← Back
Two family frame
202 WOOD AVENUE
STATEN ISLAND · Tottenville-Charleston · BIN 5089187
💬 Discuss this project
1925Year Built
2.5Stories
B2Building Class
R3XZoning
6,676 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family frame · 5,418 sf lot · 1.23 FAR built · Flood zone X
Locations of Work
ElectricalGeneral
Roof1 filing · 6 docs
Floor 21p · 1 filing · 6 docs
Floor 1
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TRINITY SOLAR LLC206/03/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ACA ASSOCIATES103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRINITY SOLAR LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BITOPI CONSULTANTS LLC7036206/03/2026
Building Lifecycle
All (9)Filed (2)Permit Issued (1)Signed Off (1)Violation (1)Special Inspection (4)
06/17/2026
Signed off — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
S01305390-I1
06/03/2026
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
S01305390-P1
06/03/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
KAMRUL AHSAN
06/03/2026
Special inspection requirement — Energy Code Compliance Inspections
Ayracon Almaraz
06/03/2026
Special inspection requirement — Final
Ayracon Almaraz
06/03/2026
Special inspection requirement — Air barrier - visual inspection
Ayracon Almaraz
10/24/2025
Permit issued — Solar
S01305390-I1-SL
10/22/2025
Filed — Alteration
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
S01305390-I1
04/17/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offTRINITY SOLAR LLC10/24/2025
1 project · most recent 10/16/2025
FiledStatusContractorScope
10/16/2025CompleteREDLINE ELECTRIC INC—
1 project · most recent 06/03/2026
FiledStatusContractorScope
06/03/2026Signed-offTRINITY SOLAR LLC16 panels, 6.56 kw, 1,140 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
06/03/2026Fire-Resistant Penetrations and JointsKAMRUL AHSANspecial
06/03/2026Energy Code Compliance InspectionsAyracon Almarazprogress
06/03/2026FinalAyracon Almarazprogress
06/03/2026Air barrier - visual inspectionAyracon Almarazenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Seals & Professional Certifications5
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026S01305390-I1Open ↗
09/01/2026S01305390-I1Open ↗
09/01/2026S01305390-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026S01305390-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/01/2026S01305390-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026S01305390-I1Open ↗