| Firm | Filings | Most Recent |
|---|---|---|
| REVAP CONSULTING ENGINEERS LLC | 1 | 10/16/2023 |
| FISCHER MAKOOI ARCHITECTS PLLC | 4 | 08/16/2023 |
| A&D ENGINEERING, PLLC | 3 | 07/25/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| JM ZONING, LLC. | 7 | 03/21/2026 |
| ZV Drafting | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| A.E. CONSTRUCTION, LLC | General Contractor | 2 | 03/21/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | AE CONSTRUCTION | 11/08/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/16/2023 | — | — | Air Conditioning Systems, Associated Ducts and Piping |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/16/2023 | — | — | 80 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/16/2023 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/16/2023 | — | — | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/16/2023 | Permit Issued | A.E. CONSTRUCTION, LLC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/24/2023 | Duct leakage testing, insulation and design | — | energy_progress |
| 11/02/2023 | Post-installed Anchors | — | special |
| 10/16/2023 | Maintenance information | — | energy_progress |
| 08/16/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 07/11/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 07/11/2023 | Sprinkler Systems | — | special |
| 07/05/2023 | Helical Piles Foundation (BB # 2014-020) | — | special |
| 07/05/2023 | Deep Foundation Elements | — | special |
| 06/08/2023 | Structural Steel - High Strength Bolting | — | special |
| 06/08/2023 | Structural Steel - Welding | — | special |
| 06/08/2023 | Final | — | progress |
| 06/08/2023 | Concrete - Cast-In-Place | — | special |
| 06/08/2023 | Subgrade Inspections | — | special |
| 06/08/2023 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 06/08/2023 | Final | — | progress |
| 06/08/2023 | Footing and Foundation | — | progress |
| 06/08/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 06/08/2023 | Heating Systems | — | special |
| 06/08/2023 | Mechanical Systems | — | special |
| 06/08/2023 | Fire-Resistance Rated Construction | — | progress |
| 06/08/2023 | Energy Code Compliance Inspections | — | progress |
| 06/08/2023 | Final | — | progress |
| 06/08/2023 | HVAC-R and service water heating equipment | — | energy_progress |
| 06/08/2023 | HVAC-R and service water heating system controls | — | energy_progress |
| 06/08/2023 | HVAC-R and service water piping design and insulation | — | energy_progress |