| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/19/2026 | Permit Issued | BEE DREAM HOUSE DESIGN IN | Heating and Air Conditioning Systems | Heat / Cool Gree LIV09HP230VIR32AH 9,100 BTU · Split System ×6 LIV18HP230VIR32AH 18,000 BTU · Split System ×3 LIV07HP230VIR32AH 7,000 BTU · Split System ×2 MULTI42HP230V1R32AO 42,000 BTU · Condensing Unit ×2 MULTI30HP230V1R32AO 28,400 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Permit Issued | JOHN FITZGERALD PLBG &HTG | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/27/2026 | Permit Issued | KWONG MING ELECTRIC INC | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| VK MODERN DESIGNS | 9 | 09/12/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/13/2025 | $1.2M | — | — → — | $739/sf building |
| 12/11/2013 | $790K | — | Private party → Private party | $467/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| BARRY DONALDSON ARCHITECTS | 5 | 08/19/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| S M TAM ARCHITECT | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KWONG MING ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| BEE DREAM HOUSE DESIGN IN | General Contractor | 1 | 04/09/2026 |
| JOHN FITZGERALD PLBG &HTG | Plumbing | 1 | 05/15/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BASSIRI | 8394 | 4 | 06/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | JOHN FITZGERALD PLBG &HTG | 05/13/2026 |
| DOB NOW | General Construction | Permit Issued | BEE DREAM HOUSE DESIGN IN | 12/05/2025 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/18/2026 | Mechanical Systems | — | special |
| 08/18/2026 | Energy Code Compliance Inspections | — | progress |
| 08/18/2026 | Final | — | progress |
| 08/18/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 08/18/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/18/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 08/18/2026 | Maintenance information | — | energy_progress |
| 06/10/2026 | HVAC-R and service water heating equipment | FARHAD BASSIRI-TEHRANI | energy_progress |
| 06/10/2026 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 06/10/2026 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 06/10/2026 | HVAC-R and service water piping design and insulation | FARHAD BASSIRI-TEHRANI | energy_progress |
| 06/10/2026 | Metering | FARHAD BASSIRI-TEHRANI | energy_progress |
| 06/10/2026 | Maintenance information | FARHAD BASSIRI-TEHRANI | energy_progress |
| 06/10/2026 | HVAC-R and service water heating system controls | FARHAD BASSIRI-TEHRANI | energy_progress |
| 03/02/2026 | Insulation placement and R values | FARHAD BASSIRI-TEHRANI | energy_progress |
| 03/02/2026 | Fire-Resistant Penetrations and Joints | FARHAD BASSIRI-TEHRANI | special |
| 03/02/2026 | Energy Code Compliance Inspections | FARHAD BASSIRI-TEHRANI | progress |
| 03/02/2026 | Fire-Resistance Rated Construction | FARHAD BASSIRI-TEHRANI | progress |
| 03/02/2026 | Fenestration air leakage | FARHAD BASSIRI-TEHRANI | energy_progress |
| 03/02/2026 | Air barrier - visual inspection | FARHAD BASSIRI-TEHRANI | energy_progress |
| 03/02/2026 | Fenestration and door U-factor and product ratings | FARHAD BASSIRI-TEHRANI | energy_progress |
| 03/02/2026 | Interior lighting power | FARHAD BASSIRI-TEHRANI | energy_progress |