| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/11/2025 | $200K | — | Private party → Private party | $68/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GEORGIOS KONTAROUDIS | 6 | 06/18/2026 |
| TETTONIS ENGINEERING PLLC | 1 | 07/22/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| JENNY FLORES EXPEDITING | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CAM ENERGY HTG&MECH CORP | Plumbing | 2 | 07/28/2026 |
| GALAXY ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| BHY CONTRACTOR INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TSS ENGINEERS | 4492 | 4 | 06/18/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | CAM ENERGY HTG&MECH CORP | 07/27/2026 |
| DOB NOW | Plumbing | Permit Issued | CAM ENERGY HTG&MECH CORP | 02/27/2025 |
| DOB NOW | General Construction | Permit Issued | BHY CONTRACTOR INC | 12/06/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2026 | Permit Issued | CAM ENERGY HTG&MECH CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/26/2025 | Permit Issued | GALAXY ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2026 | Permit Issued | CAM ENERGY HTG&MECH CORP | Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/04/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/04/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/30/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/26/2026 | Fenestration and door U-factor and product ratings | GEORGIOS KONTAROUDIS | energy_progress |
| 05/26/2026 | Energy Code Compliance Inspections | GEORGIOS KONTAROUDIS | progress |
| 05/26/2026 | Structural Stability – Alterations of existing buildings | bassam (sam) rimawi | special |
| 05/26/2026 | Fire-Resistant Penetrations and Joints | bassam (sam) rimawi | special |
| 04/28/2025 | Fire-Resistant Penetrations and Joints | bassam (sam) rimawi | special |
| 04/28/2025 | Structural Stability – Alterations of existing buildings | bassam (sam) rimawi | special |
| 04/28/2025 | Energy Code Compliance Inspections | GEORGIOS KONTAROUDIS | progress |
| 04/28/2025 | Fenestration and door U-factor and product ratings | GEORGIOS KONTAROUDIS | energy_progress |
| 03/14/2025 | Fire-Resistant Penetrations and Joints | bassam (sam) rimawi | special |
| 03/14/2025 | Structural Stability – Alterations of existing buildings | bassam (sam) rimawi | special |
| 03/14/2025 | Energy Code Compliance Inspections | GEORGIOS KONTAROUDIS | progress |
| 03/14/2025 | Fenestration and door U-factor and product ratings | GEORGIOS KONTAROUDIS | energy_progress |
| 12/31/2024 | Fire-Resistant Penetrations and Joints | bassam (sam) rimawi | special |
| 12/31/2024 | Fenestration and door U-factor and product ratings | GEORGIOS KONTAROUDIS | energy_progress |
| 12/31/2024 | Energy Code Compliance Inspections | GEORGIOS KONTAROUDIS | progress |
| 12/31/2024 | Structural Stability – Alterations of existing buildings | bassam (sam) rimawi | special |
| 06/17/2024 | Subgrade Inspections | — | special |
| 06/12/2024 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 06/12/2024 | Masonry | — | special |
| 06/12/2024 | Final | — | progress |
| 06/12/2024 | Footing and Foundation | — | progress |