1968Year Built
5Stories
W3Building Class
C4-7Zoning
360,120 sfGross Floor Area
2Units
LL97 Covered0 Active ViolationsFISP: SAFE
School or academy · 98,581 sf lot · 3.65 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 6The Juilliard School16p · 1 filing · 20 docs
Floor 5Juilliard - Alice Tully Hall, The Juilliard SchoolUnder Construction43p · 3 filings · 19 docs
Floor 4The Juilliard School13p · 1 filing · 16 docs
Floor 3The Juilliard School72p · 9 filings · 18 docs
Floor 2Lincoln Center, The Juilliard SchoolUnder Construction73p · 5 filings · 17 docs
Floor 1Alice Tully Hall, Lincoln Center123p · 67 filings · 16 docs
CellarThe Juilliard School40p · 6 filings · 15 docs
Sub-Cellar2p · 1 filing · 2 docs
Site & exteriorLincoln Center, The Juilliard School31p · 4 filings · 14 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Lincoln Center for the Performing A20910/06/2026
The Juilliard School11909/13/2026
Lcpa503/21/2026
Minority Corp Counsel Associatio103/21/2026
Cfda103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Me Engineers207/10/2026
CO4ARCHITECTURE107/09/2026
Vincent J. Liotta P.E105/04/2026
SYNC Architecture5004/20/2026
Goldman Copeland Associates103/18/2026
Fxcollaborative Architects1008/02/2024
Cutrona Architecture109/15/2023
Derive Engineers507/24/2023
Black Box Engineering205/17/2023
Demo Architecture104/03/2023
Christopher Compton203/27/2023
Nestor Bottino301/06/2023
360 Engineering811/15/2022
Kohler Ronan1005/19/2022
Andrew Formichella2201/31/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Nyccode4403/21/2026
Municipal Building Consultants3003/21/2026
Doreen A. Rizzi, Consultant203/21/2026
KM Associates of New York803/21/2026
ECC403/21/2026
AE Design Solution403/21/2026
K & M Associates803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PJP InstallersScaffold1907/08/2026
Arol ManagementGeneral Contractor907/08/2026
Arena Event ServicesGeneral Contractor707/08/2026
SondhusGeneral Contractor603/21/2026
Yorke ConstructionGeneral Contractor507/08/2026
United Plumbing MechanicalFire Protection307/08/2026
City/Suburban PlumbingPlumbing207/08/2026
Eclipse ContractingGeneral Contractor210/02/2026
Jads ProductionsGeneral Contractor203/21/2026
Team ElectricElectrical203/22/2026
Stamford Tent & Equipment CoGeneral Contractor203/21/2026
Lane Refrigeration Cospecialty_contractor107/08/2026
E-J Electric Installation CoElectrical103/22/2026
Allran Electric of NYElectrical103/21/2026
Top Shelf ElectricElectrical103/21/2026
Candela Systems Corp DbaElectrical103/22/2026
Perfectaire CoGeneral Contractor107/08/2026
Winick ProductionsGeneral Contractor104/09/2026
Archer Consultants GroupFire Protection110/06/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Franklin & Oak5758307/10/2026
Vincent J. Liotta P. E1974105/04/2026
Crosscheck Inspection Services5442407/24/2023
Black Box Engineering7196205/17/2023
Environmental Code Consulting5516203/27/2023
Building Lifecycle
All (287)Filed (80)Permit Issued (42)Signed Off (11)Facade (FISP) (15)Violation (60)Inspection (10)Objection (39)Special Inspection (30)
10/05/2026
Permit issued — Sprinklers
M01415100-S2-EW-SP
10/01/2026
Permit issued — Mechanical Systems
M01415100-S1-MS
10/01/2026
Permit issued — General Construction
M01415100-I1-GC
09/25/2026
Signed off — Alteration
Structural scope associated with Juilliard Drama Division's existing dressing room renovation. No change or use, egress, or occupancy.
M00809010-I1
08/19/2026
Permit issued — Suspended Scaffold
M01425901-I1-SC
08/06/2026
Filed — Alteration
Installation of IRA during facade inspection.
M01425901-I1
07/10/2026
Filed — Alteration
Mechanical scope associated with the interior renovation of the Media Suite at Alice Tully Hall, Lincoln Center. No change of use, egress, or occupancy.
M01415100-S2
07/10/2026
Filed — Alteration
Mechanical scope associated with the interior renovation of the Media Suite at Alice Tully Hall, Lincoln Center. No change of use, egress, or occupancy.
M01415100-S1
07/09/2026
Filed — Alteration
Mechanical scope associated with the interior renovation of the Media Suite at Alice Tully Hall, Lincoln Center. No change of use, egress, or occupancy.
M01415100-I1
06/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
Michael Kokoszka
06/17/2026
Special inspection requirement — Shutoff dampers
Michael Kokoszka
06/17/2026
Special inspection requirement — Energy Code Compliance Inspections
Michael Kokoszka
06/17/2026
Special inspection requirement — Lighting controls
Michael Kokoszka
06/17/2026
Special inspection requirement — Duct leakage testing, insulation and design
Michael Kokoszka
06/17/2026
Special inspection requirement — Interior lighting power
Michael Kokoszka
06/17/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Michael Kokoszka
06/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Michael Kokoszka
06/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
Michael Kokoszka
06/17/2026
Special inspection requirement — Post-installed Anchors
Michael Kokoszka
06/10/2026
Special inspection requirement — Final
Michael Kokoszka
06/10/2026
Special inspection requirement — Mechanical Systems
Michael Kokoszka
05/08/2026
Permit issued — Mechanical Systems
M01389127-I1-MS
05/04/2026
Filed — Alteration
REPLACEMENT OF 3 TON SPLIT SYSTEM ON FLOOR 005. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
M01389127-I1
04/20/2026
Filed — No Work
M01389495-I1
04/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
Vincent Liotta
04/17/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Vincent Liotta
04/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
Vincent Liotta
04/17/2026
Special inspection requirement — Final
Vincent Liotta
04/17/2026
Special inspection requirement — Maintenance information
Vincent Liotta
04/17/2026
Special inspection requirement — Mechanical Systems
Vincent Liotta
04/14/2026
Objection raised — Fire_Protection
03/18/2026
Filed — Alteration
Sprinkler Work- removal of 6 SPR heads from the elevator pit at the Juilliard School. No change of use, egress or occupancy.
M01370673-I1
03/11/2026
Special inspection requirement — Sprinkler Systems
02/24/2026
Filed — No Work
M01363751-I1
02/04/2026
Permit issued — General Construction
M01351801-I1-GC
01/27/2026
Filed — Alteration
Temporary scenic structures for events at Alice Tully Hall lobbies. Removed at the end of the programing. No changes to existing structures, use or egress.
M01351801-I1
01/27/2026
Filed — No Work
M01351636-I1
01/08/2026
Filed — No Work
M01343911-I1
12/01/2025
Filed — Alteration
Temporary structures for events at the Alice Tully Hall lobbies. Removed at the end of the programing. No changes to existing structures, use or egress.
M00687862-P6
12/01/2025
Special inspection requirement — Final
ANDY ENGLER ROTH
11/28/2025
Filed — No Work
M01324391-I1
11/26/2025
Special inspection requirement — Final
ANDY ENGLER ROTH
11/07/2025
Objection resolved — Addressed
11/06/2025
Objection raised — Admin
11/05/2025
Filed — No Work
M01313794-I1
07/03/2025
Filed — No Work
M01249679-I1
06/23/2025
Filed — No Work
M01244204-I1
06/23/2025
Objection raised — Fire_Protection
06/23/2025
Objection resolved — Addressed
04/24/2025
Filed — No Work
M01215340-I1
02/03/2025
Filed — Alteration
Temporary structures for events at the Alice Tully Hall lobbies. Removed at the end of the programing. No changes to existing structures, use or egress.
M00687862-P5
02/03/2025
Special inspection requirement — Final
ANDY ENGLER ROTH
01/29/2025
Filed — No Work
M01173002-I1
01/29/2025
Permit issued — General Construction
M00687862-I1-GC
11/07/2024
Filed — No Work
M01138772-I1
11/07/2024
Permit issued — General Construction
M00687862-I1-GC
09/21/2024
Objection raised — Admin
09/21/2024
Objection resolved — Addressed
09/20/2024
Filed — No Work
M01114745-I1
08/13/2024
Special inspection requirement — Public Assembly Emergency Lighting
EUGENE BIFULCO
Latest 60 of 287 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedArcher Consultants Group10/05/2026
DOB NOWMechanical SystemsPermit IssuedEclipse Contracting10/01/2026
DOB NOWGeneral ConstructionPermit IssuedEclipse Contracting10/01/2026
DOB NOWSuspended ScaffoldPermit IssuedJC Santana Contracting Co08/19/2026
DOB NOWMechanical SystemsPermit IssuedLane Refrigeration Co05/08/2026
DOB NOWGeneral ConstructionPermit IssuedWinick Productions02/04/2026
DOB NOWGeneral ConstructionPermit IssuedArena Event Services01/29/2025
DOB NOWGeneral ConstructionPermit IssuedArena Event Services11/07/2024
DOB NOWGeneral ConstructionPermit IssuedArena Event Services12/21/2023
DOB NOWGeneral ConstructionSigned-offJads Productions09/18/2023
DOB NOWGeneral ConstructionSigned-offSondhus06/19/2023
DOB NOWStructuralSigned-offSondhus06/17/2023
DOB NOWMechanical SystemsSigned-offSondhus06/17/2023
DOB NOWPlumbingSigned-offCity/Suburban Plumbing05/03/2023
DOB NOWStructuralSigned-offArol Management05/02/2023
DOB NOWMechanical SystemsSigned-offArol Management05/02/2023
DOB NOWGeneral ConstructionSigned-offArol Management05/01/2023
DOB NOWGeneral ConstructionPermit IssuedStamford Tent & Equipment Co04/24/2023
DOB NOWSprinklersSigned-offUnited Plumbing Mechanical01/25/2023
DOB NOWSidewalk ShedSigned-offPJP Installers01/18/2023
DOB NOWSupported ScaffoldPermit IssuedPJP Installers01/17/2023
DOB NOWMechanical SystemsSigned-offYorke Construction11/10/2022
DOB NOWSprinklersSigned-offUnited Plumbing Mechanical10/18/2022
DOB NOWGeneral ConstructionPermit IssuedArena Event Services08/23/2022
DOB NOWGeneral ConstructionSigned-offArol Management06/22/2022
DOB NOWGeneral ConstructionSigned-offArol Management06/07/2022
DOB NOWGeneral ConstructionSigned-offYorke Construction05/23/2022
DOB NOWGeneral ConstructionPermit IssuedArena Event Services02/28/2022
DOB NOWSupported ScaffoldPermit IssuedPJP Installers01/14/2022
DOB NOWSidewalk ShedSigned-offPJP Installers01/14/2022
DOB NOWMechanical SystemsSigned-offPerfectaire Co07/21/2021
DOB NOWSprinklersSigned-offUnited Plumbing Mechanical07/20/2021
DOB NOWPlumbingSigned-offCity/Suburban Plumbing07/16/2021
DOB NOWGeneral ConstructionSigned-offYorke Construction07/14/2021
DOB NOWSidewalk ShedSigned-offPJP Installers03/24/2021
DOB NOWSupported ScaffoldPermit IssuedPJP Installers03/24/2021
DOB NOWSupported ScaffoldPermit IssuedPJP Installers03/20/2020
DOB NOWSidewalk ShedSigned-offPJP Installers03/20/2020
DOB NOWSupported ScaffoldPermit IssuedPJP Installers01/16/2020
DOB NOWSidewalk ShedSigned-offPJP Installers01/16/2020
+ 52 more permits on file
2 projects · most recent 07/10/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
07/10/2026Permit IssuedEclipse ContractingAir Conditioning Systems
Cooling
Liebert CW038U 121,000 BTU ×1
MM40C 28,400 BTU · Crac Unit ×1
05/04/2026Permit IssuedLane Refrigeration CoAir Conditioning Systems
Cooling
Liebert MT036HK1Y00 3 tons · Crac Unit ×1
MTC38WTY21 3 tons · Crac Unit ×1
2 projects · most recent 07/10/2026
FiledStatusContractorScope
07/10/2026Permit IssuedArcher Consultants Group—
03/18/2026——6 heads
13 projects · most recent 07/23/2026
General Wiring
FiledStatusContractorScope
07/23/2026Permit IssuedC.M. Richey Electrical ContractingGeneral Wiring
03/05/2026Permit IssuedAllran Electric of NY—
02/16/2026CancelledTop Shelf Electric—
03/26/2025Permit IssuedTeam ElectricGeneral Wiring
08/15/2024Permit IssuedArcadia Elect'l CoGeneral Wiring
12/04/2023CompleteCandela Systems Corp DbaGeneral Wiring
04/14/2023CompleteTeam ElectricGeneral Wiring
10/11/2022Permit IssuedH. & L. Electric—
08/05/2022CompleteTeam ElectricGeneral Wiring
03/30/2022Permit IssuedKnight Electrical ServiceGeneral Wiring
10/08/2021CompleteH. & L. Electric—
04/13/2020CompleteE-J Electric Installation CoGeneral Wiring
01/14/2019CompleteTop Shelf Electric—
2 projects · most recent 07/24/2023
Steel
FiledStatusContractorScope
07/24/2023Signed-offCity/Suburban PlumbingSteel
06/12/2023Signed-offSondhusSteel
1 project · most recent 11/15/2022
Scaffold
FiledStatusContractorScope
11/15/2022Permit IssuedPJP InstallersScaffold
1 project · most recent 08/06/2026
FiledStatusContractorScope
08/06/2026Permit IssuedJC Santana Contracting Co—
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
08/14/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/20/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/03/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/17/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/08/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
02/03/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/28/2022Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/25/2022Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/12/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
08/09/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
06/17/2026Fire-Resistant Penetrations and JointsMichael Kokoszkaspecial
06/17/2026Post-installed AnchorsMichael Kokoszkaspecial
06/17/2026Lighting controlsMichael Kokoszkaenergy_progress
06/17/2026Shutoff dampersMichael Kokoszkaenergy_progress
06/17/2026HVAC-R and service water heating system controlsMichael Kokoszkaenergy_progress
06/17/2026Duct leakage testing, insulation and designMichael Kokoszkaenergy_progress
06/17/2026Interior lighting powerMichael Kokoszkaenergy_progress
06/17/2026HVAC-R and service water piping design and insulationMichael Kokoszkaenergy_progress
06/17/2026HVAC-R and service water heating equipmentMichael Kokoszkaenergy_progress
06/17/2026Energy Code Compliance InspectionsMichael Kokoszkaprogress
06/10/2026Mechanical SystemsMichael Kokoszkaspecial
06/10/2026FinalMichael Kokoszkaprogress
04/17/2026HVAC-R and service water heating equipmentVincent Liottaenergy_progress
04/17/2026Mechanical SystemsVincent Liottaspecial
04/17/2026Maintenance informationVincent Liottaenergy_progress
04/17/2026HVAC-R and service water heating system controlsVincent Liottaenergy_progress
04/17/2026FinalVincent Liottaprogress
04/17/2026HVAC-R and service water piping design and insulationVincent Liottaenergy_progress
03/11/2026Sprinkler Systems—special
12/01/2025FinalANDY ENGLER ROTHprogress
11/26/2025FinalANDY ENGLER ROTHprogress
02/03/2025FinalANDY ENGLER ROTHprogress
08/13/2024Public Assembly Emergency LightingEUGENE BIFULCOprogress
07/16/2024Public Assembly Emergency LightingEUGENE BIFULCOprogress
12/21/2023FinalANDY ENGLER ROTHprogress
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Juilliard - Alice Tully HallArts / Culture / EntertainmentFloor 5
Project M01389127 Alteration · Permit Entire · 05/04/2026
The Juilliard SchoolEducationCellar, Floors 1–6
Project M01370673 Alteration · Objections · 03/18/2026
Project M00921040 No Work · PA Certificate of Operation Issued · 09/21/2023
Project M00852995 Alteration · Permit Entire · 04/03/2023
Project M00809010 Alteration · Permit Entire · 01/27/2023
Project M08051354 Alteration · Approved · 12/12/2022
Project M00699696 Alteration · LOC Issued · 03/23/2022
Project M00551658 Alteration · LOC Issued · 07/06/2021
Project M00523314 Alteration · LOC Issued · 06/02/2021
Project M00523496 Alteration · LOC Issued · 06/02/2021
Project M00118896 Alteration · Permit Entire · 02/07/2019
Project M00118888 Alteration · LOC Issued · 01/14/2019
Alice Tully HallArts / Culture / EntertainmentFloor 1
Project M01351801 Alteration · Permit Entire · 01/27/2026
Project M00687862 Alteration · Permit Entire · 02/25/2022
Lincoln CenterArts / Culture / EntertainmentFloors 1, 2
Project M00862171 Alteration · Permit Entire · 04/21/2023
Project M01415100 Alteration · Permit Entire · 07/09/2026
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 1,589 on file (BIS + DOB NOW)
▸Plans & Drawings122
▸DOB NOWPlans/Sketch - Temporary Place of Assembly67
09/05/2026M00138404-I1Request digital key ↗
09/05/2026M00147717-I1Request digital key ↗
09/05/2026M00155445-I1Request digital key ↗
Showing 3 of 67 on file for this type
▸DOB NOWPlans/Sketch45
09/03/2026M00523314-P1Request digital key ↗
09/03/2026M00523314-I1Request digital key ↗
09/03/2026M00523496-I1Request digital key ↗
Showing 3 of 45 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold4
09/01/2026M00118896-P3Request digital key ↗
09/01/2026M00118896-I1Request digital key ↗
Showing 2 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed4
09/02/2026M00118888-P2Request digital key ↗
09/02/2026M00118888-P1Request digital key ↗
09/02/2026M00118888-P3Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Applications & Permits229
▸BISPLAN / WORK APPROVAL APPLICATION126
01/15/2026120019283Open ↗
12/24/2025122913883Open ↗
05/03/2023140820440Open ↗
Showing 3 of 126 on file for this type
▸BISWORK PERMIT APPLICATION91
12/17/2020121208530Open ↗
11/04/2020140937119Open ↗
11/04/2020140932178Open ↗
Showing 3 of 91 on file for this type
▸BISPLACE OF ASSEMBLY8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISPLACE OF ASSEMBLY SIGN OFF1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications521
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION185
04/24/2020123746786Open ↗
04/24/2020123746786Open ↗
03/18/2020123833968Open ↗
Showing 3 of 185 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature117
09/05/2026M00138404-I1Open ↗
09/05/2026M00155445-I1Open ↗
09/05/2026M00156277-I1Open ↗
Showing 3 of 117 on file for this type
▸DOB NOWProgress Inspector Seal & Signature63
10/01/2026M00809010-S3Open ↗
10/01/2026M00809010-S3Open ↗
09/26/2026M00852995-I1Open ↗
Showing 3 of 63 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST52
03/18/2020123833968Open ↗
12/04/2019123847631Open ↗
09/23/2019123746786Open ↗
Showing 3 of 52 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature36
10/01/2026M00809010-S3Open ↗
09/25/2026M00551658-P1Open ↗
09/25/2026M00551658-P1Open ↗
Showing 3 of 36 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT32
08/28/2020140937119Open ↗
08/20/2020140932178Open ↗
07/27/2020140923516Open ↗
Showing 3 of 32 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM25
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 25 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION5
08/28/2020140937119Open ↗
08/20/2020140932178Open ↗
07/27/2020140923516Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
08/28/2020140937119Open ↗
08/20/2020140932178Open ↗
Showing 2 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Trade Schedules & Equipment44
▸BISSCHEDULE B - PLUMBING13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISSELF-CERT PLUMBING NOTICE13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISSPRINKLER INSP REPORT : FP-856
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Environmental & Asbestos85
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'26
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 26 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report11
09/03/2026M00523314-I1Open ↗
09/03/2026M00523314-P1Open ↗
09/02/2026M00699696-S3Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form11
09/02/2026M00699696-S1Open ↗
09/02/2026M00699696-S2Open ↗
09/02/2026M00699696-I1Open ↗
Showing 3 of 11 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)8
12/16/2020121208530Open ↗
Showing 1 of 8 on file for this type
▸BISASBESTOS INSPECTION REPORT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM3
11/04/2020140937119Open ↗
11/04/2020140932178Open ↗
11/04/2020140923516Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance36
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY10
05/05/2021140937119Open ↗
11/13/2020121208530Open ↗
11/04/2020140937119Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS7
03/18/2020123833968Open ↗
12/20/2019123724648Open ↗
Showing 2 of 7 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS6
05/07/2021140923516Open ↗
05/05/2021140937119Open ↗
05/04/2021140932178Open ↗
Showing 3 of 6 on file for this type
▸BISNYCECC ANALYSIS4
08/28/2020140937119Open ↗
08/20/2020140932178Open ↗
07/27/2020140923516Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS3
08/28/2020140937119Open ↗
08/20/2020140932178Open ↗
Showing 2 of 3 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.2
09/03/2026M00523314-I1Open ↗
09/02/2026M00699696-S1Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTR8: ENERGY CODE PROGRESS INSPS TECHNICAL REPORT1
08/20/2020140932178Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/03/2023140820440Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
07/03/2023140820440Open ↗
▸Inspections & Test Reports32
▸BISTECHNICAL REPORT: RESPONSIBILITY24
05/07/2021140923516Open ↗
05/07/2021140923516Open ↗
05/05/2021140937119Open ↗
Showing 3 of 24 on file for this type
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS2
11/20/2025110484921Open ↗
07/03/2023140820440Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
11/20/2025110484921Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
11/20/2025110484921Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
01/09/2026120019283Open ↗
▸BISWALL PANELS, CURTAIN WALLS, AND VENEERS1
07/03/2023140820440Open ↗
▸BISTECHNICAL REPORT: PILE DRIVING1
01/24/2020123847631Open ↗
▸Approvals, Objections & Sign-offs240
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter96
09/03/2026M00523314-P1Open ↗
09/03/2026M00523314-I1Open ↗
09/03/2026M00618928-I1Open ↗
Showing 3 of 96 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST77
01/14/2026120019283Open ↗
07/03/2023140820440Open ↗
05/07/2021140923516Open ↗
Showing 3 of 77 on file for this type
▸BISADMINISTRATIVE OBJECTIONS43
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 43 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION16
09/06/2020140937119Open ↗
08/21/2020140923516Open ↗
Showing 2 of 16 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
11/05/2020121208530Open ↗
11/02/2020121208530Open ↗
06/12/2019104352488Open ↗
▸DOB NOWDEP Variance (V5) letter3
09/02/2026M00699696-S1Open ↗
09/02/2026M00699696-S2Open ↗
09/02/2026M00699696-I1Open ↗
▸BISFINAL2
01/08/2026120019283Open ↗
07/03/2023140820440Open ↗
▸Cost, Insurance & Ownership110
▸BISCOST AFFIDAVIT107
05/07/2021140923516Open ↗
05/05/2021140937119Open ↗
05/04/2021140932178Open ↗
Showing 3 of 107 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW33
01/12/2026120019283Open ↗
12/23/2025110484921Open ↗
07/03/2023140820440Open ↗
▸Filing & Intake Forms125
▸BISEFILING COVER SHEET62
04/29/2020104352488Open ↗
03/18/2020123833968Open ↗
12/20/2019123724648Open ↗
Showing 3 of 62 on file for this type
▸BISBOROUGH INTAKE FORM30
04/29/2020104352488Open ↗
04/27/2020104352488Open ↗
04/24/2020123746786Open ↗
Showing 3 of 30 on file for this type
▸BISADDITIONAL INFORMATION25
05/31/2023140820440Open ↗
05/15/2023140820440Open ↗
08/21/2020140923516Open ↗
Showing 3 of 25 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET8
08/28/2020140937119Open ↗
08/20/2020140932178Open ↗
07/27/2020140923516Open ↗
Showing 3 of 8 on file for this type
▸Other Documents37
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION15
03/18/2020123833968Open ↗
12/19/2019123724648Open ↗
Showing 2 of 15 on file for this type
▸BISFEE EXEMPTION DOCUMENTATION4
08/28/2020140937119Open ↗
08/20/2020140932178Open ↗
07/27/2020140923516Open ↗
Showing 3 of 4 on file for this type
▸BISSupporting Document: Fee Exempt3
05/15/2023140820440Open ↗
08/12/2020140923516Open ↗
04/30/2020140820440Open ↗
▸BISSupporting Document: Fee Deferment2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAlternate Plan 42
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAlternate Plan 32
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAlternate Plan 12
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAlternate Plan 22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWAlternate Plan 52
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDoc 12
09/02/2026M00118888-P1Open ↗
Showing 1 of 2 on file for this type
▸DOB NOWIRA Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type