← Back
Over six families without stores
203 17 STREET
BROOKLYN · BIN 3008926
💬 Discuss this project
1920Year Built
5Stories
C1Building Class
R6BZoning
18,960 sfGross Floor Area
29Units
Rent Stabilized24 Open Violations ▸
Over six families without stores · Owner of record: 203 17 ASSOCIATES LLC · 5,008 sf lot · 3.79 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Roof4p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
203 17 ASSOCIATES LLC203/22/2026
203 17 REALTY LLC1203/22/2026
203 17 ST REALTY LLC203/22/2026
203 17TH STREET,LLC103/22/2026
OTR MEDIA GROUP INC STE 51003/22/2026
AMA HOLDINGS703/22/2026
OTR MEDIA GROUP703/22/2026
203 17TH REALTY LLC1303/22/2026
203 17TH REALTY LLC/OR OW303/22/2026
203 17 ST103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
10/28/2021$7.8M—— → —$411/sf building
12/30/2013$6.5M—— → —$340/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TECTONIC ENGINEERING & SURVEYING CO204/21/2025
ARCNET ARCHITECTS INC.107/16/2019
ADVANTAGE ENGINEERS107/25/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CCM CONSULTING GROUP, INC.403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FEIN, STANLEYElectrical103/21/2026
JIMENEZ, CRISElectrical103/21/2026
CROSSLINK WIRELESS LLCGeneral Contractor107/08/2026
ETAK SYSTEMS LLCGeneral Contractor107/08/2026
JACOBS TELECOMMUN. INCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
TECTONIC ENGINEERING CONS106204/21/2025
PAPAY ENGINEERING & CONST4506107/16/2019
R MARSAC CONSULTING LLC329107/25/2018
Building Lifecycle
All (110)Filed (5)Permit Issued (4)Signed Off (3)Violation (60)Objection (20)Special Inspection (18)
08/02/2026
Violation issued (HPD, open)
A
08/02/2026
Violation issued (HPD, open)
B
08/02/2026
Violation issued (HPD, open)
B
08/02/2026
Violation issued (HPD, open)
B
08/02/2026
Violation issued (HPD, open)
B
08/02/2026
Violation issued (HPD, open)
A
08/02/2026
Violation issued (HPD, open)
A
08/02/2026
Violation issued (HPD, open)
B
08/02/2026
Violation issued (HPD, open)
A
08/02/2026
Violation issued (HPD, open)
B
08/02/2026
Violation issued (HPD, open)
A
08/02/2026
Violation issued (HPD, open)
A
05/01/2026
Violation issued (HPD, closed)
A
09/30/2025
Signed off — Alteration
B01140522-I1
09/22/2025
Permit issued — Suspended Scaffold
B01140522-I1-SC
06/06/2025
Violation issued (HPD, closed)
A
05/06/2025
Signed off — Alteration
Replacement of existing condensing units on roof. Replacement of existing air handling units in existing equipment room in basement. Replacement of existing lineset per plans. No change to occupancy, use, or egress.
B01024669-I1
04/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Manojkumar Patel
04/29/2025
Special inspection requirement — Post-installed Anchors
Manojkumar Patel
04/29/2025
Special inspection requirement — Tenant Protection Plan Compliance
Manojkumar Patel
04/29/2025
Special inspection requirement — Mechanical Systems
Manojkumar Patel
04/29/2025
Special inspection requirement — Final
Manojkumar Patel
04/29/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Manojkumar Patel
04/29/2025
Special inspection requirement — HVAC-R and service water heating equipment
Manojkumar Patel
04/29/2025
Special inspection requirement — HVAC-R and service water heating system controls
Manojkumar Patel
04/29/2025
Special inspection requirement — Maintenance information
Manojkumar Patel
04/21/2025
Filed — Alteration
Replacement of existing condensing units on roof. Replacement of existing air handling units in existing equipment room in basement. Replacement of existing lineset per plans. No change to occupancy, use, or egress.
B01024669-P1
02/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Manojkumar Patel
02/18/2025
Special inspection requirement — Mechanical Systems
Manojkumar Patel
02/18/2025
Special inspection requirement — Post-installed Anchors
Manojkumar Patel
02/18/2025
Special inspection requirement — Tenant Protection Plan Compliance
02/18/2025
Special inspection requirement — Final
Manojkumar Patel
02/18/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Manojkumar Patel
02/18/2025
Special inspection requirement — HVAC-R and service water heating equipment
Manojkumar Patel
02/18/2025
Special inspection requirement — Maintenance information
Manojkumar Patel
02/18/2025
Special inspection requirement — HVAC-R and service water heating system controls
Manojkumar Patel
01/29/2025
Violation issued (HPD, closed)
B
01/29/2025
Violation issued (HPD, closed)
C
01/29/2025
Violation issued (HPD, open)
B
01/29/2025
Violation issued (HPD, closed)
A
01/29/2025
Violation issued (HPD, closed)
B
11/25/2024
Permit issued — Mechanical Systems
B01024669-I1-GC-CX
11/17/2024
Filed — Alteration
B01140522-I1
10/30/2024
Objection resolved — Addressed
10/10/2024
Objection resolved — Addressed
09/30/2024
Objection resolved — Addressed
09/06/2024
Objection raised — Scope
09/06/2024
Objection raised — Zoning
09/06/2024
Objection raised — Energy
08/28/2024
Filed — Alteration
Replacement of existing condensing units on roof. Replacement of existing air handling units in existing equipment room in basement. Replacement of existing lineset per plans. No change to occupancy, use, or egress.
B01024669-I1
06/08/2024
Violation issued (HPD, closed)
C
04/19/2024
Violation issued (HPD, closed)
B
04/19/2024
Violation issued (HPD, closed)
B
04/19/2024
Violation issued (HPD, closed)
B
04/19/2024
Violation issued (HPD, closed)
B
04/19/2024
Violation issued (HPD, open)
C
04/19/2024
Violation issued (HPD, closed)
B
04/19/2024
Violation issued (HPD, closed)
B
04/19/2024
Violation issued (HPD, closed)
B
04/19/2024
Violation issued (HPD, closed)
B
Latest 60 of 110 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedJEPOL CONSTRUCTION INC09/22/2025
DOB NOWMechanical SystemsSigned-offETAK SYSTEMS LLC11/25/2024
DOB NOWAntennaSigned-offSTEADFAST DEVEL AND CONS08/27/2019
DOB NOWAntennaPermit IssuedARMENTUM DIGITAL INFRASTR02/27/2019
BISOTISSUEDBECHTEL INFRASTRUCTURE AN04/21/2017
BISOTISSUEDBECHTEL INFRASTRUCTURE AN10/17/2016
BISOTISSUEDBECHTEL INFRASTRUCTURE AN08/23/2016
BISEQISSUEDATCO RESTORATION INC03/09/2016
BISOTISSUEDBECHTEL INFRASTRUCTURE AN08/03/2015
BISMHISSUEDWIRELESS NETWORK GROUP IN11/19/2012
BISOTISSUEDEDWARDS AND KELCEY TECHNOLOGY07/01/2004
BISOTISSUEDTYREE ORGANIZATION10/24/2001
BISMHISSUEDCELLULAR TELEPHONE COMPANY02/25/1997
BISPLISSUEDELITE PLBG & HEATING01/12/1993
BISBLISSUEDEMPIRE STATE FUEL CORP01/12/1993
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
04/29/2025Fire-Resistant Penetrations and JointsManojkumar Patelspecial
04/29/2025Post-installed AnchorsManojkumar Patelspecial
04/29/2025Tenant Protection Plan ComplianceManojkumar Patelspecial
04/29/2025Mechanical SystemsManojkumar Patelspecial
04/29/2025FinalManojkumar Patelprogress
04/29/2025HVAC-R and service water piping design and insulationManojkumar Patelenergy_progress
04/29/2025HVAC-R and service water heating equipmentManojkumar Patelenergy_progress
04/29/2025HVAC-R and service water heating system controlsManojkumar Patelenergy_progress
04/29/2025Maintenance informationManojkumar Patelenergy_progress
02/18/2025Fire-Resistant Penetrations and JointsManojkumar Patelspecial
02/18/2025Mechanical SystemsManojkumar Patelspecial
02/18/2025Post-installed AnchorsManojkumar Patelspecial
02/18/2025Tenant Protection Plan Compliance—special
02/18/2025FinalManojkumar Patelprogress
02/18/2025HVAC-R and service water piping design and insulationManojkumar Patelenergy_progress
02/18/2025HVAC-R and service water heating equipmentManojkumar Patelenergy_progress
02/18/2025Maintenance informationManojkumar Patelenergy_progress
02/18/2025HVAC-R and service water heating system controlsManojkumar Patelenergy_progress
▾Documents — 84 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch2
08/23/2026B01140522-I1Request digital key ↗
08/14/2026B00003841-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Antenna1
09/02/2026B00184289-I1Request digital key ↗
▸Applications & Permits10
▸BISWORK PERMIT APPLICATION5
05/02/2017321456651Open ↗
10/18/2016321456651Open ↗
08/24/2016321365633Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION5
09/27/2016321456651Open ↗
04/13/2016321365633Open ↗
03/08/2016340359757Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications29
▸DOB NOWProgress Inspector Seal & Signature10
09/01/2026B01024669-I1Open ↗
09/01/2026B01024669-I1Open ↗
09/01/2026B01024669-I1Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
08/24/2017321456651Open ↗
11/22/2016321365633Open ↗
10/18/2016321456651Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/01/2026B01024669-I1Open ↗
09/01/2026B01024669-I1Open ↗
09/01/2026B01024669-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
09/03/2026B00003841-I1Open ↗
08/13/2026B00184289-I1Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/08/2016340359757Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
03/08/2016340359757Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
03/08/2016340359757Open ↗
▸Trade Schedules & Equipment2
▸BISFA - FDNY APPROVAL : FD-FAA2
10/25/2016321456651Open ↗
08/24/2016321365633Open ↗
▸Safety & Tenant Protection2
▸BISTenant Protection Plan and Notes2
09/27/2016321456651Open ↗
04/13/2016321365633Open ↗
▸Environmental & Asbestos6
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
09/27/2016321456651Open ↗
04/13/2016321365633Open ↗
07/06/2015321149119Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/14/2026B00003841-I1Open ↗
08/13/2026B00184289-I1Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS7
08/24/2017321456651Open ↗
11/22/2016321365633Open ↗
10/18/2016321456651Open ↗
Showing 3 of 7 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
08/24/2017321456651Open ↗
11/22/2016321365633Open ↗
06/15/2016321149119Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
03/08/2016340359757Open ↗
▸Approvals, Objections & Sign-offs6
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
08/24/2017321456651Open ↗
11/22/2016321365633Open ↗
06/15/2016321149119Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
07/06/2015321149119Open ↗
10/27/2012320564983Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
08/24/2017321456651Open ↗
▸Cost, Insurance & Ownership7
▸BISCOST AFFIDAVIT7
08/24/2017321456651Open ↗
11/22/2016321365633Open ↗
09/27/2016321456651Open ↗
Showing 3 of 7 on file for this type
▸Filing & Intake Forms6
▸BISEFILING COVER SHEET4
09/27/2016321456651Open ↗
04/13/2016321365633Open ↗
07/06/2015321149119Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM1
08/24/2017321456651Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
03/08/2016340359757Open ↗
▸Other Documents2
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
11/22/2016321365633Open ↗
▸DOB NOWIRA Certification1
08/13/2026B01140522-I1Open ↗