| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/24/2020 | $3.4M | — | — → — | $900/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CHARLES G. MICHEL ENGINEERING, PC. | 5 | 07/17/2026 |
| SOLK ARCHITECTURE PLLC | 2 | 07/16/2026 |
| MARTOS ENGINEERING | 3 | 02/18/2026 |
| CWB ARCHITECTS | 5 | 02/23/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| J CALLAHAN CONSULTING | 16 | 03/21/2026 |
| EC BUILDING CONSULTANTS | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| E.L. CONTRACTING INC | General Contractor | 8 | 07/08/2026 |
| CONSTRUCTION BROOKLYN INC | General Contractor | 4 | 07/08/2026 |
| ARCON PLBG SOLUTIONS | Plumbing | 3 | 07/08/2026 |
| FOCUS ELECTRICAL INC | Electrical | 1 | 03/22/2026 |
| HANUKA ELYAGUOV | Electrical | 1 | 03/21/2026 |
| BLAZE PLUMBING & HEATING | Plumbing | 1 | 09/18/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CHRISTIAN L. MARTOS ENGIN | 5965 | 3 | 02/18/2026 |
| THE BROOKLYN STUDIO OF AR | 2684 | 1 | 08/19/2022 |
| CHARLES G MICHEL ENGINEER | 2871 | 1 | 08/25/2021 |
| FRAME DESIGN AND CONSTRUC | 7971 | 1 | 07/26/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | BLAZE PLUMBING & HEATING | 09/17/2026 |
| DOB NOW | General Construction | Permit Issued | CONSTRUCTION BROOKLYN INC | 06/05/2026 |
| DOB NOW | Structural | Permit Issued | CONSTRUCTION BROOKLYN INC | 06/05/2026 |
| DOB NOW | General Construction | Permit Issued | CONSTRUCTION BROOKLYN INC | 04/28/2026 |
| DOB NOW | Structural | Permit Issued | CONSTRUCTION BROOKLYN INC | 04/27/2026 |
| DOB NOW | Mechanical Systems | Signed-off | EL CONTRACTING INC | 11/14/2022 |
| DOB NOW | General Construction | Signed-off | EL CONTRACTING INC | 11/14/2022 |
| DOB NOW | Plumbing | Signed-off | ARCON PLBG SOLUTIONS | 02/11/2022 |
| DOB NOW | Mechanical Systems | Signed-off | EL CONTRACTING INC | 11/29/2021 |
| DOB NOW | General Construction | Signed-off | EL CONTRACTING INC | 11/29/2021 |
| DOB NOW | Structural | Signed-off | EL CONTRACTING INC | 11/23/2021 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/17/2026 | — | — | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-SM48NLHZ 4 tons · Condensing Unit ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/17/2026 | Permit Issued | BLAZE PLUMBING & HEATING | Gas, Water/Sanitary |
| 02/23/2023 | Signed-off | DONATO PLUMBING, INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/13/2023 | Complete | FOCUS ELECTRICAL INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/10/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/06/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/03/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 10/06/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/29/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/05/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Water Test | Certified | View ↗ |
| 08/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/01/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/26/2022 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/25/2022 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/21/2026 | Final | Charles Michel | progress |
| 09/21/2026 | Fire-Resistant Penetrations and Joints | ANA ACCETTA | special |
| 09/21/2026 | Mechanical Systems | Charles Michel | special |
| 08/14/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/17/2026 | Final | LEAH SOLK | progress |
| 06/29/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/29/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/29/2026 | Mechanical Systems | — | special |
| 06/29/2026 | Final | — | progress |
| 06/29/2026 | Final | LEAH SOLK | progress |
| 08/19/2022 | Chimneys and vents | SURESH WARREN | special |
| 08/19/2022 | Final | SURESH WARREN | progress |
| 08/19/2022 | Fire-Resistance Rated Construction | SURESH WARREN | progress |
| 08/19/2022 | Fire-Resistant Penetrations and Joints | SURESH WARREN | special |
| 07/28/2022 | Fire-Resistance Rated Construction | BRENDAN COBURN | progress |
| 07/28/2022 | Final | BRENDAN COBURN | progress |
| 07/28/2022 | Fire-Resistant Penetrations and Joints | BRENDAN COBURN | special |
| 07/28/2022 | Chimneys and vents | BRENDAN COBURN | special |
| 01/27/2022 | Structural Steel - Details | Christian Martos | special |
| 01/27/2022 | Structural Steel - Welding | Christian Martos | special |
| 01/27/2022 | Final | Christian Martos | progress |
| 01/27/2022 | Structural Wood Frame | Christian Martos | progress |
| 01/27/2022 | Masonry | Christian Martos | special |
| 01/27/2022 | Post-installed Anchors | Christian Martos | special |
| 01/27/2022 | Structural Stability – Alterations of existing buildings | Christian Martos | special |