| Owner | Filings | Most Recent |
|---|---|---|
| KEY DEVELOPERS | 12 | 07/08/2026 |
| OWNERS REP | 5 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS | 2 | 03/21/2026 |
| 206-210 PARKVILLE AVENUE REALTY LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/06/2013 | $400K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| JOSE LOCKHART, P.E. | 2 | 03/04/2020 |
| DOOLING & COMPANY ARCHITECTS | 2 | 09/17/2019 |
| KZ ENGINEERING, P.C | 2 | 07/12/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| BDP EXPEDITERS GROUP | 2 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KEY DEVELOPERS INC | General Contractor | 16 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 4 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 3 | 03/22/2026 |
| TFK ELECTRIC CORP | Electrical | 2 | 03/22/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Permit Issued | KEY DEVELOPERS INC | 06/01/2020 |
| DOB NOW | Construction Fence | Signed-off | KEY DEVELOPERS INC | 04/06/2020 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 09/17/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 09/17/2019 |
| DOB NOW | Construction Fence | Signed-off | KEY DEVELOPERS INC | 07/15/2019 |
| DOB NOW | Supported Scaffold | Signed-off | KEY DEVELOPERS INC | 07/12/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | KEY DEVELOPERS INC | 07/12/2019 |
| BIS | PL | ISSUED | PRIME PIPING & HEATING IN | 06/22/2020 |
| BIS | SP | ISSUED | PRIME PIPING & HEATING IN | 01/29/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/04/2020 | Complete | TFK ELECTRIC CORP | 145 meters, 145 new_meters |
| 06/04/2020 | Complete | TFK ELECTRIC CORP | General Wiring |
| 06/04/2020 | Complete | TFK ELECTRIC CORP | General Wiring |
| 10/05/2019 | Complete | TFK ELECTRIC CORP | — |
| 09/16/2019 | Complete | V. VASS ELECTRIC CORP | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/05/2019 | Final | Karol Zdancewicz | progress |