| Owner | Filings | Most Recent |
|---|---|---|
| NOEL CONSULTANTS | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| NASIR J, KHANZADA LLC | 1 | 03/25/2026 |
| DOWNTOWN ENGINEERS | 2 | 03/18/2026 |
| MELTZER/MANDL ARCHITECTS, P.C. | 1 | 03/11/2026 |
| LEVIN ENGINEERING PLLC | 2 | 03/21/2022 |
| RICHARD WAINER ARCHITECT, PLLC | 1 | 01/24/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| LEVIN ENGINEERING PLLC | 4 | 03/21/2026 |
| SWA ARCHITECTURE | 2 | 03/21/2026 |
| REDCUT EXPEDITING | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMBROSINO CONST CORP | General Contractor | 3 | 07/08/2026 |
| MICHAEL SHEA | Electrical | 1 | 03/21/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TRIANGLE INSPECTION & TES | 7495 | 3 | 03/21/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | SAFETY FIRE SPRINKLER CORP | 04/07/2022 |
| DOB NOW | Mechanical Systems | Signed-off | AMBROSINO CONST | 04/06/2022 |
| DOB NOW | General Construction | Signed-off | AMBROSINO CONST | 03/25/2022 |
| BIS | MH | ISSUED | PLN INC | 03/04/2020 |
| BIS | SP | ISSUED | ASHLAR MECHANICAL CORP | 06/09/2014 |
| BIS | PL | ISSUED | FOUNTAIN OF TREVI, INC | 04/30/2014 |
| BIS | OT | ISSUED | AMBROSINO CONST CORP | 04/17/2014 |
| BIS | MH | ISSUED | AMBROSINO CONST CORP | 04/17/2014 |
| BIS | PL | ISSUED | ADVANCED PLBG LLC | 08/16/2011 |
| BIS | PL | ISSUED | ADVANCED PLBG LLC | 06/01/2010 |
| BIS | MH | ISSUED | PAUL M MAINTENANCE INC | 04/14/2010 |
| BIS | OT | ISSUED | PAUL M MAINTENANCE INC | 04/14/2010 |
| BIS | PL | ISSUED | MAJOR SEWER & WATER | 12/18/2007 |
| BIS | — | ISSUED | AMBROSINO CONST CORP | 06/14/2007 |
| BIS | PL | ISSUED | FOUNTAIN OF TREVI, INC | 01/04/2007 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/18/2026 | — | — | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/18/2026 | — | — | 4 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/18/2026 | — | — | Storm |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/08/2022 | Complete | KGB ELEC'L CONTR'G CORP | General Wiring |
| 03/14/2019 | Permit Issued | WILLDAN ELECTRICAL OF NY | General Wiring |
| 03/07/2019 | Permit Issued | WILLDAN ELECTRICAL OF NY | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/25/2026 | — | — | Steel |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/17/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/17/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/17/2026 | Shutoff dampers | — | energy_progress |
| 03/17/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 03/17/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/17/2026 | Post-installed Anchors | — | special |
| 03/17/2026 | Energy Code Compliance Inspections | — | progress |
| 03/17/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/17/2026 | Maintenance information | — | energy_progress |
| 03/10/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 02/19/2026 | Interior lighting power | — | energy_progress |
| 02/19/2026 | Fenestration air leakage | — | energy_progress |
| 02/19/2026 | Fenestration areas | — | energy_progress |
| 02/19/2026 | Air barrier - visual inspection | — | energy_progress |
| 02/19/2026 | Lighting controls | — | energy_progress |
| 02/19/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 02/19/2026 | Protection of exposed foundation insulation | — | energy_progress |
| 02/19/2026 | Insulation placement and R values | — | energy_progress |
| 02/19/2026 | Exterior lighting power | — | energy_progress |
| 02/19/2026 | Fire-Resistance Rated Construction | — | progress |
| 02/19/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 02/19/2026 | Energy Code Compliance Inspections | — | progress |
| 02/19/2026 | Final | — | progress |
| 02/17/2026 | Mechanical Systems | — | special |
| 02/17/2026 | Final | — | progress |