1967Year Built
8Stories
W6Building Class
R3-1Zoning
353,600 sfGross Floor Area
1Units
LL97 Covered19 Open Violations 2 unresolved · 17 paperwork only ▸FISP: UNSAFEFDNY Report ↗
Other college and university · 2,430,020 sf lot · 0.15 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalFire ProtectionGeneral
Roof6p · 2 filings · 8 docs
Floor 82p · 2 filings · 8 docs
Floor 71p · 2 filings · 8 docs
Floor 61p · 1 filing · 4 docs
Floor 5
Floor 42p · 2 filings · 10 docs
Floor 31p · 1 filing · 4 docs
Floor 25p · 2 filings · 8 docs
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DORMITORY AUTHORITY STATE OF N Y203/21/2026
DORMITORY AUTHORITY OF NY103/21/2026
DASNY403/21/2026
DORMITORY AUTHORITY103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SUPERSTRUCTURES ENG. + ARCH.209/29/2025
VENTROP ENGINEERING CONSULTING GROU112/09/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SUPERSTRUCTURES ENG + ARCH203/21/2026
P WOLFE CONSULTANTS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ARTHUR GROSSMANElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SOCOTEC ENGINEERING4983112/09/2024
Building Lifecycle
All (50)Filed (3)Facade (FISP) (12)Violation (7)Special Inspection (28)
09/29/2025
Filed — Alteration
KBCC Kibbee Library, Exterior repairs including: Removal/Replacement/Repairs to sloped metal roofs, curtain walls, windows, sloped glazing, skylights, storefronts, hollow metal doors, brick masonry, brick corner, pointing, and spandrel shelf angle.
B01284973-I1
09/10/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
09/10/2025
Special inspection requirement — Vestibules
09/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/10/2025
Special inspection requirement — Insulation placement and R values
09/10/2025
Special inspection requirement — Fenestration areas
09/10/2025
Special inspection requirement — Air barrier - visual inspection
09/10/2025
Special inspection requirement — Fenestration air leakage
09/10/2025
Special inspection requirement — Final
Paul Millman
09/10/2025
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
09/10/2025
Special inspection requirement — Structural Steel - Welding
09/10/2025
Special inspection requirement — Post-installed Anchors
09/10/2025
Special inspection requirement — Masonry
03/12/2025
Cycle 10 facade report submitted
03/07/2025
Cycle 10 facade report signed — UNSAFE
03/04/2025
Cycle 10 facade inspection completed
03/04/2025
Cycle 9 facade inspection completed
02/27/2025
Cycle 9 facade report signed — UNSAFE
12/18/2024
Violation issued (FDNY_NOV, closed)
12/18/2024
Violation issued (FDNY_NOV, closed)
12/09/2024
Filed — Alteration
HEREWITH FILING FOR LIKE-TO-LIKE REPLACEMENT OF EXISTING DAMPER AND/OR ACTUATOR ASSEMBLY ON THE 4TH FLOOR AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY
B01023058-I1
07/11/2024
Cycle 9 facade report submitted
07/11/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/20/2024
Special inspection requirement — Final
MARISA HARTE
03/20/2024
Special inspection requirement — Post-installed Anchors
MARISA HARTE
03/20/2024
Special inspection requirement — Mechanical Systems
MARISA HARTE
03/20/2024
Special inspection requirement — Energy Code Compliance Inspections
MARISA HARTE
02/22/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/12/2022
Filed — Alteration
KBCC Kibbee Library repairs as per the plans filed including: Removal and replacement of brick masonry, existing metal roofs, curtain walls, windows, sloped glazing, skylight, storefronts, and hollow metal doors.
B08002296-I1
09/12/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
09/12/2022
Special inspection requirement — Air barrier - visual inspection
09/12/2022
Special inspection requirement — Vestibules
09/12/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
09/12/2022
Special inspection requirement — Fenestration areas
09/12/2022
Special inspection requirement — Insulation placement and R values
09/12/2022
Special inspection requirement — Fenestration air leakage
09/12/2022
Special inspection requirement — Final
Paul Millman
09/12/2022
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
09/12/2022
Special inspection requirement — Structural Steel - Welding
09/12/2022
Special inspection requirement — Post-installed Anchors
09/12/2022
Special inspection requirement — Masonry
09/20/2021
Violation issued (FDNY_NOV, closed)
12/22/2017
Cycle 8 facade report signed — SWARMP
10/16/2017
Cycle 8 facade report submitted
08/22/2017
Cycle 8 facade inspection completed
01/25/2013
Violation issued (FDNY_ORDER, closed)
08/17/2012
Cycle 7 facade report submitted
08/03/2012
Cycle 7 facade report signed — SAFE
08/01/2012
Cycle 7 facade inspection completed
04/10/2012
Violation issued (FDNY_ORDER, closed)
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISMHISSUEDDAVRIAL ENTERPRISES INC12/13/2013
BISEQISSUEDB & S RESTORATION INC12/24/2009
BISFSISSUEDEDWARD LEVINSON01/21/2009
BISMHISSUEDMIKAB CORPORATION02/06/2008
BISOTISSUEDMIKAB CORP01/25/2008
BISOTISSUEDMIKAB CORP.01/25/2008
BISOTISSUEDVMK08/02/2007
BISOTISSUEDVMK08/11/2006
2 projects · most recent 09/29/2025
FiledStatusContractorScope
09/29/2025——1 scope_items
09/12/2022——1 scope_items
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
09/10/2025Fenestration and door U-factor and product ratings—energy_progress
09/10/2025Vestibules—energy_progress
09/10/2025Fire-Resistant Penetrations and Joints—special
09/10/2025Insulation placement and R values—energy_progress
09/10/2025Fenestration areas—energy_progress
09/10/2025Air barrier - visual inspection—energy_progress
09/10/2025Fenestration air leakage—energy_progress
09/10/2025FinalPaul Millmanprogress
09/10/2025Wall Panels, Curtain Walls, and Veneers—special
09/10/2025Structural Steel - Welding—special
09/10/2025Post-installed Anchors—special
09/10/2025Masonry—special
03/20/2024FinalMARISA HARTEprogress
03/20/2024Post-installed AnchorsMARISA HARTEspecial
03/20/2024Mechanical SystemsMARISA HARTEspecial
03/20/2024Energy Code Compliance InspectionsMARISA HARTEprogress
09/12/2022Fire-Resistant Penetrations and Joints—special
09/12/2022Air barrier - visual inspection—energy_progress
09/12/2022Vestibules—energy_progress
09/12/2022Fenestration and door U-factor and product ratings—energy_progress
09/12/2022Fenestration areas—energy_progress
09/12/2022Insulation placement and R values—energy_progress
09/12/2022Fenestration air leakage—energy_progress
09/12/2022FinalPaul Millmanprogress
09/12/2022Wall Panels, Curtain Walls, and Veneers—special
Latest 25 of 28.
▾Documents — 75 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/28/2026B08002296-I1Request digital key ↗
08/23/2026B01023058-I1Request digital key ↗
08/20/2026B01284973-I1Request digital key ↗
▸Applications & Permits16
▸BISWORK PERMIT APPLICATION9
12/23/2013320880249Open ↗
10/19/2010320066156Open ↗
06/10/2010320113569Open ↗
Showing 3 of 9 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION6
12/14/2010320244785Open ↗
12/29/2009320113569Open ↗
09/01/2009320066156Open ↗
Showing 3 of 6 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
02/07/2018321786082Open ↗
▸Seals & Professional Certifications19
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION10
02/07/2018321786082Open ↗
10/21/2013320880249Open ↗
12/14/2010320244785Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/28/2026B08002296-I1Open ↗
08/23/2026B01023058-I1Open ↗
08/20/2026B01284973-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature3
08/26/2026B01023058-I1Open ↗
08/25/2026B08002296-I1Open ↗
08/22/2026B01284973-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
12/29/2009320113569Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
12/29/2009320113569Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026B01023058-I1Open ↗
▸Trade Schedules & Equipment3
▸BISEQUIPMENT USE APPLICATION/PERMIT2
12/30/2013320880249Open ↗
07/18/2008310079875Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
01/28/2008310083708Open ↗
▸Environmental & Asbestos7
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
12/14/2010320244785Open ↗
09/01/2009320066156Open ↗
01/28/2008310083708Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
10/21/2013320880249Open ↗
12/31/2009320113569Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
02/07/2018321786082Open ↗
12/30/2013320880249Open ↗
10/21/2013320880249Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/30/2013320880249Open ↗
▸Approvals, Objections & Sign-offs12
▸BISADMINISTRATIVE OBJECTIONS7
10/21/2013320880249Open ↗
12/14/2010320244785Open ↗
12/29/2009320113569Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter3
08/13/2026B01023058-I1Open ↗
08/13/2026B01284973-I1Open ↗
08/13/2026B08002296-I1Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
12/30/2013320880249Open ↗
07/17/2008310079875Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT7
02/07/2018321786082Open ↗
12/30/2013320880249Open ↗
10/21/2013320880249Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms4
▸BISEFILING COVER SHEET4
02/07/2018321786082Open ↗
12/14/2010320244785Open ↗
12/29/2009320113569Open ↗
Showing 3 of 4 on file for this type