| Owner | Filings | Most Recent |
|---|---|---|
| NYC SCHOOL CONSTRUCTION AUTHORITY | 41 | 07/08/2026 |
| NYC DEPARTMENT OF EDUCATION | 1 | 03/22/2026 |
| DEPARTMENT OF EDUCATION | 3 | 03/22/2026 |
| DEPT.OF EDUCATION P.S.159 | 1 | 03/22/2026 |
| PMY CONSTRUCTION | 2 | 03/22/2026 |
| PS 159 DOE | 13 | 03/22/2026 |
| DOE PS 159 040 | 8 | 03/22/2026 |
| AMCON CONTRACTING | 1 | 03/22/2026 |
| DEPT. OF EDUCATION 0 | 1 | 03/22/2026 |
| DOE P.S. 159 | 4 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STV INCORPORATED | 8 | 03/20/2026 |
| AK CONSULTING SERVICES, INC | 4 | 04/08/2025 |
| AME SERVICES INC | 3 | 07/26/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| STV | 14 | 03/21/2026 |
| AME SERVICES | 6 | 03/21/2026 |
| AK CONSULTING SERVICES | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMCON CONTRACTING CORP | General Contractor | 14 | 04/12/2026 |
| FIDELIS CONTRACTING INC | General Contractor | 8 | 07/08/2026 |
| ROMA SCAFFOLDING INC | General Contractor | 7 | 07/08/2026 |
| VARSITY PLBG AND HTG INC | Plumbing | 3 | 07/08/2026 |
| PACIFIC ELEC'L CONTR'G IN | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| UNIVERSAL TESTING AND INS | 400 | 10 | 12/17/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | AMCON CONTRACTING CORP | 04/10/2026 |
| DOB NOW | General Construction | Permit Issued | AMCON CONTRACTING CORP | 04/10/2026 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 10/14/2025 |
| DOB NOW | Support of Excavation | Signed-off | FIDELIS CONTRACTING INC | 07/18/2025 |
| DOB NOW | Construction Fence | Signed-off | AMCON CONTRACTING CORP | 04/10/2025 |
| DOB NOW | General Construction | Signed-off | AMCON CONTRACTING CORP | 04/04/2025 |
| DOB NOW | Structural | Permit Issued | AMCON CONTRACTING CORP | 04/04/2025 |
| DOB NOW | Support of Excavation | Signed-off | FIDELIS CONTRACTING INC | 02/19/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | ROMA SCAFFOLDING INC | 02/04/2025 |
| DOB NOW | Supported Scaffold | Signed-off | ROMA SCAFFOLDING INC | 01/13/2025 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 10/15/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | ROMA SCAFFOLDING INC | 09/13/2024 |
| DOB NOW | Construction Fence | Signed-off | AMCON CONTRACTING CORP | 04/09/2024 |
| DOB NOW | General Construction | Permit Issued | AMCON CONTRACTING CORP | 04/04/2024 |
| DOB NOW | General Construction | Signed-off | AMCON CONTRACTING CORP | 03/28/2024 |
| DOB NOW | Structural | Permit Issued | AMCON CONTRACTING CORP | 03/28/2024 |
| DOB NOW | Construction Fence | Signed-off | AMCON CONTRACTING CORP | 03/28/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ROMA SCAFFOLDING INC | 01/22/2024 |
| DOB NOW | Plumbing | Permit Issued | VARSITY PLBG AND HTG INC | 10/10/2023 |
| DOB NOW | Structural | Signed-off | AMCON CONTRACTING CORP | 10/06/2023 |
| DOB NOW | Structural | Permit Issued | AMCON CONTRACTING CORP | 10/06/2023 |
| DOB NOW | Construction Fence | Signed-off | AMCON CONTRACTING CORP | 09/12/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | JSK 2 CORP | 09/12/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ROMA SCAFFOLDING INC | 09/11/2023 |
| DOB NOW | Support of Excavation | Signed-off | FIDELIS CONTRACTING INC | 07/27/2022 |
| DOB NOW | Construction Fence | Signed-off | FIDELIS CONTRACTING INC | 07/05/2022 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 08/04/2025 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 08/04/2025 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 08/08/2024 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 08/08/2024 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 07/31/2024 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 07/24/2023 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 07/24/2023 |
| BIS | OT | ISSUED | PMY CONSTRUCTION CORP | 08/29/2022 |
| BIS | OT | ISSUED | FIDELIS CONTRACTING INC | 07/27/2022 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 07/27/2022 |
| BIS | PL | ISSUED | VARSITY PLBG AND HTG INC | 07/27/2022 |
| BIS | OT | ISSUED | FIDELIS CONTRACTING INC | 07/27/2022 |
| BIS | OT | ISSUED | PMY CONSTRUCTION CORP | 11/30/2020 |
| BIS | OT | ISSUED | PMY CONSTRUCTION CORP | 11/12/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | Permit Issued | VARSITY PLBG AND HTG INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/20/2026 | Permit Issued | PRECISION ELECL CONT CORP | General Wiring |
| 11/04/2024 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 11/07/2023 | Permit Issued | PACIFIC ELEC'L CONTR'G IN | — |
| 10/27/2023 | Complete | MILAD CONTRACTING CORP. | General Wiring, Lighting |
| 09/07/2023 | Complete | HYLAN DATACOM & ELECL LLC | — |
| 09/22/2020 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 06/03/2020 | Complete | DYNAMO ELECTRICAL CORP | General Wiring |
| 03/13/2020 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 09/19/2019 | Complete | CHARAN ELEC'L ENTERP'S IN | — |
| 01/24/2019 | Complete | J & Y ELECTRIC AND INTER* | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/20/2026 | Signed-off | AMCON CONTRACTING CORP | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/09/2022 | Signed-off | FIDELIS CONTRACTING INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/24/2026 | Lighting controls | NELSON LOPEZ | energy_progress |
| 02/24/2026 | Insulation placement and R values | NELSON LOPEZ | energy_progress |
| 02/24/2026 | Fenestration and door U-factor and product ratings | NELSON LOPEZ | energy_progress |
| 02/24/2026 | Fenestration air leakage | NELSON LOPEZ | energy_progress |
| 02/24/2026 | Exterior lighting power | NELSON LOPEZ | energy_progress |
| 02/24/2026 | Final | NELSON LOPEZ | progress |
| 02/24/2026 | Energy Code Compliance Inspections | NELSON LOPEZ | progress |
| 02/24/2026 | Structural Steel - Details | NELSON LOPEZ | special |
| 02/24/2026 | Structural Stability – Alterations of existing buildings | NELSON LOPEZ | special |
| 02/24/2026 | Subgrade Inspections | NELSON LOPEZ | special |
| 02/24/2026 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 02/24/2026 | Structural Steel - Welding | NELSON LOPEZ | special |
| 02/24/2026 | Concrete - Cast-In-Place | NELSON LOPEZ | special |
| 02/24/2026 | Post-installed Anchors | NELSON LOPEZ | special |
| 02/24/2026 | Masonry | NELSON LOPEZ | special |
| 02/24/2026 | Subsurface Conditions – Fill Placement & In-Place Density | NELSON LOPEZ | special |
| 02/18/2026 | Fire-Resistant Penetrations and Joints | NELSON LOPEZ | special |
| 12/15/2025 | Final | NELSON LOPEZ | progress |
| 12/15/2025 | Concrete - Cast-In-Place | NELSON LOPEZ | special |
| 12/15/2025 | Masonry | NELSON LOPEZ | special |
| 12/15/2025 | Post-installed Anchors | NELSON LOPEZ | special |
| 12/15/2025 | Structural Stability – Alterations of existing buildings | NELSON LOPEZ | special |
| 12/15/2025 | Structural Steel - Details | NELSON LOPEZ | special |
| 12/15/2025 | Structural Steel - Welding | NELSON LOPEZ | special |
| 12/15/2025 | Subgrade Inspections | NELSON LOPEZ | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| P.S. 159 | Education | — | Project Q00722959 |