← Back
BuildNYC
Old law tenement
202 WEST 133RD STREET
MANHATTAN · BIN 1058786
💬 Discuss this project
1930Year Built
5Stories
C4Building Class
R7-2Zoning
14,175 sfGross Floor Area
20Units
Rent Stabilized14 Active Violations ▸FDNY Report ↗
Old law tenement · Owner of record: Restoring Communities Housing Development Fund C Orp · 3,747 sf lot · 3.78 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofPlumbing and sprinkler work68p · 3 filings · 20 docs
Bulkhead1p · 1 filing · 16 docs
Floor 5Plumbing and sprinkler work60p · 3 filings · 20 docs
Floor 4Plumbing and sprinkler work59p · 3 filings · 20 docs
Floor 3Plumbing and sprinkler work66p · 3 filings · 20 docs
Floor 2Plumbing and sprinkler work13p · 3 filings · 20 docs
Floor 1Plumbing and sprinkler work68p · 3 filings · 20 docs
CellarPlumbing and sprinkler work63p · 3 filings · 20 docs
Site & exteriorPlumbing and sprinkler work64p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC Department of Housing Preservation and Development803/21/2026
Restoring Communities HDFC303/22/2026
West Harlem Group Assistance103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Rosenthal1006/11/2024
Old Structures Engineering209/28/2021
Ashraf207/08/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Rigid Structural Design203/21/2026
BMB Building Consulting2403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Intersystem InstallationScaffold1207/08/2026
Intersystems Installation S&SScaffold303/21/2026
Watson's Plumbing, Heating, & BuildingPlumbing307/08/2026
Erin Construction & DevelopmentGeneral Contractor207/08/2026
SNB Electrical ContngElectrical203/21/2026
Expert Fire SprinklerFire Protection207/08/2026
SNB Electrical ContngElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M. Hamdi Gunal, PE30001206/11/2024
Building Lifecycle
All (131)Filed (14)Permit Issued (14)Signed Off (6)Violation (39)Inspection (4)Objection (24)Special Inspection (30)
04/29/2026
Violation issued (HPD, closed)
A
06/04/2025
Violation issued (HPD, closed)
A
07/22/2024
Signed off — Alteration
Propose to install TWO (2) new gas fired Boilers filed in conjunction with ALT1 # 121205980.
M00236036-I1
07/01/2024
Signed off — Alteration
PROPOSE PLUMBING AND SPRINKLER WORK IN CONJUNCTION WITH ALT I # 121205980. CAP AND REMOVE ALL EXISTING BOILER, GAS, AND PL FIXTIRES WITH PIPING THROUGHOUT THE BLDG.
M00221176-I1
06/11/2024
Filed — Alteration
PROPOSE PLUMBING AND SPRINKLER WORK IN CONJUNCTION WITH ALT I # 121205980. CAP AND REMOVE ALL EXISTING BOILER, GAS, AND PL FIXTIRES WITH PIPING THROUGHOUT THE BLDG.
M00221176-P4
06/06/2024
Special inspection requirement — Energy Code Compliance Inspections
Mehmet Gunal
06/06/2024
Special inspection requirement — Sprinkler Systems
Mehmet Gunal
04/25/2024
Signed off — Alteration
SEPARATE FILING FOR MECHANICAL SCOPE OF WORK FILED IN CONJUNCTION WITH ALT I # 121205980
M00229157-I1
04/24/2024
Signed off — Alteration
Propose Structural Scope of Work as per plan filed in conjunction with Alt1# 121205980.
M00236097-I1
04/17/2024
Objection resolved — Addressed
04/16/2024
Objection raised — Other
04/09/2024
Filed — Alteration
PROPOSE PLUMBING AND SPRINKLER WORK IN CONJUNCTION WITH ALT I # 121205980. CAP AND REMOVE ALL EXISTING BOILER, GAS, AND PL FIXTIRES WITH PIPING THROUGHOUT THE BLDG.
M00221176-P3
04/04/2024
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
04/02/2024
Violation issued (HPD, closed)
A
04/01/2024
Special inspection requirement — HVAC and service water heating equipment
Mehmet Gunal
04/01/2024
Special inspection requirement — HVAC and service water heating system controls
Mehmet Gunal
04/01/2024
Special inspection requirement — Heating Systems
Mehmet Gunal
04/01/2024
Special inspection requirement — Maintenance information
Mehmet Gunal
04/01/2024
Special inspection requirement — Shutoff dampers
Mehmet Gunal
03/29/2024
Filed — Alteration
Propose to install TWO (2) new gas fired Boilers filed in conjunction with ALT1 # 121205980.
M00236036-P2
03/19/2024
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/26/2024
Signed off — Alteration
Installation of a temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00553953-I1
02/16/2024
Permit issued — Mechanical Systems
M00229157-I1-MS
12/05/2023
Permit issued — Sprinklers
M00221176-I1-EW-SP
11/14/2023
Filed — Alteration
PROPOSE PLUMBING AND SPRINKLER WORK IN CONJUNCTION WITH ALT I # 121205980. CAP AND REMOVE ALL EXISTING BOILER, GAS, AND PL FIXTIRES WITH PIPING THROUGHOUT THE BLDG.
M00221176-P2
11/13/2023
Special inspection requirement — HVAC insulation and sealing
Mehmet Gunal
11/13/2023
Special inspection requirement — Energy Code Compliance Inspections
Mehmet Gunal
11/13/2023
Special inspection requirement — Sprinkler Systems
Mehmet Gunal
10/12/2023
Permit issued — Sprinklers
M00221176-I1-PL
09/25/2023
Permit issued — Sidewalk Shed
M00553953-I1-SH
09/20/2023
Signed off — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00553965-I1
09/13/2023
Permit issued — Structural
M00236097-I1-ST
09/12/2023
Special inspection requirement — Structural Steel - Details
Mehmet Gunal
09/12/2023
Special inspection requirement — Structural Wood Frame
Mehmet Gunal
09/12/2023
Special inspection requirement — Final
Mehmet Gunal
09/12/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mehmet Gunal
09/12/2023
Special inspection requirement — Structural Steel - Welding
Mehmet Gunal
09/12/2023
Special inspection requirement — Masonry
Mehmet Gunal
09/12/2023
Special inspection requirement — Concrete - Cast-In-Place
Mehmet Gunal
09/12/2023
Special inspection requirement — Structural Steel - High Strength Bolting
Mehmet Gunal
08/07/2023
Permit issued — Sidewalk Shed
M00553953-I1-SH
05/24/2023
Permit issued — Boiler Equipment
M00236036-I1-BE
04/25/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/21/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/21/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/16/2023
Violation issued (HPD, closed)
A
11/21/2022
Permit issued — Plumbing
M00221176-I1-EW-SP
10/11/2022
Permit issued — Plumbing
M00221176-I1-PL
07/22/2022
Permit issued — Sidewalk Shed
M00553953-I1-SH
02/16/2022
Violation issued (HPD, closed)
A
02/08/2022
Objection resolved — Addressed
09/30/2021
Objection raised — Admin
09/28/2021
Filed — Alteration
Propose Structural Scope of Work as per plan filed in conjunction with Alt1# 121205980.
M00236097-P1
09/20/2021
Special inspection requirement — Mechanical Systems
Mehmet Gunal
09/20/2021
Special inspection requirement — Fire-Resistance Rated Construction
Mehmet Gunal
09/20/2021
Special inspection requirement — Energy Code Compliance Inspections
Mehmet Gunal
09/20/2021
Special inspection requirement — Final
Mehmet Gunal
09/20/2021
Special inspection requirement — HVAC insulation and sealing
Mehmet Gunal
09/20/2021
Special inspection requirement — HVAC and service water heating system controls
Mehmet Gunal
09/20/2021
Special inspection requirement — Shutoff dampers
Mehmet Gunal
Latest 60 of 131 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offErin Construction & Development02/16/2024
DOB NOWSprinklersSigned-offExpert Fire Sprinkler12/05/2023
DOB NOWPlumbingSigned-offWatson's Plumbing, Heating, & Building10/12/2023
DOB NOWSidewalk ShedSigned-offIntersystems Installation S&S09/25/2023
DOB NOWStructuralSigned-offErin Construction & Development09/13/2023
DOB NOWSidewalk ShedSigned-offIntersystem Installation08/07/2023
DOB NOWBoiler EquipmentSigned-offWatson's Plumbing, Heating, & Building05/24/2023
DOB NOWSprinklersSigned-offExpert Fire Sprinkler11/21/2022
DOB NOWPlumbingSigned-offWatson's Plumbing, Heating, & Building10/11/2022
DOB NOWSidewalk ShedSigned-offIntersystem Installation07/22/2022
DOB NOWSidewalk ShedSigned-offIntersystem Installation08/10/2021
DOB NOWSupported ScaffoldSigned-offIntersystem Installation07/30/2021
DOB NOWSidewalk ShedSigned-offIntersystem Installation07/09/2021
DOB NOWSupported ScaffoldSigned-offIntersystem Installation07/09/2021
BIS—ISSUEDErin Construction & Development09/04/2024
BIS—ISSUEDErin Construction & Development09/01/2023
BIS—ISSUEDErin Construction & Development09/08/2022
BIS—ISSUEDErin Construction & Development09/13/2021
BIS—RE-ISSUEDErin Construction & Development07/22/2021
BISOTISSUEDRavidas Construction09/30/2004
BISPLISSUEDEmpire Used Boiler Sup. Co03/08/2004
BISBLISSUEDEmpire Used Boiler Supp03/08/2004
BISOTISSUEDNational Gen Construction06/25/1999
BISEQISSUEDTriple R10/13/1998
BISOTISSUED"I AM" Construction07/02/1998
BISOTISSUEDJasbir Singh/ B&A General04/20/1998
BISOTISSUEDRPH Construction Copr09/18/1996
BISPLISSUEDNationwide Mechanical02/06/1992
BISPLISSUEDNationwide Mechanical10/11/1991
BISOTRE-ISSUEDColmike Enterprises10/11/1991
6 projects · most recent 07/12/2024
General Wiring
FiledStatusContractorScope
07/12/2024CompleteSNB Electrical ContngGeneral Wiring
06/24/2024CompleteSNB Electrical ContngGeneral Wiring
05/18/2024CancelledSNB Electrical ContngGeneral Wiring
07/22/2021CompleteRamdeen's Electric ContractingGeneral Wiring
06/28/2021CompleteSteven Farkas—
10/30/2020CompleteLeone Electric CoGeneral Wiring
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
04/04/2024Pass-Final Boiler Equipment InspectionPassView ↗
03/19/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
04/21/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/21/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 49
DateRequirementInspectorRole
06/06/2024Energy Code Compliance InspectionsMehmet Gunalprogress
06/06/2024Sprinkler SystemsMehmet Gunalspecial
04/01/2024HVAC and service water heating equipment Mehmet Gunalenergy_progress
04/01/2024HVAC and service water heating system controls Mehmet Gunalenergy_progress
04/01/2024Heating SystemsMehmet Gunalspecial
04/01/2024Maintenance informationMehmet Gunalenergy_progress
04/01/2024Shutoff dampersMehmet Gunalenergy_progress
11/13/2023HVAC insulation and sealing Mehmet Gunalenergy_progress
11/13/2023Energy Code Compliance InspectionsMehmet Gunalprogress
11/13/2023Sprinkler SystemsMehmet Gunalspecial
09/12/2023Structural Steel - DetailsMehmet Gunalspecial
09/12/2023Structural Wood FrameMehmet Gunalprogress
09/12/2023FinalMehmet Gunalprogress
09/12/2023Structural Stability – Alterations of existing buildingsMehmet Gunalspecial
09/12/2023Structural Steel - WeldingMehmet Gunalspecial
09/12/2023MasonryMehmet Gunalspecial
09/12/2023Concrete - Cast-In-PlaceMehmet Gunalspecial
09/12/2023Structural Steel - High Strength BoltingMehmet Gunalspecial
09/20/2021Mechanical SystemsMehmet Gunalspecial
09/20/2021Fire-Resistance Rated ConstructionMehmet Gunalprogress
09/20/2021Energy Code Compliance InspectionsMehmet Gunalprogress
09/20/2021FinalMehmet Gunalprogress
09/20/2021HVAC insulation and sealing Mehmet Gunalenergy_progress
09/20/2021HVAC and service water heating system controls Mehmet Gunalenergy_progress
09/20/2021Shutoff dampersMehmet Gunalenergy_progress
Latest 25 of 49.
▾Documents — 136 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch - Sprinkler5
09/03/2026M00221176-P4Request digital key ↗
09/03/2026M00221176-P2Request digital key ↗
09/03/2026M00221176-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Plumbing5
09/03/2026M00221176-P4Request digital key ↗
09/03/2026M00221176-I1Request digital key ↗
09/03/2026M00221176-P2Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Boiler Equipment3
09/03/2026M00236036-P2Request digital key ↗
09/03/2026M00236036-P1Request digital key ↗
08/15/2026M00236036-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/03/2026M00229157-P1Request digital key ↗
08/15/2026M00229157-I1Request digital key ↗
▸DOB NOWPlans/Sketch2
09/03/2026M00553965-I1Request digital key ↗
09/03/2026M00553953-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural2
08/14/2026M00236097-I1Request digital key ↗
08/14/2026M00236097-P1Request digital key ↗
▸Applications & Permits11
▸BISPLAN / WORK APPROVAL APPLICATION9
12/13/2024100328851Open ↗
12/13/2024102202322Open ↗
12/06/2024103924167Open ↗
Showing 3 of 9 on file for this type
▸BISWORK PERMIT APPLICATION1
07/22/2021121205980Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
02/12/2024121205980Open ↗
▸Seals & Professional Certifications36
▸DOB NOWDPL-1: Design Professional Seal & Signature14
09/03/2026M00229157-I1Open ↗
09/03/2026M00229157-P1Open ↗
09/03/2026M00236036-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature12
09/23/2026M00236036-I1Open ↗
09/02/2026M00221176-P2Open ↗
09/02/2026M00221176-P2Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature10
09/23/2026M00236036-I1Open ↗
09/02/2026M00221176-P2Open ↗
09/01/2026M00229157-P1Open ↗
Showing 3 of 10 on file for this type
▸Trade Schedules & Equipment1
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
09/16/2024121205980Open ↗
▸Safety & Tenant Protection2
▸BISSTREET TREE CHECKLIST2
09/30/2019121205980Open ↗
08/30/2019121205980Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form4
08/15/2026M00229157-I1Open ↗
08/15/2026M00236036-I1Open ↗
08/13/2026M00236097-I1Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT SHALL PROVIDE 1 ACP-21 FORMPRIOR TO SIGN OFF: TRU1142MN211
03/22/2024121205980Open ↗
▸BISASBESTOS: VARIANCE (DEP FORM V5)1
07/22/2021121205980Open ↗
▸Energy Compliance17
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
06/27/2024121205980Open ↗
07/22/2021121205980Open ↗
08/30/2019121205980Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
06/27/2024121205980Open ↗
▸BISINTERIOR LIGHTING POWER1
06/27/2024121205980Open ↗
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
06/27/2024121205980Open ↗
▸BISFENESTRATION AREAS1
06/27/2024121205980Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
06/27/2024121205980Open ↗
▸BISLIGHTING IN DWELLING UNITS1
06/27/2024121205980Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
04/15/2024121205980Open ↗
▸BISELECTRIC MOTORS1
06/27/2024121205980Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
04/15/2024121205980Open ↗
▸BISLIGHTING CONTROLS1
06/27/2024121205980Open ↗
▸BISELECTRICAL ENERGY CONSUMPTION1
06/27/2024121205980Open ↗
▸BISEXTERIOR LIGHTING POWER1
06/27/2024121205980Open ↗
▸BISFENESTRATION AIR LEAKAGE1
06/27/2024121205980Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/15/2026M00236036-I1Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: RESPONSIBILITY3
04/15/2024121205980Open ↗
07/22/2021121205980Open ↗
08/30/2019121205980Open ↗
▸BISCONCRETE - CAST-IN-PLACE1
04/15/2024121205980Open ↗
▸BISSTRUCTURAL STEEL - DETAILS1
04/15/2024121205980Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
04/15/2024121205980Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
04/15/2024121205980Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
04/15/2024121205980Open ↗
▸BISMASONRY1
04/15/2024121205980Open ↗
▸BISSTRUCTURAL STEEL - HIGH STRENGTH BOLTING1
04/15/2024121205980Open ↗
▸BISSTRUCTURAL STEEL - WELDING1
04/15/2024121205980Open ↗
▸Approvals, Objections & Sign-offs24
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter12
09/03/2026M00229157-P1Open ↗
09/03/2026M00236036-P1Open ↗
09/03/2026M00236036-P2Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWDEP Variance (V5) letter4
08/15/2026M00229157-I1Open ↗
08/15/2026M00236036-I1Open ↗
08/13/2026M00221176-I1Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE3
03/08/2024121205980Open ↗
02/29/2024121205980Open ↗
02/21/2024121205980Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
03/25/2024103791372Open ↗
09/23/2019121205980Open ↗
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)2
08/14/2026M00236097-I1Open ↗
08/13/2026M00236097-P1Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
03/25/2024103791372Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT1
08/30/2019121205980Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
08/29/2024121205980Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION4
03/22/2024121205980Open ↗
03/12/2024121205980Open ↗
09/30/2019121205980Open ↗
Showing 3 of 4 on file for this type
▸Other Documents3
▸BISSTRUCTURAL COLD-FORMED STEEL1
04/15/2024121205980Open ↗
▸BISMAINTENANCE INFORMATION1
06/27/2024121205980Open ↗
▸BISPLOT DIAGRAM1
08/30/2019121205980Open ↗