| Owner | Filings | Most Recent |
|---|---|---|
| St Peters Boys High School | 40 | 10/13/2026 |
| Sts. Peter and Paul and Assumption | 5 | 03/22/2026 |
| RC Church St Peter | 4 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Rampulla Associates Architects | 3 | 08/27/2026 |
| George Sigalos | 2 | 08/21/2026 |
| Zee Structural Engineering | 2 | 08/13/2026 |
| C&P Design Consultants | 2 | 05/22/2024 |
| NY AC | 1 | 05/26/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| Municipal Building Consultants | 1 | 03/21/2026 |
| Largime Mujovic | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Daggart of Richmond | General Contractor | 3 | 08/25/2026 |
| Flag Contracting | General Contractor | 3 | 03/21/2026 |
| Perciballi Industries | General Contractor | 2 | 03/21/2026 |
| Sken Services | Scaffold | 2 | 03/21/2026 |
| Daggart of Richmond | Scaffold | 1 | 08/26/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A Tech Engineering NYC, P | 6738 | 4 | 08/27/2026 |
| SRA Planning & Expediting | 5677 | 1 | 05/22/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | Daggart of Richmond | 08/24/2026 |
| DOB NOW | Structural | Permit Issued | Daggart of Richmond | 08/19/2026 |
| DOB NOW | Foundation | Permit Issued | Daggart of Richmond | 08/19/2026 |
| DOB NOW | Construction Fence | Permit Issued | Daggart of Richmond | 08/03/2026 |
| DOB NOW | Full Demolition | Signed-off | Perciballi Industries | 06/24/2024 |
| DOB NOW | Construction Fence | Signed-off | TT & T Construction | 04/30/2024 |
| DOB NOW | General Construction | Signed-off | Flag Contracting | 06/16/2021 |
| BIS | PL | ISSUED | Scaran Plumbing | 01/15/2021 |
| BIS | BL | ISSUED | Scaran Plumbing | 01/15/2021 |
| BIS | FB | ISSUED | Scaran Oil Service Co | 10/23/2018 |
| BIS | BL | ISSUED | Scaran Plumbing | 10/05/2018 |
| BIS | PL | ISSUED | Scaran Plumbing | 10/05/2018 |
| BIS | PL | ISSUED | JB Buzco Plumbing | 08/01/2012 |
| BIS | OT | ISSUED | Umana Designs | 05/25/2012 |
| BIS | MH | ISSUED | Master Fire Prevent Systems I | 12/14/2010 |
| BIS | FP | ISSUED | Master Fire Systems | 12/13/2010 |
| BIS | PL | ISSUED | J & A Plumbing | 01/04/2010 |
| BIS | PL | ISSUED | J & A Plumbing | 09/17/2008 |
| BIS | — | ISSUED | Daggart of Richmond | 08/15/2008 |
| BIS | EQ | ISSUED | Daggart of Richmond | 08/15/2008 |
| BIS | OT | ISSUED | The Landtek Group | 07/14/2005 |
| BIS | OT | ISSUED | The Landtek Group | 01/28/2005 |
| BIS | MH | ISSUED | Peter Steven Quanci & Associates | 05/24/2001 |
| BIS | PL | ISSUED | Carmine's Mechanical | 12/14/2000 |
| BIS | PL | ISSUED | Carmine's Mechanical | 09/20/2000 |
| BIS | — | ISSUED | Daggart of Richmond | 09/01/2000 |
| BIS | EQ | ISSUED | Daggart of Richmond | 07/05/2000 |
| BIS | — | ISSUED | Daggart of Richmond | 07/05/2000 |
| BIS | OT | ISSUED | Bartlett Tree Experts | 02/22/2000 |
| BIS | OT | ISSUED | Bartlett Tree Experts | 10/21/1999 |
| BIS | OT | ISSUED | Cahill Tree Experts & Services | 09/24/1999 |
| BIS | OT | ISSUED | St Peters Boys High School | 01/11/1999 |
| BIS | OT | ISSUED | O'Connor Contracting | 04/16/1998 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/27/2026 | Permit Issued | Daggart of Richmond | Heating and Air Conditioning Systems | Heat / Cool Carrier MHP5-3-7-11-30FP 28,000 BTU · Heat Pump Outdoor ×4 MHP5-3-7-11-24FP 24,000 BTU · Heat Pump Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/21/2026 | Permit Issued | Fichera Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2026 | Permit Issued | Daggart of Richmond | Steel, Concrete |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/27/2026 | Lighting controls | anthony santoro | energy_progress |
| 08/27/2026 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 08/27/2026 | Insulation placement and R values | anthony santoro | energy_progress |
| 08/27/2026 | Exterior lighting power | anthony santoro | energy_progress |
| 08/27/2026 | Maintenance information | anthony santoro | energy_progress |
| 08/27/2026 | Fenestration areas | anthony santoro | energy_progress |
| 08/27/2026 | Excavations - Sheeting, Shoring, and Bracing | anthony santoro | special |
| 08/27/2026 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 08/27/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | anthony santoro | special |
| 08/27/2026 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 08/27/2026 | Energy Code Compliance Inspections | anthony santoro | progress |
| 08/27/2026 | Fire-Resistance Rated Construction | anthony santoro | progress |
| 08/27/2026 | Air barrier - visual inspection | anthony santoro | energy_progress |
| 08/27/2026 | Interior lighting power | anthony santoro | energy_progress |
| 08/27/2026 | Fenestration air leakage | anthony santoro | energy_progress |
| 08/17/2026 | HVAC-R and service water heating equipment | George Sigalos | energy_progress |
| 08/17/2026 | Mechanical Systems | — | special |
| 08/17/2026 | Final | — | progress |
| 08/17/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/17/2026 | HVAC-R and service water heating system controls | George Sigalos | energy_progress |
| 08/17/2026 | Shutoff dampers | George Sigalos | energy_progress |
| 08/04/2026 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 08/04/2026 | Footing and Foundation | anthony santoro | progress |
| 08/04/2026 | Final | anthony santoro | progress |
| 08/04/2026 | Structural Stability – Alterations of existing buildings | anthony santoro | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| St Peter's Boys School | Education | Sub-basement, Basement, Floor 1, Roof | Project S01372896 Project S01017658 Project S00522721 |