1930Year Built
2Stories
A5Building Class
R6Zoning
1,624 sfGross Floor Area
1Units
One family attached or semi-detached · Owner of record: Five Forces · 2,000 sf lot · 0.81 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbingCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofConvert one family dwelling to two family dwelling1p · 1 filing · 20 docs
Floor 2Convert one family dwelling to two family dwelling7p · 3 filings · 20 docs
Floor 1Convert one family dwelling to two family dwelling7p · 3 filings · 20 docs
CellarConvert one family dwelling to two family dwelling6p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
GHM Development1907/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/03/2025$990K—— → —$610/sf building
03/14/2024$930K—MAZAL STRAUSS BH LLC → FIVE FORCES LLC$573/sf building
09/24/2022$315K—— → —$194/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Syed Engineering410/16/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KM Associates of New York403/21/2026
K & M Associates403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Yafe MeodGeneral Contractor1307/08/2026
DPH Plumbing & HeatingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Askon Architect3596410/16/2023
Building Lifecycle
All (54)Filed (4)Permit Issued (6)Signed Off (2)Inspection (6)Objection (6)Special Inspection (30)
01/16/2024
Signed off — Alteration
MECHANICAL WORK FILED IN CONJUNCTION WITH ALTERATION TYPE ONE JOB NO: B00826610-I1
B00848542-I1
01/10/2024
Signed off — Alteration
SCOPE OF WORK:PLUMBING APPLICATION FILED UNDER ALTERATION TYPE ONE JOB NO: B00826610-I1
B00848533-I1
01/05/2024
Permit issued — Mechanical Systems
B00848542-I1-MS
12/04/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
11/16/2023
Permit issued — General Construction
B00826610-I1-FO
11/16/2023
Permit issued — Earth Work
B00826610-I1-EA
11/16/2023
Permit issued — Earth Work
B00826610-I1-ST
11/15/2023
Special inspection requirement — Permanent certificate
Akeeb Shekoni
11/15/2023
Special inspection requirement — Insulation placement and R values
Akeeb Shekoni
11/15/2023
Special inspection requirement — Air barrier - visual inspection
Akeeb Shekoni
11/15/2023
Special inspection requirement — Final
HANSA PERSAUD
11/15/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
11/15/2023
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Akeeb Shekoni
11/15/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Akeeb Shekoni
11/15/2023
Special inspection requirement — Lighting controls
Akeeb Shekoni
11/15/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
Akeeb Shekoni
11/15/2023
Special inspection requirement — Maintenance information
Akeeb Shekoni
11/15/2023
Special inspection requirement — Fenestration areas
Akeeb Shekoni
11/15/2023
Special inspection requirement — Masonry
Akeeb Shekoni
11/15/2023
Special inspection requirement — Fire-Resistance Rated Construction
Akeeb Shekoni
11/15/2023
Special inspection requirement — Energy Code Compliance Inspections
Akeeb Shekoni
11/15/2023
Special inspection requirement — Footing and Foundation
Akeeb Shekoni
11/15/2023
Special inspection requirement — Protection of exposed foundation insulation
Akeeb Shekoni
11/15/2023
Special inspection requirement — Fenestration air leakage
Akeeb Shekoni
11/01/2023
Objection resolved — Addressed
10/31/2023
Objection raised — Other
10/16/2023
Filed — Alteration CO
CONVERT ONE FAMILY DWELLING TO TWO FAMILY DWELLING. OBTAIN NEW CERTIFICATE OF OCCUPANCY.
B00826610-P1
10/10/2023
Special inspection requirement — Lighting controls
Akeeb Shekoni
10/10/2023
Special inspection requirement — Protection of exposed foundation insulation
Akeeb Shekoni
10/10/2023
Special inspection requirement — Permanent certificate
Akeeb Shekoni
10/10/2023
Special inspection requirement — Construction Operations Influencing Adjacent Structures
Akeeb Shekoni
10/10/2023
Special inspection requirement — Final
HANSA PERSAUD
10/10/2023
Special inspection requirement — Fire-Resistance Rated Construction
Akeeb Shekoni
10/10/2023
Special inspection requirement — Footing and Foundation
Akeeb Shekoni
10/10/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
Akeeb Shekoni
10/10/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Akeeb Shekoni
10/10/2023
Special inspection requirement — Masonry
Akeeb Shekoni
10/10/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Akeeb Shekoni
10/10/2023
Special inspection requirement — Energy Code Compliance Inspections
Akeeb Shekoni
10/10/2023
Special inspection requirement — Air barrier - visual inspection
Akeeb Shekoni
07/07/2023
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/30/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
06/30/2023
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
06/30/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/30/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/13/2023
Permit issued — Plumbing
B00848533-I1-PL
05/19/2023
Objection raised — Inspections
05/19/2023
Objection resolved — Addressed
05/18/2023
Permit issued — Earth Work
B00826610-I1-GC
05/05/2023
Objection raised — Scope
05/05/2023
Objection resolved — Addressed
04/20/2023
Filed — Alteration
MECHANICAL WORK FILED IN CONJUNCTION WITH ALTERATION TYPE ONE JOB NO: B00826610-I1
B00848542-I1
04/20/2023
Filed — Alteration
SCOPE OF WORK:PLUMBING APPLICATION FILED UNDER ALTERATION TYPE ONE JOB NO: B00826610-I1
B00848533-I1
03/03/2023
Filed — Alteration CO
CONVERT ONE FAMILY DWELLING TO TWO FAMILY DWELLING. OBTAIN NEW CERTIFICATE OF OCCUPANCY.
B00826610-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offYafe Meod01/05/2024
DOB NOWGeneral ConstructionSigned-offYafe Meod11/16/2023
DOB NOWEarth WorkSigned-offYafe Meod11/16/2023
DOB NOWEarth WorkSigned-offYafe Meod11/16/2023
DOB NOWPlumbingSigned-offDPH Plumbing & Heating06/13/2023
DOB NOWEarth WorkPermit IssuedYafe Meod05/18/2023
1 project · most recent 09/05/2023
General Wiring
FiledStatusContractorScope
09/05/2023CompleteK.A.B. ElectricGeneral Wiring
1 project · most recent 10/16/2023
Masonry Wood
FiledStatusContractorScope
10/16/2023Signed-offYafe MeodMasonry, Wood
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
12/04/2023Pass-Final CND-Occupancy InspectionPassView ↗
07/07/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/30/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
06/30/2023Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
06/30/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/30/2023Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 39
DateRequirementInspectorRole
11/15/2023Permanent certificateAkeeb Shekonienergy_progress
11/15/2023Insulation placement and R valuesAkeeb Shekonienergy_progress
11/15/2023Air barrier - visual inspectionAkeeb Shekonienergy_progress
11/15/2023FinalHANSA PERSAUDprogress
11/15/2023Fire-Resistant Penetrations and JointsAkeeb Shekonispecial
11/15/2023Construction Operations Influencing Adjacent StructuresAkeeb Shekonispecial
11/15/2023Structural Stability – Alterations of existing buildingsAkeeb Shekonispecial
11/15/2023Lighting controlsAkeeb Shekonienergy_progress
11/15/2023Fenestration and door U-factor and product ratingsAkeeb Shekonienergy_progress
11/15/2023Maintenance informationAkeeb Shekonienergy_progress
11/15/2023Fenestration areasAkeeb Shekonienergy_progress
11/15/2023MasonryAkeeb Shekonispecial
11/15/2023Fire-Resistance Rated ConstructionAkeeb Shekoniprogress
11/15/2023Energy Code Compliance InspectionsAkeeb Shekoniprogress
11/15/2023Footing and FoundationAkeeb Shekoniprogress
11/15/2023Protection of exposed foundation insulationAkeeb Shekonienergy_progress
11/15/2023Fenestration air leakageAkeeb Shekonienergy_progress
10/10/2023Lighting controlsAkeeb Shekonienergy_progress
10/10/2023Protection of exposed foundation insulationAkeeb Shekonienergy_progress
10/10/2023Permanent certificateAkeeb Shekonienergy_progress
10/10/2023Construction Operations Influencing Adjacent StructuresAkeeb Shekonispecial
10/10/2023FinalHANSA PERSAUDprogress
10/10/2023Fire-Resistance Rated ConstructionAkeeb Shekoniprogress
10/10/2023Footing and FoundationAkeeb Shekoniprogress
10/10/2023Fenestration and door U-factor and product ratingsAkeeb Shekonienergy_progress
Latest 25 of 39.
▾Documents — 47 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/27/2026B00848542-I1Request digital key ↗
08/26/2026B00826610-I1Request digital key ↗
08/15/2026B00826610-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records6
▸DOB NOWRestrictive Declaration/Easement 22
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸DOB NOWRestrictive Declaration/Easement 12
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram2
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸Seals & Professional Certifications17
▸DOB NOWProgress Inspector Seal & Signature9
09/02/2026B00826610-P1Open ↗
09/02/2026B00826610-P1Open ↗
09/02/2026B00826610-P1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/27/2026B00848542-I1Open ↗
08/26/2026B00826610-I1Open ↗
08/13/2026B00848533-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026B00826610-P1Open ↗
09/01/2026B00826610-I1Open ↗
08/25/2026B00848533-I1Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸Safety & Tenant Protection2
▸DOB NOWStreet Tree Checklist2
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/27/2026B00848542-I1Open ↗
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
Showing 3 of 4 on file for this type
▸Inspections & Test Reports2
▸DOB NOWGeotechnical Report (BC 1803.6)2
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸Other Documents10
▸DOB NOWSite Survey: Initial2
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸DOB NOWPlot Diagram2
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸DOB NOWProperty Ownership Certification2
08/26/2026B00826610-I1Open ↗
08/13/2026B00826610-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00826610-I1Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00826610-I1Open ↗