2025Permit IssuedSAFEWAY CONSTRUCTION, INCGeneral Wiring
2 projects · most recent 08/07/2026
Steel Masonry
FiledStatusContractorScope
08/07/2026Permit IssuedGREENWOOD MONITORING LLCSteel, Masonry
10/01/2025——3 scope_items
3 projects · most recent 08/07/2026
Fence Scaffold Sidewalk Shed
FiledStatusContractorScope
08/07/2026Permit IssuedGREENWOOD MONITORING LLCFence
11/20/2025Permit IssuedNEW AMERICAN CONSTRUCTIONScaffold
11/20/2025Permit IssuedNEW AMERICAN CONSTRUCTIONSidewalk Shed
▾Field Inspections (DOB CAP) — 12
DateTypeResultReport
09/09/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/07/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/03/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/15/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
04/13/2026Pass-Final PL - UndergroundPassView ↗
04/10/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
04/10/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/07/2026Pass-Final SP - Up to 3 Requested FloorsPassView ↗
05/28/2025Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
05/28/2025Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments)CertifiedView ↗
03/06/2025Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
03/06/2025Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 81
DateRequirementInspectorRole
03/12/2026FinalSHAHRIAR QUAYYUMprogress
03/12/2026Structural Stability – Alterations of existing buildingsSHAHRIAR QUAYYUMspecial
03/12/2026MasonrySHAHRIAR QUAYYUMspecial
03/12/2026Structural Steel - High Strength BoltingSHAHRIAR QUAYYUMspecial
03/12/2026Structural Steel - DetailsSHAHRIAR QUAYYUMspecial
03/12/2026Structural Steel - WeldingSHAHRIAR QUAYYUMspecial
03/12/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
03/12/2026Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
02/26/2026Concrete - Cast-In-PlaceSHAHRIAR QUAYYUMspecial
02/26/2026Excavations - Sheeting, Shoring, and BracingSHAHRIAR QUAYYUMspecial
02/26/2026Structural Stability – Alterations of existing buildings—special
02/26/2026Subgrade InspectionsSHAHRIAR QUAYYUMspecial
02/26/2026Subsurface Investigations (Borings/Test Pits)SHAHRIAR QUAYYUMspecial
02/26/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
02/26/2026FinalSHAHRIAR QUAYYUMprogress
02/26/2026Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
02/26/2026Footing and FoundationSHAHRIAR QUAYYUMprogress
02/26/2026Structural Stability – Alterations of existing buildingsSHAHRIAR QUAYYUMspecial
02/26/2026Structural Steel - DetailsSHAHRIAR QUAYYUMspecial
02/26/2026Structural Steel - High Strength BoltingSHAHRIAR QUAYYUMspecial
02/26/2026Structural Steel - WeldingSHAHRIAR QUAYYUMspecial
02/26/2026Energy Code Compliance InspectionsSHAHRIAR QUAYYUMprogress
02/26/2026FinalSHAHRIAR QUAYYUMprogress
02/26/2026Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
02/26/2026MasonrySHAHRIAR QUAYYUMspecial
Latest 25 of 81.
▾Documents — 107 on file (BIS + DOB NOW)
▸Plans & Drawings16
▸DOB NOWPlans/Sketch16
08/21/2026B01205434-P1Request digital key ↗
08/21/2026B01205434-I1Request digital key ↗
08/21/2026B01175087-P5Request digital key ↗
Showing 3 of 16 on file for this type
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION3
02/24/2025340915996Open ↗
11/29/2023310158209Open ↗
06/19/2008310158209Open ↗
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram2
08/21/2026B01175087-P5Open ↗
08/13/2026B01175087-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/21/2026B01175087-P5Open ↗
08/13/2026B01175087-I1Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
06/26/2025340915996Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01175087-I1Open ↗
▸Seals & Professional Certifications45
▸DOB NOWDPL-1: Design Professional Seal & Signature16
08/21/2026B01205434-I1Open ↗
08/21/2026B01205434-P1Open ↗
08/21/2026B01175087-P5Open ↗
Showing 3 of 16 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature13
09/01/2026B01175087-P1Open ↗
09/01/2026B01175087-P1Open ↗
09/01/2026B01175087-P4Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWProgress Inspector Seal & Signature12
09/01/2026B01175087-P1Open ↗
09/01/2026B01175087-P4Open ↗
08/31/2026B01175087-S2Open ↗
Showing 3 of 12 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
06/26/2025340915996Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
06/19/2008310158209Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
06/19/2008310158209Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
06/19/2008310158209Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/21/2026B01175087-P5Open ↗
08/13/2026B01175087-I1Open ↗
▸Safety & Tenant Protection3
▸BISBPP: STREET TREES SITE PLAN1
02/14/2025340915996Open ↗
▸BISSTREET TREE CHECKLIST1
02/14/2025340915996Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B01175087-I1Open ↗
▸Environmental & Asbestos15
▸DOB NOWDEP ACP-5: Asbestos Assessment Report14
08/21/2026B01205434-P1Open ↗
08/21/2026B01205434-I1Open ↗
08/21/2026B01175087-S5Open ↗
Showing 3 of 14 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
06/19/2008310158209Open ↗
▸Inspections & Test Reports4
▸DOB NOWSOIL REPORT3
08/15/2026B01175087-P1Open ↗
08/15/2026B01175087-S4Open ↗
08/13/2026B01175087-P4Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B01175087-S4Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
06/19/2008310158209Open ↗
▸Filing & Intake Forms4
▸BISEFILING JOB APPLICATION COVER SHEET1
02/14/2025340915996Open ↗
▸BISADDITIONAL INFORMATION1
06/26/2025340915996Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
02/14/2025340915996Open ↗
▸BISEFILING COVER SHEET1
06/19/2008310158209Open ↗
▸Other Documents8
▸DOB NOWSite Survey: Initial2
08/21/2026B01175087-P5Open ↗
08/13/2026B01175087-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/21/2026B01175087-P5Open ↗
08/13/2026B01175087-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/21/2026B01175087-P5Open ↗
08/13/2026B01175087-I1Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
06/26/2025340915996Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B01175087-S5Open ↗