Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction24p · 1 filing · 20 docs
Floor 6Under Construction53p · 1 filing · 20 docs
Floor 5Under Construction54p · 1 filing · 20 docs
Floor 4Under Construction47p · 1 filing · 20 docs
Floor 3Under Construction50p · 1 filing · 20 docs
Floor 2Under Construction23p · 1 filing · 20 docs
Floor 1Under Construction50p · 1 filing · 20 docs
CellarUnder Construction54p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TITAN SERVICES USA309/13/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/05/2024$275K—C2618 DEVELOPMENT LLC → 200 MT. HOPE PLACE LLC— not available
05/08/2024$226K—Private party → MOUNT HOPE 200 LLC— not available
05/08/2024$165K—MOUNT HOPE 200 LLC → C2618 DEVELOPMENT LLC— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NODE ARCHITECTURE,ENGINEERING, CONS1205/29/2026
IKRA CONSULTING LLC105/14/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NODE ARCHITECTURE,ENGINEERING,CON2003/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AABM CONSTRUCTION CORPGeneral Contractor708/20/2026
TITAN SERVICES USA INCGeneral Contractor208/21/2026
PRIME PIPING & HEATING INFire Protection108/26/2026
HORBRIDGE PLUMBING & HEATINGPlumbing106/27/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NODE ARCHITECTURE,ENGINEE67991105/29/2026
INTERNATIONAL GEOTEHCNICA1795505/04/2026
Building Lifecycle
All (66)Filed (13)Permit Issued (11)Signed Off (1)Violation (7)Inspection (1)Special Inspection (30)Tax Incentive (3)
01/01/2027
485-x construction completed
08/20/2026
Permit issued — Sidewalk Shed
X01396154-I1-SH
08/18/2026
Permit issued — General Construction
X01217545-I1-GC
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Cranes and Derricks
08/03/2026
Violation issued (ECB, open)
Unknown
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/30/2026
Signed off — New Building
PLUMBING WORK FILED FOR NEW BUILDING.
X01217545-Z1
07/15/2026
Permit issued — Sprinklers
X01217545-S7-EW-SP
07/08/2026
Special inspection requirement — Protection of exposed foundation insulation
Radomir Delic
07/08/2026
Special inspection requirement — Fenestration air leakage
Radomir Delic
07/08/2026
Special inspection requirement — Metering
Radomir Delic
07/08/2026
Special inspection requirement — Lighting controls
Radomir Delic
07/08/2026
Special inspection requirement — Combustible Exterior Wall Coverings
Radomir Delic
07/08/2026
Special inspection requirement — Fenestration areas
Radomir Delic
07/08/2026
Special inspection requirement — Maintenance information
Radomir Delic
07/08/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Radomir Delic
07/08/2026
Special inspection requirement — Exterior lighting power
Radomir Delic
07/08/2026
Special inspection requirement — Insulation placement and R values
Radomir Delic
07/08/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Radomir Delic
07/08/2026
Special inspection requirement — Interior lighting power
Radomir Delic
07/08/2026
Special inspection requirement — Electrical motors and elevators
Radomir Delic
07/08/2026
Special inspection requirement — Lighting in dwelling units
Radomir Delic
07/08/2026
Special inspection requirement — Air barrier — testing
Radomir Delic
07/08/2026
Special inspection requirement — Air barrier - visual inspection
Radomir Delic
07/08/2026
Special inspection requirement — Energy Code Compliance Inspections
Radomir Delic
07/08/2026
Special inspection requirement — Fire-Resistance Rated Construction
Radomir Delic
06/25/2026
Permit issued — Plumbing
X01217545-S6-PL
05/29/2026
Filed — New Building
PLUMBING WORK FILED FOR NEW BUILDING.
X01217545-P3
05/26/2026
Special inspection requirement — Maintenance information
Radomir Delic
05/26/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Radomir Delic
05/26/2026
Special inspection requirement — Lighting controls
Radomir Delic
05/26/2026
Special inspection requirement — Fenestration areas
Radomir Delic
05/26/2026
Special inspection requirement — Electrical motors and elevators
Radomir Delic
05/26/2026
Special inspection requirement — Metering
Radomir Delic
05/26/2026
Special inspection requirement — Protection of exposed foundation insulation
Radomir Delic
05/26/2026
Special inspection requirement — Interior lighting power
Radomir Delic
05/26/2026
Special inspection requirement — Air barrier - visual inspection
Radomir Delic
05/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Radomir Delic
05/26/2026
Special inspection requirement — Combustible Exterior Wall Coverings
Radomir Delic
05/26/2026
Special inspection requirement — Fire-Resistance Rated Construction
Radomir Delic
05/22/2026
Permit issued — Structural
X01217545-Z2-ST
05/18/2026
Permit issued — Sidewalk Shed
X01396154-I1-SH
05/14/2026
Filed — Alteration
INSTALLATION OF 300PSF SIDEWALK SHED AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CH #33 OF THE NYC CODE 2022. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
X01396154-I1
05/04/2026
Filed — New Building
PLUMBING WORK FILED FOR NEW BUILDING.
X01217545-P2
04/08/2026
Violation issued (ECB, closed)
Construction
04/08/2026
Violation issued (ECB, closed)
Construction
04/07/2026
Violation issued (ECB, closed)
Construction
02/23/2026
Permit issued — General Construction
X01217545-I1-GC
02/19/2026
Filed — New Building
PLUMBING WORK FILED FOR NEW BUILDING.
X01217545-P1
01/26/2026
Permit issued — Support of Excavation
X01217545-Z1-SE
01/20/2026
Permit issued — Foundation
X01217545-Z3-FO
11/20/2025
485-x registration filed
11/07/2025
Permit issued — Foundation
X01217545-S9-FO
11/07/2025
485-x construction commenced
11/03/2025
Filed — New Building
PLUMBING WORK FILED FOR NEW BUILDING.
X01217545-Z3
10/28/2025
Permit issued — Construction Fence
X01217592-I1-FN
09/04/2025
Filed — New Building
PLUMBING WORK FILED FOR NEW BUILDING.
X01217545-S5
09/02/2025
Filed — New Building
PLUMBING WORK FILED FOR NEW BUILDING.
X01217545-Z1
Latest 60 of 66 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedTITAN SERVICES USA INC08/20/2026
DOB NOWGeneral ConstructionPermit IssuedAABM CONSTRUCTION CORP08/18/2026
DOB NOWSprinklersPermit IssuedPRIME PIPING & HEATING IN07/15/2026
DOB NOWPlumbingPermit IssuedHORBRIDGE PLUMBING & HEATING06/25/2026
DOB NOWStructuralPermit IssuedAABM CONSTRUCTION CORP05/22/2026
DOB NOWSidewalk ShedPermit IssuedTITAN SERVICES USA INC05/18/2026
DOB NOWGeneral ConstructionPermit IssuedAABM CONSTRUCTION02/23/2026
DOB NOWSupport of ExcavationSigned-offAABM CONSTRUCTION01/26/2026
DOB NOWFoundationSigned-offAABM CONSTRUCTION01/20/2026
DOB NOWFoundationPermit IssuedAABM CONSTRUCTION11/07/2025
DOB NOWConstruction FencePermit IssuedAABM CONSTRUCTION10/28/2025
2 projects · most recent 06/02/2026
General Wiring
FiledStatusContractorScope
06/02/2026Permit IssuedAV GROUP ELECTRICAL LLCGeneral Wiring
05/18/2026Permit IssuedRICHARD NEU—
2 projects · most recent 05/14/2026
Sidewalk Shed Fence
FiledStatusContractorScope
05/14/2026Permit IssuedTITAN SERVICES USA INCSidewalk Shed
07/07/2025Permit IssuedAABM CONSTRUCTION CORPFence
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
08/03/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 74
DateRequirementInspectorRole
07/08/2026Fire-Resistant Penetrations and JointsRadomir Delicspecial
07/08/2026Insulation placement and R valuesRadomir Delicenergy_progress
07/08/2026Electrical motors and elevatorsRadomir Delicenergy_progress
07/08/2026Lighting in dwelling unitsRadomir Delicenergy_progress
07/08/2026Exterior lighting powerRadomir Delicenergy_progress
07/08/2026Fenestration areasRadomir Delicenergy_progress
07/08/2026MeteringRadomir Delicenergy_progress
07/08/2026Fenestration and door U-factor and product ratingsRadomir Delicenergy_progress
07/08/2026Interior lighting powerRadomir Delicenergy_progress
07/08/2026Protection of exposed foundation insulationRadomir Delicenergy_progress
07/08/2026Lighting controlsRadomir Delicenergy_progress
07/08/2026Maintenance informationRadomir Delicenergy_progress
07/08/2026Air barrier - visual inspectionRadomir Delicenergy_progress
07/08/2026Fenestration air leakageRadomir Delicenergy_progress
07/08/2026Air barrier — testing Radomir Delicenergy_progress
07/08/2026Energy Code Compliance InspectionsRadomir Delicprogress
07/08/2026Fire-Resistance Rated ConstructionRadomir Delicprogress
07/08/2026Combustible Exterior Wall CoveringsRadomir Delicspecial
05/26/2026Air barrier - visual inspectionRadomir Delicenergy_progress
05/26/2026Combustible Exterior Wall CoveringsRadomir Delicspecial
05/26/2026Fire-Resistant Penetrations and JointsRadomir Delicspecial
05/26/2026Energy Code Compliance InspectionsRadomir Delicprogress
05/26/2026Fire-Resistance Rated ConstructionRadomir Delicprogress
05/26/2026MeteringRadomir Delicenergy_progress
05/26/2026Protection of exposed foundation insulationRadomir Delicenergy_progress
Latest 25 of 74.
▾Documents — 75 on file (BIS + DOB NOW)
▸Plans & Drawings13
▸DOB NOWPlans/Sketch13
08/19/2026X01217592-I1Request digital key ↗
08/16/2026X01396154-I1Request digital key ↗
08/16/2026X01217545-P2Request digital key ↗
Showing 3 of 13 on file for this type
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/16/2026X01217545-P3Open ↗
08/13/2026X01217545-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/16/2026X01217545-P3Open ↗
08/13/2026X01217545-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026X01217545-I1Open ↗
▸Seals & Professional Certifications40
▸DOB NOWSpecial Inspector Seal & Signature14
09/28/2026X01217545-Z1Open ↗
09/26/2026X01217545-S6Open ↗
09/26/2026X01217545-S6Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature13
08/19/2026X01217592-I1Open ↗
08/16/2026X01396154-I1Open ↗
08/16/2026X01217545-P2Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWProgress Inspector Seal & Signature11
09/26/2026X01217545-S6Open ↗
09/26/2026X01217545-S6Open ↗
09/02/2026X01217545-P3Open ↗
Showing 3 of 11 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
09/11/2025240362353Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/11/2025240362353Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026X01217545-I1Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist2
08/16/2026X01217545-I1Open ↗
08/16/2026X01217545-P3Open ↗
▸BISSTREET TREE SUPPORTING DOCUMENT1
09/11/2025240362353Open ↗
▸BISSTREET TREE CHECKLIST1
09/11/2025240362353Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026X01217545-I1Open ↗
▸Inspections & Test Reports2
▸DOB NOWSOIL REPORT1
08/13/2026X01217545-S9Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026X01217545-S9Open ↗
▸Other Documents9
▸DOB NOWSite Survey: Initial2
08/16/2026X01217545-P3Open ↗
08/13/2026X01217545-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/16/2026X01217545-P3Open ↗
08/13/2026X01217545-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/16/2026X01217545-I1Open ↗
08/16/2026X01217545-P3Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
09/11/2025240362353Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
09/11/2025240362353Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026X01217545-Z1Open ↗