1915Year Built
6Stories
RCBuilding Class
C6-1GZoning
32,007 sfGross Floor Area
20Units
LL97 Covered38 Open Violations 37 unresolved · 1 paperwork only ▸
Condo, commercial tower (mixed-use) [derived] · 5,025 sf lot · 6.37 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanical
Roof2p · 2 filings · 11 docs
Floor 44p · 1 filing · 12 docs
Floor 3
Floor 2
Floor 1
1 job · most recent 12/20/2021
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
12/20/2021Permit IssuedNEW KAMPAR INCAir Conditioning Systems
Cooling
Fujitsu AOU30CLX1 30,800 BTU · Condensing Unit ×1
Trane 2TTM3036A1000AA 36,000 BTU · Condensing Unit ×1
4 jobs · most recent 04/14/2026
General Wiring
FiledStatusContractorScope
04/14/2026Permit IssuedTHOMAS NOTOGeneral Wiring
10/06/2025CompleteKWONG MING ELECTRIC INCGeneral Wiring
06/20/2019CompleteKWONG MING ELECTRIC INCGeneral Wiring
06/20/2019CompleteKWONG MING ELECTRIC INC—
Building Lifecycle
All (99)Filed (7)Permit Issued (6)Signed Off (5)Violation (60)Inspection (2)Special Inspection (19)
04/03/2026
Violation issued (ECB, open)
Construction
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/10/2025
Signed off — Alteration
132/24 REPLACE EXISTING BROADAIR A C UNIT WITH NEW A C UNIT & OBTAIN A CERTIFICATE OF COMPLIANCE (EQUIPMENT USE PERMIT) FOR REPLACEMENT AC UNIT PER FIRE DEPT VIOLATION NUMBER 114707467J
M01126031-I1
01/08/2025
Permit issued — Mechanical Systems
M01126031-I1-MS
11/20/2024
Filed — Alteration
132/24 REPLACE EXISTING BROADAIR A C UNIT WITH NEW A C UNIT & OBTAIN A CERTIFICATE OF COMPLIANCE (EQUIPMENT USE PERMIT) FOR REPLACEMENT AC UNIT PER FIRE DEPT VIOLATION NUMBER 114707467J
M01126031-I1
06/17/2024
Signed off — Alteration
RENOVATE FOR DENTAL OFFICE AT 4TH FLOOR (STE 402) . INCLUDE REMOVING AND INSTALLINGNEW INTERIOR NON-LOAD BEARING PARTITIONS, LIGHTING ANDFINISH WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M00938063-S1
06/17/2024
Signed off — Alteration
RENOVATE FOR DENTAL OFFICE AT 4TH FLOOR (STE 402) . INCLUDE REMOVING AND INSTALLINGNEW INTERIOR NON-LOAD BEARING PARTITIONS, LIGHTING ANDFINISH WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M00938063-I1
02/22/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/14/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
12/04/2023
Permit issued — Plumbing
M00938063-S1-PL
10/10/2023
Permit issued — General Construction
M00938063-I1-GC
10/02/2023
Filed — Alteration
RENOVATE FOR DENTAL OFFICE AT 4TH FLOOR (STE 402) . INCLUDE REMOVING AND INSTALLINGNEW INTERIOR NON-LOAD BEARING PARTITIONS, LIGHTING ANDFINISH WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M00938063-S1
09/27/2023
Filed — Alteration
RENOVATE FOR DENTAL OFFICE AT 4TH FLOOR (STE 402) . INCLUDE REMOVING AND INSTALLINGNEW INTERIOR NON-LOAD BEARING PARTITIONS, LIGHTING ANDFINISH WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY
M00938063-I1
09/27/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Joon Ho Chai
09/27/2023
Special inspection requirement — Maintenance information
Joon Ho Chai
09/27/2023
Special inspection requirement — Energy Code Compliance Inspections
Joon Ho Chai
09/27/2023
Special inspection requirement — Fire-Resistance Rated Construction
Joon Ho Chai
09/27/2023
Special inspection requirement — Lighting controls
Joon Ho Chai
09/27/2023
Special inspection requirement — Maintenance information
Joon Ho Chai
09/27/2023
Special inspection requirement — Interior lighting power
Joon Ho Chai
09/27/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joon Ho Chai
09/22/2023
Special inspection requirement — Final
JIN WOO LEE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/22/2022
Signed off — Alteration
Replace AV condenser units on the roof, no change of use, egress or occupancy under this application.
M00692627-I1
04/19/2022
Permit issued — Mechanical Systems
M00692627-I1-MS
04/13/2022
Filed — Alteration
Replace AV condenser units on the roof, no change of use, egress or occupancy under this application.
M00692627-I1
03/05/2022
Special inspection requirement — Final
ALLEN SHINFELD
03/05/2022
Special inspection requirement — HVAC-R and service water heating equipment
ALLEN SHINFELD
03/05/2022
Special inspection requirement — HVAC-R and service water heating system controls
ALLEN SHINFELD
03/05/2022
Special inspection requirement — Mechanical Systems
ALLEN SHINFELD
03/05/2022
Special inspection requirement — Energy Code Compliance Inspections
ALLEN SHINFELD
02/02/2022
Permit issued — Mechanical Systems
M00646539-I1-MS
12/21/2021
Special inspection requirement — Mechanical Systems
ALLEN SHINFELD
12/21/2021
Special inspection requirement — HVAC-R and service water heating equipment
ALLEN SHINFELD
12/21/2021
Special inspection requirement — HVAC-R and service water heating system controls
ALLEN SHINFELD
12/21/2021
Special inspection requirement — Energy Code Compliance Inspections
ALLEN SHINFELD
12/21/2021
Special inspection requirement — Final
ALLEN SHINFELD
12/20/2021
Filed — Alteration
Replace AC condenser units on the roof, no change of uses, egress or occupancy under this application.
M00646539-P1
12/16/2021
Filed — Alteration
Replace AC condenser units on the roof, no change of uses, egress or occupancy under this application.
M00646539-I1
02/26/2021
Signed off — Alteration
REPLACE H.V.A.C UNIT ON ROOF AS PER PLAN; NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00394347-I1
09/29/2020
Permit issued — Mechanical Systems
M00394347-I1-MS
09/10/2020
Filed — Alteration
REPLACE H.V.A.C UNIT ON ROOF AS PER PLAN; NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00394347-I1
05/15/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/08/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/08/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/08/2019
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/12/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
06/04/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
04/06/2018
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
02/24/2017
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/14/2015
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
05/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/01/2013
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/09/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
Latest 60 of 99 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NO 1 GOLDEN MOUNTAIN407/08/2026
BETHEL MANAGEMENT1407/08/2026
201 AUTUMN AVE303/22/2026
OWNER OF PREMISES 198 CAN103/22/2026
C.J. TRADERS INC103/22/2026
198 CANAL ST303/21/2026
TUNG SHING PROPERTIES103/21/2026
TUNG SHING PROPERTY203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
G. PEROTTO ASSOCIATES111/20/2024
JAMES CHAI ARCHITECT, P.C.210/02/2023
ALLEN SHINFELD, P.E. PLLC304/13/2022
YL DESIGN GROUP109/10/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PROJECT ENTRY303/21/2026
HTX BUILDING CONSULTING203/21/2026
G PEROTTO ASSOCIATES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW KAMPAR INCGeneral Contractor407/08/2026
RRP PLUMBING CORPPlumbing307/08/2026
BERN CONCEPT INCGeneral Contractor303/21/2026
YILIN CONSTRUCTION INCGeneral Contractor303/21/2026
AI FANG WUElectrical203/21/2026
KWONG MING ELECTRIC INCElectrical103/22/2026
ROOPCHAND SINGHElectrical103/21/2026
ALL DAY PLUMBING & HEATINGGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREGORY V. PEROTTO, P.E.947111/20/2024
JAMES JH CHAI & ASSOCIATE6481109/27/2023
ALLEN SHINFELD, P.E. PLLC1305204/13/2022
YL DESIGN GROUP LLC7584109/10/2020
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offALL DAY PLUMBING HEATI*01/08/2025
DOB NOWPlumbingSigned-offRRP PLUMBING CORP12/04/2023
DOB NOWGeneral ConstructionSigned-offBERN CONCEPT INC10/10/2023
DOB NOWMechanical SystemsSigned-offNEW KAMPAR INC04/19/2022
DOB NOWMechanical SystemsPermit IssuedNEW KAMPAR INC02/02/2022
DOB NOWMechanical SystemsSigned-offYILIN CONSTRUCTION INC09/29/2020
BISOTISSUEDTEAMWORK RESTORATION INC03/27/2017
BISPLISSUEDS & L PLUMBING INC01/20/2017
BISEQISSUEDB H & B CONSTRUCTION INC05/25/2011
BISPLISSUEDFINEST MECHANICAL CORP09/21/2009
BISOTISSUEDGLOBAL DESIGN TEAM CORP06/08/2009
BISMHISSUEDWELL CONSTRUCTION08/30/2004
BISSPISSUEDL.R.P. CONSTRUCTION04/30/2004
BISMHISSUEDGRAND BUILDER CONTR. INC.04/14/2004
BISPLISSUEDS & L PLUMBING INC12/19/2003
BISMHISSUEDGRAND BUILDER CONTR. INC.11/17/2003
BISPLISSUEDK & BH PLUMBING & HTG INC05/02/2003
BISOTISSUEDGRACELAND DESIGN BUILD ASSOCI10/03/2000
BISOTISSUEDSERVICE SING & ERECTORS CO INC08/08/2000
BISOTISSUEDHKC CONSTRUCTION11/22/1999
BISPLISSUEDMAGOR PLUMBING & HEATING12/12/1997
BISOTISSUEDM KEE CONSTRUCTION INC11/20/1997
BISPLISSUEDCHINATOWN PLBG & HTG INC01/30/1997
BISPLISSUEDMAGOR PLUMBING HEATING09/05/1995
BISMHISSUEDS L T CONST INC08/17/1995
BISPLISSUEDCHINATOWN PLBG & HTG INC08/11/1994
BISOTRE-ISSUEDS/W WILSON ENTERPRISE INC07/05/1994
BISOTISSUEDBIN ZOHNGD/B/A AASTRFRNT. & SGN07/06/1993
BISPLISSUEDMAGOR PLUMBING & HEATING06/03/1992
BISOTISSUEDWING KIN INSTALLATION & MAIN INC05/28/1992
BISOTISSUED2828 CONTRACTORS05/27/1992
BISPLISSUEDWASOFF PLBG & UTILITY CO03/25/1992
BISEQISSUEDUNITED HOISTING_CO.01/31/1992
BISOTISSUEDWING KIN INSTALLATION & MAIN INC01/31/1992
BIS—ISSUEDYOUNG'S CONST CO INC01/17/1992
BISEQISSUEDUNITED HOISTING COMPANY INC04/15/1991
BISFAISSUEDELECTRO MAGNETIC CORP.03/14/1991
BISEQISSUEDUNITED HOISTING01/30/1991
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
02/22/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/14/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
09/27/2023HVAC-R and service water piping design and insulationJoon Ho Chaienergy_progress
09/27/2023Maintenance informationJoon Ho Chaienergy_progress
09/27/2023Energy Code Compliance InspectionsJoon Ho Chaiprogress
09/27/2023Fire-Resistance Rated ConstructionJoon Ho Chaiprogress
09/27/2023Lighting controlsJoon Ho Chaienergy_progress
09/27/2023Maintenance informationJoon Ho Chaienergy_progress
09/27/2023Interior lighting powerJoon Ho Chaienergy_progress
09/27/2023Fire-Resistant Penetrations and JointsJoon Ho Chaispecial
09/22/2023FinalJIN WOO LEEprogress
03/05/2022FinalALLEN SHINFELDprogress
03/05/2022HVAC-R and service water heating equipmentALLEN SHINFELDenergy_progress
03/05/2022HVAC-R and service water heating system controlsALLEN SHINFELDenergy_progress
03/05/2022Mechanical SystemsALLEN SHINFELDspecial
03/05/2022Energy Code Compliance InspectionsALLEN SHINFELDprogress
12/21/2021Mechanical SystemsALLEN SHINFELDspecial
12/21/2021HVAC-R and service water heating equipmentALLEN SHINFELDenergy_progress
12/21/2021HVAC-R and service water heating system controlsALLEN SHINFELDenergy_progress
12/21/2021Energy Code Compliance InspectionsALLEN SHINFELDprogress
12/21/2021FinalALLEN SHINFELDprogress
▾Documents — 123 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch6
09/03/2026M00646539-P1Request digital key ↗
09/03/2026M00646539-I1Request digital key ↗
09/02/2026M00692627-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00394347-I1Request digital key ↗
▸Applications & Permits18
▸BISPLAN / WORK APPROVAL APPLICATION12
01/05/2018102766437Open ↗
01/05/2018102766437Open ↗
01/31/2017122647421Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION6
04/03/2017122647421Open ↗
01/24/2017102766437Open ↗
05/31/2011120703694Open ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications41
▸DOB NOWProgress Inspector Seal & Signature13
09/05/2026M00646539-I1Open ↗
09/05/2026M00646539-I1Open ↗
09/05/2026M00646539-I1Open ↗
Showing 3 of 13 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION12
05/24/2017122647421Open ↗
03/23/2017122647421Open ↗
03/16/2017102766437Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature7
08/25/2026M01126031-I1Open ↗
08/13/2026M00692627-I1Open ↗
08/13/2026M00938063-S1Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
05/31/2011120703694Open ↗
07/29/2009120118746Open ↗
06/04/2009120054868Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
05/31/2011120703694Open ↗
07/29/2009120118746Open ↗
06/04/2009120054868Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
09/05/2026M00646539-I1Open ↗
09/01/2026M00692627-I1Open ↗
08/25/2026M00938063-I1Open ↗
▸Trade Schedules & Equipment8
▸BISSCHEDULE B - PLUMBING4
02/05/2010120118746Open ↗
01/13/2010120118746Open ↗
01/06/2010120118746Open ↗
Showing 3 of 4 on file for this type
▸BISSELF-CERT PLUMBING NOTICE2
05/07/2010120118746Open ↗
04/20/2010120118746Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
06/26/2018121415067Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
01/27/2017102766437Open ↗
▸Safety & Tenant Protection1
▸BISST-1 Street Tree Checklist1
06/04/2009120054868Open ↗
▸Environmental & Asbestos8
▸BISTHIS IS NOT AN ASBESTOS PROJECT2
07/29/2009120118746Open ↗
07/29/2009120118746Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
05/31/2011120703694Open ↗
06/04/2009120054868Open ↗
▸BISASBESTOS-CERTIFICATION (DEP ACP5)2
12/03/2012121415067Open ↗
01/31/2017122647421Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/13/2026M00938063-S1Open ↗
08/13/2026M00938063-I1Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
03/23/2017122647421Open ↗
03/16/2017102766437Open ↗
02/27/2017102766437Open ↗
Showing 3 of 4 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS2
05/24/2017122647421Open ↗
02/27/2017102766437Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026M00692627-I1Open ↗
▸Approvals, Objections & Sign-offs12
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
01/03/2019100167597Open ↗
12/26/2018100229646Open ↗
07/02/2018121415067Open ↗
Showing 3 of 7 on file for this type
▸BISADMINISTRATIVE OBJECTIONS5
12/03/2012121415067Open ↗
05/31/2011120703694Open ↗
07/29/2009120118746Open ↗
Showing 3 of 5 on file for this type
▸Cost, Insurance & Ownership10
▸BISCOST AFFIDAVIT10
07/02/2018121415067Open ↗
05/24/2017122647421Open ↗
03/16/2017102766437Open ↗
Showing 3 of 10 on file for this type
▸Filing & Intake Forms11
▸BISEFILING COVER SHEET5
01/31/2017122647421Open ↗
01/23/2014121902405Open ↗
12/03/2012121415067Open ↗
Showing 3 of 5 on file for this type
▸BISADDITIONAL INFORMATION3
01/05/2018102766437Open ↗
01/05/2018102766437Open ↗
01/27/2017102766437Open ↗
▸BISBOROUGH INTAKE FORM3
01/03/2019100167597Open ↗
12/26/2018100229646Open ↗
07/02/2018121415067Open ↗