| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/05/2020 | $1.3M | — | — → — | $481/sf building |
| 09/23/2013 | $424K | — | Private party → Private party | $157/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FRANK AMBROSINO | 7 | 06/12/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| ENKAY DESIGN CONSULTING | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HOCKMANN HILL GROUP INC | General Contractor | 5 | 07/08/2026 |
| LOTUS ELECTRIC | Electrical | 1 | 03/22/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BADALY ARCHITECT PLLC | 7137 | 1 | 06/12/2024 |
| AMBROSINO ARCHITECTS | 6357 | 6 | 09/27/2023 |
| INTEGRITY CONSULTING SERV | 666 | 1 | 07/28/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | HOCKMANN HILL GROUP | 07/29/2024 |
| DOB NOW | General Construction | Signed-off | HOCKMANN HILL GROUP | 10/23/2023 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 10/27/2022 |
| DOB NOW | Mechanical Systems | Signed-off | HOCKMANN HILL GROUP | 10/26/2022 |
| DOB NOW | General Construction | Signed-off | HOCKMANN HILL GROUP | 10/25/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2024 | Complete | LOTUS ELECTRIC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/27/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/27/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/23/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/23/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/20/2022 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/13/2024 | Concrete - Cast-In-Place | ALEKSANDR LEVIN | special |
| 06/13/2024 | Structural Steel - Welding | ALEKSANDR LEVIN | special |
| 06/13/2024 | Structural Steel - Details | ALEKSANDR LEVIN | special |
| 06/13/2024 | Structural Wood Frame | Frank Ambrosino | progress |
| 06/13/2024 | Final | Frank Ambrosino | progress |
| 06/13/2024 | Subgrade Inspections | Frank Ambrosino | special |
| 06/13/2024 | Structural Steel - High Strength Bolting | ALEKSANDR LEVIN | special |
| 05/31/2024 | Concrete - Cast-In-Place | SHAHIN BADALY | special |
| 05/31/2024 | Structural Steel - High Strength Bolting | SHAHIN BADALY | special |
| 05/31/2024 | Structural Steel - Welding | SHAHIN BADALY | special |
| 05/31/2024 | Structural Wood Frame | — | progress |
| 05/31/2024 | Final | — | progress |
| 05/31/2024 | Subgrade Inspections | — | special |
| 05/31/2024 | Structural Steel - Details | SHAHIN BADALY | special |
| 10/19/2023 | Fire-Resistant Penetrations and Joints | Frank Ambrosino | special |
| 10/19/2023 | Energy Code Compliance Inspections | Frank Ambrosino | progress |
| 10/19/2023 | HVAC-R and service water piping design and insulation | Frank Ambrosino | energy_progress |
| 06/29/2023 | HVAC-R and service water piping design and insulation | Frank Ambrosino | energy_progress |
| 06/29/2023 | Energy Code Compliance Inspections | Frank Ambrosino | progress |
| 06/29/2023 | Fire-Resistant Penetrations and Joints | Frank Ambrosino | special |
| 12/27/2022 | HVAC-R and service water piping design and insulation | Frank Ambrosino | energy_progress |
| 12/27/2022 | Fire-Resistant Penetrations and Joints | Frank Ambrosino | special |
| 12/27/2022 | Energy Code Compliance Inspections | Frank Ambrosino | progress |
| 08/16/2022 | Maintenance information | Frank Ambrosino | energy_progress |
| 08/16/2022 | HVAC-R and service water heating system controls | Frank Ambrosino | energy_progress |