| Owner | Filings | Most Recent |
|---|---|---|
| BREEZY POINT COOPERATIVE, INC | 6 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BUNGALOW DESIGN & ENGINEERING PC | 1 | 07/11/2019 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JOSEPH O'GRADY P & H INC | Plumbing | 4 | 03/22/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| BIS | PL | ISSUED | JOSEPH O'GRADY P & H INC | 04/02/2021 |
| BIS | — | ISSUED | SAND-BAR CONTRACTORS INC | 11/18/2020 |
| BIS | PL | ISSUED | JOSEPH O'GRADY P & H INC | 02/14/2020 |
| BIS | — | ISSUED | SAND-BAR CONTRACTORS INC | 12/31/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/12/2020 | Complete | DANIEL T. O'LEARY | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/09/2019 | Final | Deidre Duffy | progress |