← Back
Two family converted from one family
1981 53 STREET
BROOKLYN · BIN 3130076
💬 Discuss this project
1925Year Built
2Stories
B3Building Class
R5Zoning
1,632 sfGross Floor Area
2Units
2 Open Violations ▸FDNY Report ↗
Two family converted from one family · Owner of record: 1981 53 TYH LLC · 2,003 sf lot · 0.81 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingLandscapeGeneral
Roof31p · 1 filing · 20 docs
Floor 333p · 1 filing · 20 docs
Floor 234p · 1 filing · 20 docs
Floor 129p · 1 filing · 20 docs
Cellar39p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEW AMERICAN CONSTRUCTION INC1807/08/2026
FETTMAN DESIGN303/22/2026
1981 53 TYH LLC203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/21/2022$995K—CONG. SANZ OF LAKEWOOD, INC. → Private party$610/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MARK WEINBERGER ARCHITECT PLLC312/09/2024
CHOSEN MEP, CORP.312/05/2024
MJE PROFESSIONAL SERVICES602/09/2024
SH ENGINEERING PLLC204/18/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BMG GROUP USA603/21/2026
BizfiGroup203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FETTMAN DESIGN LLCGeneral Contractor1907/08/2026
NEW AMERICAN CONSTRUCTION INCGeneral Contractor707/08/2026
ROM PIPING & HTG INCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AA BUILDING & INSPECTION1519712/09/2024
Building Lifecycle
All (117)Filed (14)Permit Issued (14)Signed Off (8)Violation (5)Inspection (8)Objection (38)Special Inspection (30)
07/28/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/29/2025
Violation issued (ECB, open)
Construction
05/29/2025
Violation issued (ECB, open)
Construction
01/24/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/20/2025
Signed off — Alteration CO
support of excavation and foundation filled in conjunction with alt1 filing number b00818107_i1
B00818107-S6
01/14/2025
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
12/26/2024
Special inspection requirement — Insulation placement and R values
Younes Abouyaala
12/26/2024
Special inspection requirement — Protection of exposed foundation insulation
Younes Abouyaala
12/26/2024
Special inspection requirement — Maintenance information
Younes Abouyaala
12/26/2024
Special inspection requirement — Electric vehicle service equipment requirements
Younes Abouyaala
12/26/2024
Special inspection requirement — Air barrier — testing
Younes Abouyaala
12/26/2024
Special inspection requirement — Fenestration areas
Younes Abouyaala
12/26/2024
Special inspection requirement — Fenestration air leakage
Younes Abouyaala
12/26/2024
Special inspection requirement — Air barrier - visual inspection
Younes Abouyaala
12/26/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
12/26/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Younes Abouyaala
12/26/2024
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Younes Abouyaala
12/26/2024
Special inspection requirement — Energy Code Compliance Inspections
Younes Abouyaala
12/26/2024
Special inspection requirement — Fire-Resistance Rated Construction
Younes Abouyaala
12/26/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
Younes Abouyaala
12/26/2024
Special inspection requirement — Permanent certificate
Younes Abouyaala
12/19/2024
Objection resolved — Addressed
12/19/2024
Objection resolved — Addressed
12/19/2024
Objection resolved — Addressed
12/17/2024
Objection raised — Other
12/17/2024
Objection raised — Other
12/17/2024
Objection raised — Other
12/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Younes Abouyaala
12/17/2024
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Younes Abouyaala
12/17/2024
Special inspection requirement — Maintenance information
Younes Abouyaala
12/17/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Younes Abouyaala
12/17/2024
Special inspection requirement — HVAC-R and service water heating equipment
Younes Abouyaala
12/17/2024
Special inspection requirement — HVAC-R and service water heating system controls
Younes Abouyaala
12/09/2024
Filed — Alteration CO
support of excavation and foundation filled in conjunction with alt1 filing number b00818107_i1
B00818107-P1
12/05/2024
Filed — Alteration CO
support of excavation and foundation filled in conjunction with alt1 filing number b00818107_i1
B00818107-P2
11/25/2024
Permit issued — General Construction
B00818107-I1-GC
11/19/2024
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
11/06/2024
Signed off — Alteration CO
support of excavation and foundation filled in conjunction with alt1 filing number b00818107_i1
B00818107-S7
11/05/2024
Signed off — Alteration CO
support of excavation and foundation filled in conjunction with alt1 filing number b00818107_i1
B00818107-S2
10/17/2024
Permit issued — General Construction
B00818107-I1-GC
09/24/2024
Permit issued — Construction Fence
B00818107-S2-FN
09/24/2024
Permit issued — Mechanical Systems
B00818107-S7-MS
09/20/2024
Violation issued (ECB, closed)
Construction
09/20/2024
Violation issued (ECB, closed)
Construction
09/17/2024
Permit issued — Plumbing
B00818107-S6-PL
07/02/2024
Signed off — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SHALL COMPLY WITH CHAPTER#33 OF 2022 NYC BUILDING CODE.
B00965370-I1
07/02/2024
Signed off — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00963175-I1
07/02/2024
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00965361-I1
05/22/2024
Signed off — Alteration CO
support of excavation and foundation filled in conjunction with alt1 filing number b00818107_i1
B00818107-S3
05/22/2024
Signed off — Alteration CO
support of excavation and foundation filled in conjunction with alt1 filing number b00818107_i1
B00818107-S4
05/06/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/12/2024
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/11/2024
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
03/18/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/09/2024
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00965361-P1
02/02/2024
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00963175-P2
12/05/2023
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00963175-P1
11/21/2023
Permit issued — Protection and Mechanical Methods
B00965370-I1-PMM
11/21/2023
Permit issued — Supported Scaffold
B00965361-I1-SF
11/20/2023
Filed — Alteration
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SHALL COMPLY WITH CHAPTER#33 OF 2022 NYC BUILDING CODE.
B00965370-I1
Latest 60 of 117 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedFETTMAN DESIGN LLC11/25/2024
DOB NOWGeneral ConstructionPermit IssuedFETTMAN DESIGN LLC10/17/2024
DOB NOWConstruction FenceSigned-offFETTMAN DESIGN LLC09/24/2024
DOB NOWMechanical SystemsSigned-offFETTMAN DESIGN LLC09/24/2024
DOB NOWPlumbingSigned-offROM PIPING & HTG INC09/17/2024
DOB NOWProtection and Mechanical MethodsSigned-offNEW AMERICAN CONSTRUCTION11/21/2023
DOB NOWSupported ScaffoldSigned-offNEW AMERICAN CONSTRUCTION11/21/2023
DOB NOWSidewalk ShedSigned-offNEW AMERICAN CONSTRUCTION11/20/2023
DOB NOWPlumbingSigned-offROM PIPING & HTG INC10/12/2023
DOB NOWStructuralSigned-offFETTMAN DESIGN LLC05/25/2023
DOB NOWGeneral ConstructionPermit IssuedFETTMAN DESIGN LLC05/25/2023
DOB NOWFoundationSigned-offFETTMAN DESIGN LLC05/16/2023
DOB NOWGeneral ConstructionPermit IssuedFETTMAN DESIGN LLC04/27/2023
DOB NOWConstruction FenceSigned-offFETTMAN DESIGN LLC04/21/2023
1 project · most recent 12/09/2024
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
12/09/2024Permit IssuedFETTMAN DESIGN LLCHeating and Air Conditioning Systems
Heat / Cool
Mitsubishi Electric Make: MITSUBISHI Model: MXZ-SM60NAM2 573,500 BTU · Vrf Outdoor ×9
1 project · most recent 12/09/2024
Gas Water/Sanitary
FiledStatusContractorScope
12/09/2024Signed-offROM PIPING & HTG INCGas, Water/Sanitary
3 projects · most recent 05/01/2024
General Wiring
FiledStatusContractorScope
05/01/2024CompleteGREEN STAR ELECTL CONT INGeneral Wiring
05/01/2024CompleteGREEN STAR ELECTL CONT IN—
11/17/2023CompleteRICHARD NEU—
1 project · most recent 12/09/2024
Steel Concrete
FiledStatusContractorScope
12/09/2024Permit IssuedFETTMAN DESIGN LLCSteel, Concrete
1 project · most recent 12/09/2024
Fence
FiledStatusContractorScope
12/09/2024Permit IssuedFETTMAN DESIGN LLCFence
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
07/28/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/24/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/14/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/19/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
05/06/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/12/2024Pass-Final General Construction Non-Directive 14PassView ↗
04/11/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
03/18/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 44
DateRequirementInspectorRole
12/26/2024Insulation placement and R valuesYounes Abouyaalaenergy_progress
12/26/2024Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
12/26/2024Maintenance informationYounes Abouyaalaenergy_progress
12/26/2024Electric vehicle service equipment requirementsYounes Abouyaalaenergy_progress
12/26/2024Air barrier — testing Younes Abouyaalaenergy_progress
12/26/2024Fenestration areasYounes Abouyaalaenergy_progress
12/26/2024Fenestration air leakageYounes Abouyaalaenergy_progress
12/26/2024Air barrier - visual inspectionYounes Abouyaalaenergy_progress
12/26/2024Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
12/26/2024Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
12/26/2024Construction Operations Influencing Adjacent StructuresYounes Abouyaalaspecial
12/26/2024Energy Code Compliance InspectionsYounes Abouyaalaprogress
12/26/2024Fire-Resistance Rated ConstructionYounes Abouyaalaprogress
12/26/2024Fenestration and door U-factor and product ratingsYounes Abouyaalaenergy_progress
12/26/2024Permanent certificateYounes Abouyaalaenergy_progress
12/17/2024Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
12/17/2024Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationYounes Abouyaalaspecial
12/17/2024Maintenance informationYounes Abouyaalaenergy_progress
12/17/2024HVAC-R and service water piping design and insulationYounes Abouyaalaenergy_progress
12/17/2024HVAC-R and service water heating equipmentYounes Abouyaalaenergy_progress
12/17/2024HVAC-R and service water heating system controlsYounes Abouyaalaenergy_progress
06/07/2023Protection of exposed foundation insulationYounes Abouyaalaenergy_progress
06/07/2023Construction Operations Influencing Adjacent StructuresYounes Abouyaalaspecial
06/07/2023Fire-Resistant Penetrations and JointsYounes Abouyaalaspecial
06/07/2023Structural Stability – Alterations of existing buildingsYounes Abouyaalaspecial
Latest 25 of 44.
▾Documents — 69 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch14
08/27/2026B00818107-S6Request digital key ↗
08/27/2026B00818107-P2Request digital key ↗
08/27/2026B00818107-S7Request digital key ↗
Showing 3 of 14 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026B00818107-P1Open ↗
08/13/2026B00818107-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00818107-I1Open ↗
▸Seals & Professional Certifications28
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/27/2026B00818107-S6Open ↗
08/27/2026B00818107-P2Open ↗
08/27/2026B00818107-S7Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature9
09/01/2026B00818107-S6Open ↗
09/01/2026B00818107-S6Open ↗
09/01/2026B00818107-S6Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/01/2026B00818107-S6Open ↗
09/01/2026B00818107-S6Open ↗
09/01/2026B00818107-S3Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/13/2026B00818107-P1Open ↗
08/13/2026B00818107-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00818107-I1Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/27/2026B00818107-P2Open ↗
08/27/2026B00818107-S7Open ↗
08/27/2026B00818107-S6Open ↗
Showing 3 of 8 on file for this type
▸Inspections & Test Reports3
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B00818107-S4Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026B00818107-S4Open ↗
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026B00818107-S4Open ↗
▸Other Documents10
▸DOB NOWPlot Diagram3
08/13/2026B00818107-P1Open ↗
08/13/2026B00818107-S4Open ↗
08/13/2026B00818107-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026B00818107-P1Open ↗
08/13/2026B00818107-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026B00818107-I1Open ↗
08/13/2026B00818107-P1Open ↗
▸DOB NOWProperty Ownership Certification2
08/27/2026B00818107-P1Open ↗
08/15/2026B00818107-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00818107-I1Open ↗