RoofUnder Construction1p · 2 filings · 7 docs
ArchitectureMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing
PASSIVE RECREATION ROOF TERRACE RENOVATIONS FOR APARTMENT PH3. INSTALL PLANTERS, NEW PAVERS, OUTDOOR GRILLE, SINK, COOKTOP, OUTDOOR SHOWER, SPA, VENTLESS GAS FIRE PLACE AND MOVABLE SHADE FRAME
On file for this project
7 documents · 1 drawing sheet
Project M00258632Permit Issued · 03/31/2021
FILING HEREWITH NEW BOILER INSTALLATION AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Floor 151 filing
GeneralMechanical
Issued Permit Scope
Boiler Equipment · Mechanical Systems
Project M00258632Permit Issued · 03/31/2021
FILING HEREWITH NEW BOILER INSTALLATION AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Floor 142p · 2 filings · 6 docs
ArchitectureGeneralMechanical
Issued Permit Scope
Boiler Equipment · Mechanical Systems
FILING HEREWITH NEW BOILER INSTALLATION AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
On file for this project
6 documents · 2 drawing sheets
Project M00258632Permit Issued · 03/31/2021
FILING HEREWITH NEW BOILER INSTALLATION AS PER PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY.
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 61 filing · 2 docs
ArchitectureGeneralMechanical
Issued Permit Scope
Boiler Equipment · Mechanical Systems
No filed description on record for this project.
On file for this project
2 documents
Floor 52p · 2 filings · 6 docs
ArchitectureGeneralMechanical
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems
Install of temp platforms, no alt to exist structures for Vibecon. A TPA is required. Producer is responsible to monitor site safety. All production equipment removed upon event completion
On file for this project
4 documents
No filed description on record for this project.
On file for this project
2 documents · 2 drawing sheets
Floor 4Under Construction1 filing · 20 docs
ArchitectureMechanicalStructural
Issued Permit Scope
Boiler Equipment · Mechanical Systems · Structural
NEW CONCRETE SLAB AND WALLS AT CELLAR LEVEL. NEW STEEL FRAMING AT AUDITORIUM CEILING TO SUPPORT AUDITORIUM EQUIPMENT. NEW STEEL CANTILEVERS TO SUPPORT NEW LED SIGNS AS PER PLANS.
On file for this project
28 documents
Floor 3Under Construction16p · 6 filings · 20 docs
ArchitectureDMElectricalFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
NEW CONCRETE SLAB AND WALLS AT CELLAR LEVEL. NEW STEEL FRAMING AT AUDITORIUM CEILING TO SUPPORT AUDITORIUM EQUIPMENT. NEW STEEL CANTILEVERS TO SUPPORT NEW LED SIGNS AS PER PLANS.
On file for this project
28 documents
Plumbing modifications at existing offices.
On file for this project
20 documents · 8 drawing sheets
HEREWITH FILING PLUMBING, SPRINKLER & STANDPIPE WORK FOR FIT OUT AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
On file for this project
9 documents · 3 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 2Under Construction15p · 25 filings · 20 docs
ArchitectureCivilElectricalFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers · Standpipe · Structural
Filling herewith plumbing modifications to the existing system as per plans. No change to use, egress or occupancy.
On file for this project
11 documents
NEW CONCRETE SLAB AND WALLS AT CELLAR LEVEL. NEW STEEL FRAMING AT AUDITORIUM CEILING TO SUPPORT AUDITORIUM EQUIPMENT. NEW STEEL CANTILEVERS TO SUPPORT NEW LED SIGNS AS PER PLANS.
On file for this project
28 documents · 2 drawing sheets
Temporary structures for events. This application is filed in conjunction with a TPA. No change to existing structures, use or egress.
On file for this project
9 documents
Latest 3 of 25 filings on this floor.
Floor 1Under Construction19p · 17 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers
NEW CONCRETE SLAB AND WALLS AT CELLAR LEVEL. NEW STEEL FRAMING AT AUDITORIUM CEILING TO SUPPORT AUDITORIUM EQUIPMENT. NEW STEEL CANTILEVERS TO SUPPORT NEW LED SIGNS AS PER PLANS.
On file for this project
28 documents · 2 drawing sheets
Tenant fit out for Chase bank. No change to use, egress or occupancy.
On file for this project
11 documents · 3 drawing sheets
Temporary structures for events. This application is filed in conjunction with a TPA. No change to existing structures, use or egress.
On file for this project
9 documents
Latest 3 of 17 filings on this floor.
CellarUnder Construction2p · 4 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalStructural
Issued Permit Scope
Boiler Equipment · Mechanical Systems · Sprinklers · Structural
NEW CONCRETE SLAB AND WALLS AT CELLAR LEVEL. NEW STEEL FRAMING AT AUDITORIUM CEILING TO SUPPORT AUDITORIUM EQUIPMENT. NEW STEEL CANTILEVERS TO SUPPORT NEW LED SIGNS AS PER PLANS.
On file for this project
28 documents
Tenant fit out for Chase bank. No change to use, egress or occupancy.
On file for this project
11 documents
HEREWITH FILING SPRINKLER WORK AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY
On file for this project
4 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Sub-CellarUnder Construction13p · 25 filings · 20 docs
ArchitectureCivilElectricalFire ProtectionGeneralMechanicalPlumbingStructuralOther
Issued Permit Scope
Boiler Equipment · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
NEW CONCRETE SLAB AND WALLS AT CELLAR LEVEL. NEW STEEL FRAMING AT AUDITORIUM CEILING TO SUPPORT AUDITORIUM EQUIPMENT. NEW STEEL CANTILEVERS TO SUPPORT NEW LED SIGNS AS PER PLANS.
On file for this project
28 documents · 7 drawing sheets
Install of temp scenic walls, no alt to exist structures for Simkhai SS26 Fashion Show. TPA required. Producer is responsible to monitor site safety. All production equipment removed upon event completion
On file for this project
2 documents
Temporary structures for events. This application is filed in conjunction with a TPA. No change to existing structures, use or egress.
On file for this project
9 documents
Latest 3 of 25 filings on this floor.
Site & exteriorUnder Construction5 filings · 20 docs
ArchitectureDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Sidewalk Shed · Sign · Supported Scaffold
Tenant fit out for Chase bank. No change to use, egress or occupancy.
On file for this project
11 documents · 12 drawing sheets
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF 2022 THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents · 4 drawing sheets
INSTALLATION OF PLYWOOD FENCE, AS PER DRAWINGS. PLYWOOD FENCE SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. FENCE TO BE INSTALLED ON SIDEWALK / ROADWAY. DOT PERMITS BY OTHERS.
On file for this project
3 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Filed — no permit issued3 filings · 8 docs
ArchitectureFire ProtectionGeneral
Project M00793645PAA Approved
No filed description on record for this project.
On file for this project
3 documents · 7 drawing sheets
HEREWITH FILING ARCHITECTURAL WORK AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY
On file for this project
2 documents · 3 drawing sheets
No filed description on record for this project.
On file for this project
3 documents · 3 drawing sheets