← Back
Two stories - detached, small or mid-size
196-05 119 AVENUE
QUEENS · St. Albans · BIN 4271830
💬 Discuss this project
1930Year Built
2.75Stories
A1Building Class
R3AZoning
1,926 sfGross Floor Area
1Units
Two stories - detached, small or mid-size · 3,000 sf lot · 0.64 FAR built · Flood zone X
Locations of Work
ArchitectureElectrical
Roof4p · 1 filing · 10 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/21/2015$405K—— → —$210/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GREEN RIVER ENVIRONMENTAL ENGINEERI212/23/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY State Solar LLC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYSS LLCGeneral Contractor303/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREEN RIVER ENVIRONMENTAL7841212/23/2025
Building Lifecycle
All (8)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (4)
01/06/2026
Signed off — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
Q01158104-I1
12/23/2025
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
Q01158104-P1
12/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
12/23/2025
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
12/23/2025
Special inspection requirement — Final
ROBERT MASONE
12/23/2025
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
12/20/2024
Permit issued — Solar
Q01158104-I1-SL
12/19/2024
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS
Q01158104-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYSS LLC12/20/2024
1 project · most recent 12/18/2024
FiledStatusContractorScope
12/18/2024CompleteNY SOLAR ELECTRICAL LLC—
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
12/23/2025Fire-Resistant Penetrations and JointsROBERT MASONEspecial
12/23/2025Energy Code Compliance InspectionsROBERT MASONEprogress
12/23/2025FinalROBERT MASONEprogress
12/23/2025Air barrier - visual inspectionROBERT MASONEenergy_progress
▾Documents — 10 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/18/2026Q01158104-P1Request digital key ↗
08/18/2026Q01158104-I1Request digital key ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/18/2026Q01158104-I1Open ↗
08/18/2026Q01158104-P1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/29/2026Q01158104-I1Open ↗
08/29/2026Q01158104-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/29/2026Q01158104-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/18/2026Q01158104-I1Open ↗
08/18/2026Q01158104-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01158104-I1Open ↗