| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/19/2024 | $700K | — | Private party → 196 EAST 94 LLC | $179/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PRAMODRAY SHAH, P.E. | 2 | 04/23/2025 |
| VASILIOS ARTEMIOU PE | 1 | 01/17/2025 |
| LEANDRO NILS DICKSON ARCHITECT, LLC | 2 | 12/20/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJH CONSTRUCTION CORP | General Contractor | 4 | 03/21/2026 |
| S&R ELECTRICAL & MECHANIC | Electrical | 1 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 5 | 04/23/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | MJH CONSTRUCTION CORP | 03/06/2025 |
| DOB NOW | Plumbing | Signed-off | A M B MECHANICAL INC | 01/15/2025 |
| DOB NOW | Plumbing | Signed-off | PRIME PIPING & HEATING IN | 01/15/2025 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 01/07/2025 |
| BIS | BL | ISSUED | CITY TESTING & PLUMBING I | 12/03/2008 |
| BIS | — | ISSUED | BUILDING VIOLATIONS REMOVAL INC. | 08/11/2008 |
| BIS | PL | ISSUED | CITY TESTING & PLUMBING I | 07/29/2008 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/23/2025 | Signed-off | MJH CONSTRUCTION CORP | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2025 | Signed-off | PRIME PIPING & HEATING IN | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/23/2025 | Signed-off | A M B MECHANICAL INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/07/2025 | Complete | S&R ELECTRICAL & MECHANIC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/24/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/21/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/27/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/25/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/19/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/04/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/08/2025 | Post-installed Anchors | FAHAD FATEH | special |
| 05/08/2025 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 05/08/2025 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 05/08/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 05/08/2025 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 05/08/2025 | Sprinkler Systems | FAHAD FATEH | special |
| 05/08/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 04/10/2025 | Post-installed Anchors | FAHAD FATEH | special |
| 04/10/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 04/10/2025 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 04/10/2025 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 04/10/2025 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 04/10/2025 | Sprinkler Systems | FAHAD FATEH | special |
| 04/10/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 02/04/2025 | Ventilation and air distribution system | FAHAD FATEH | energy_progress |
| 01/10/2025 | Post-installed Anchors | FAHAD FATEH | special |
| 01/10/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 01/10/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 01/10/2025 | Shutoff dampers | FAHAD FATEH | energy_progress |
| 01/10/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 01/10/2025 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 01/10/2025 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 01/10/2025 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 01/09/2025 | Mechanical Systems | FAHAD FATEH | special |
| 01/09/2025 | Final | FAHAD FATEH | progress |