| Owner | Filings | Most Recent |
|---|---|---|
| OEE GROUP | 60 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JING XIE | 3 | 06/16/2026 |
| XIU CHEN | 6 | 02/13/2026 |
| HM LOKE CONSULTING ENGINEERING PC | 1 | 09/12/2024 |
| MY ARCHITECT PC | 2 | 09/28/2023 |
| A & T ENGINEERING, P.C. | 2 | 05/23/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| AJ EXPEDITING | 4 | 03/21/2026 |
| JT ENGINEERING, PC | 4 | 03/21/2026 |
| MY ARCHITECT | 4 | 03/21/2026 |
| HM LOKE CONSULTING ENGINEERING PC | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| POWER RHC INC | General Contractor | 28 | 07/08/2026 |
| NY DRILLING INC | General Contractor | 4 | 07/08/2026 |
| RRP PLUMBING CORP | Plumbing | 2 | 07/08/2026 |
| RRP PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| MPS PLUMBING & HEATING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ARK ENGINEERING PC | 7261 | 10 | 06/16/2026 |
| TRIANGLE INSPECTION & TES | 7495 | 2 | 06/16/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | RRP PLUMBING CORP | 05/26/2026 |
| DOB NOW | Construction Fence | Permit Issued | POWER RHC INC | 01/20/2026 |
| DOB NOW | General Construction | Permit Issued | POWER RHC INC | 01/20/2026 |
| DOB NOW | Sprinklers | Permit Issued | RALPH W. LANDOLFI JR. | 11/14/2025 |
| DOB NOW | Plumbing | Permit Issued | RRP PLUMBING CORP | 05/23/2025 |
| DOB NOW | General Construction | Permit Issued | POWER RHC INC | 12/23/2024 |
| DOB NOW | Support of Excavation | Permit Issued | POWER RHC INC | 12/20/2024 |
| DOB NOW | Construction Fence | Permit Issued | POWER RHC INC | 12/20/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | POWER RHC INC | 12/20/2024 |
| DOB NOW | Structural | Permit Issued | POWER RHC INC | 12/20/2024 |
| DOB NOW | Foundation | Permit Issued | POWER RHC INC | 12/20/2024 |
| DOB NOW | Support of Excavation | Permit Issued | POWER RHC INC | 10/01/2024 |
| DOB NOW | Construction Fence | Permit Issued | POWER RHC INC | 09/12/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | POWER RHC INC | 08/30/2024 |
| DOB NOW | General Construction | Permit Issued | POWER RHC INC | 08/28/2024 |
| DOB NOW | Structural | Permit Issued | POWER RHC INC | 08/27/2024 |
| DOB NOW | Foundation | Permit Issued | POWER RHC INC | 08/27/2024 |
| DOB NOW | Plumbing | Permit Issued | MPS PLUMBING & HEATING IN | 06/05/2024 |
| DOB NOW | Full Demolition | Signed-off | NY DRILLING INC | 09/04/2023 |
| DOB NOW | Construction Fence | Signed-off | NY DRILLING INC | 08/29/2023 |
| BIS | — | ISSUED | FOUR SEASONS OF MANHASSET | 08/22/1989 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/16/2026 | Permit Issued | POWER RHC INC | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/28/2025 | Permit Issued | INTELOGIC ELECTRIC, INC. | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/26/2026 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 04/21/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/21/2025 | Pass-Final House Connection | Pass | View ↗ |
| 07/17/2025 | Pass-Final PL - Underground | Pass | View ↗ |
| 02/13/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 02/13/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/25/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | George Lau | special |
| 11/25/2025 | Fire-Resistant Penetrations and Joints | George Lau | special |
| 11/25/2025 | HVAC-R and service water heating system controls | XIU CHEN | energy_progress |
| 11/25/2025 | HVAC-R and service water piping design and insulation | XIU CHEN | energy_progress |
| 11/25/2025 | Maintenance information | XIU CHEN | energy_progress |
| 11/25/2025 | HVAC-R and service water heating equipment | XIU CHEN | energy_progress |
| 11/25/2025 | Energy Code Compliance Inspections | XIU CHEN | progress |
| 11/25/2025 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Rajasekhar Sakhamuri | special |
| 10/01/2024 | Subgrade Inspections | George Lau | special |
| 10/01/2024 | Excavations - Sheeting, Shoring, and Bracing | George Lau | special |
| 08/29/2024 | Subgrade Inspections | George Lau | special |
| 08/29/2024 | Excavations - Sheeting, Shoring, and Bracing | George Lau | special |
| 01/19/2024 | Concrete - Cast-In-Place | George Lau | special |
| 01/19/2024 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 01/19/2024 | Structural Steel - Welding | George Lau | special |
| 01/19/2024 | Structural Steel - High Strength Bolting | George Lau | special |
| 01/19/2024 | Concrete - Cast-In-Place | George Lau | special |
| 01/10/2024 | Electric vehicle service equipment requirements | George Lau | energy_progress |
| 11/16/2023 | Final | George Lau | progress |
| 11/16/2023 | Footing and Foundation | George Lau | progress |
| 11/16/2023 | Final | George Lau | progress |
| 08/21/2023 | Metering | George Lau | energy_progress |
| 08/21/2023 | Fenestration areas | George Lau | energy_progress |
| 08/21/2023 | Subgrade Inspections | George Lau | special |
| 08/21/2023 | Air barrier - visual inspection | George Lau | energy_progress |