← Back
Public elementary, junior or senior high
The Stephanie A. Vierno School
200 OTIS AVENUE · BIN 5052791
💬 Discuss this project
1931Year Built
3Stories
W1Building Class
R3XZoning
86,850 sfGross Floor Area
1Units
2 Open Violations 0 unresolved · 2 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC DEPARTMENT OF EDUCATION · 100,000 sf lot · 0.87 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionCivilGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction12p · 2 filings · 20 docs
Floor 3Under Construction16p · 3 filings · 20 docs
Floor 2Under Construction10p · 3 filings · 20 docs
Floor 1Under Construction11p · 3 filings · 20 docs
CellarUnder Construction56p · 3 filings · 20 docs
Basement2p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC SCHOOL CONSTRUCTION AUTHORITY9709/13/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
DEPT OF EDUCATION PS.41 0403/22/2026
D.O.E. P.S.41 0503/22/2026
DEPARTMENT OF EDUCATION203/22/2026
DOE P.S.411403/22/2026
DOE PS 41 040903/22/2026
DOE PS 41 NEW DORP 040103/22/2026
PS 41 DEPT OF EDUCATION203/22/2026
PS 41 DEPT OF ED103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PRECISION 3SIXTY NYC, INC2403/21/2026
NYC SCHOOL CONSTRUCTION AUTHORITY903/21/2026
DSENY ENGINEERING SERVICES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KG CONSTRUCTION SERVICESGeneral Contractor2208/22/2026
MARIC PLUMBING & HEATINGGeneral Contractor2107/08/2026
R.A.M.S. MECHANICAL INCGeneral Contractor1807/08/2026
V. C. VITANZA SONS INCPlumbing407/08/2026
WHITESTONE CONSTRUCTION CORPGeneral Contractor307/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MUNICIPAL TESTING LABORAT2302808/14/2026
Building Lifecycle
All (236)Filed (40)Permit Issued (58)Signed Off (1)Violation (60)Inspection (5)Objection (42)Special Inspection (30)
08/21/2026
Permit issued — Sidewalk Shed
S01098967-I1-SH
08/20/2026
Objection resolved — Addressed
08/20/2026
Special inspection requirement — Masonry
08/18/2026
Objection raised — Other
08/14/2026
Filed — Alteration
Remove & Replace existing , Roofing systems, Parapets, bulkhead doors & Sills, steel lintels, windows,& guards. Repoint all masonry joints at all elevations, broken bricks replacement, replace Sealants at masonry openings. Interior ceiling plaster repairs
S00922659-P5
08/13/2026
Special inspection requirement — Masonry
STEPHEN LATUS
08/13/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
STEPHEN LATUS
08/13/2026
Special inspection requirement — Structural Steel - Welding
STEPHEN LATUS
08/13/2026
Special inspection requirement — Structural Steel - High Strength Bolting
STEPHEN LATUS
08/13/2026
Special inspection requirement — Post-installed Anchors
STEPHEN LATUS
08/13/2026
Special inspection requirement — Concrete - Cast-In-Place
STEPHEN LATUS
08/13/2026
Special inspection requirement — Final
STEPHEN LATUS
08/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
STEPHEN LATUS
08/13/2026
Special inspection requirement — Fire-Resistance Rated Construction
STEPHEN LATUS
08/13/2026
Special inspection requirement — Structural Steel - Details
STEPHEN LATUS
07/10/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
STEPHEN LATUS
07/10/2026
Special inspection requirement — Sprinkler Systems
07/10/2026
Special inspection requirement — Post-installed Anchors
STEPHEN LATUS
07/02/2026
Filed — Alteration
REMOVE AND REPLACE CONCRETE PAVEMENT AND SUBBASE. INSTALL SHEET MEMBRANE WATERPROOFING AT EXISTING BOILER PIT. PERFORM INJECTION GROUTING AT EXISTING FOUNDATION WALL
S01016639-P2
06/25/2026
Special inspection requirement — Concrete - Cast-In-Place
STEPHEN LATUS
06/25/2026
Special inspection requirement — Post-installed Anchors
STEPHEN LATUS
06/25/2026
Special inspection requirement — Structural Steel - Welding
STEPHEN LATUS
06/25/2026
Special inspection requirement — Structural Steel - High Strength Bolting
STEPHEN LATUS
06/25/2026
Special inspection requirement — Final
STEPHEN LATUS
06/25/2026
Special inspection requirement — Fire-Resistance Rated Construction
STEPHEN LATUS
06/25/2026
Special inspection requirement — Structural Steel - Details
STEPHEN LATUS
06/25/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
STEPHEN LATUS
06/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
STEPHEN LATUS
06/24/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/22/2026
Filed — Alteration
Remove & Replace existing , Roofing systems, Parapets, bulkhead doors & Sills, steel lintels, windows,& guards. Repoint all masonry joints at all elevations, broken bricks replacement, replace Sealants at masonry openings. Interior ceiling plaster repairs
S00922659-P4
06/22/2026
Special inspection requirement — Final
STEPHEN LATUS
06/22/2026
Special inspection requirement — Concrete - Cast-In-Place
STEPHEN LATUS
06/22/2026
Special inspection requirement — Fire-Resistance Rated Construction
STEPHEN LATUS
06/22/2026
Special inspection requirement — Structural Steel - Welding
STEPHEN LATUS
06/22/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
STEPHEN LATUS
06/22/2026
Special inspection requirement — Structural Steel - Details
STEPHEN LATUS
06/22/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
STEPHEN LATUS
05/26/2026
Permit issued — Sidewalk Shed
S01098967-I1-SH
05/15/2026
Inspection — Under Review Boiler Equipment Inspection
Under Review
View inspection ↗
05/05/2026
Permit issued — Boiler Equipment
S01016639-I1-BE
05/01/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/07/2026
Filed — Alteration
Remove & Replace existing , Roofing systems, Parapets, bulkhead doors & Sills, steel lintels, windows,& guards. Repoint all masonry joints at all elevations, broken bricks replacement, replace Sealants at masonry openings. Interior ceiling plaster repairs
S00922659-P3
04/02/2026
Permit issued — Mechanical Systems
S01016639-S3-MS
04/02/2026
Permit issued — Mechanical Systems
S00922659-S1-MS
04/02/2026
Permit issued — Mechanical Systems
S00539124-S2-MS
03/25/2026
Permit issued — Mechanical Systems
S01016639-S3-MS
03/25/2026
Permit issued — Mechanical Systems
S00922659-S1-MS
03/25/2026
Permit issued — Mechanical Systems
S00539124-S2-MS
03/25/2026
Violation issued (FDNY_ORDER, closed)
03/25/2026
Violation issued (FDNY_ORDER, closed)
03/24/2026
Permit issued — Mechanical Systems
S00539124-S2-MS
03/24/2026
Permit issued — Mechanical Systems
S00922659-S1-MS
03/20/2026
Permit issued — Mechanical Systems
S01016639-S3-MS
03/19/2026
Permit issued — General Construction
S00922659-I1-GC-CX
03/19/2026
Permit issued — Structural
S01016639-S2-ST
03/19/2026
Permit issued — General Construction
S01016639-S5-GC-CX
03/19/2026
Permit issued — General Construction
S01016639-S1-GC
03/04/2026
Permit issued — Mechanical Systems
S00539124-S2-MS
02/25/2026
Permit issued — Sidewalk Shed
S01098967-I1-SH
02/18/2026
Permit issued — Plumbing
S00922659-S2-PL
Latest 60 of 236 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedKG CONSTRUCTION SERVICES08/21/2026
DOB NOWSidewalk ShedPermit IssuedKG CONSTRUCTION SERVICES05/26/2026
DOB NOWBoiler EquipmentPermit IssuedCHAMPION COMBUSTION CORP05/05/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC04/02/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC04/02/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC04/02/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/25/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/25/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/25/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/24/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/24/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/20/2026
DOB NOWGeneral ConstructionPermit IssuedSTALCO03/19/2026
DOB NOWStructuralPermit IssuedSTALCO03/19/2026
DOB NOWGeneral ConstructionPermit IssuedSTALCO03/19/2026
DOB NOWGeneral ConstructionPermit IssuedSTALCO03/19/2026
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/04/2026
DOB NOWSidewalk ShedPermit IssuedSTALCO02/25/2026
DOB NOWPlumbingPermit IssuedV. C. VITANZA SONS INC02/18/2026
DOB NOWPlumbingPermit IssuedV. C. VITANZA SONS INC02/18/2026
DOB NOWSidewalk ShedPermit IssuedSTALCO01/15/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedSTALCO01/12/2026
DOB NOWSupported ScaffoldPermit IssuedSTALCO01/12/2026
DOB NOWConstruction FencePermit IssuedSTALCO01/12/2026
DOB NOWConstruction FencePermit IssuedR.A.M.S. MECHANICAL INC10/06/2025
DOB NOWBoiler EquipmentPermit IssuedCHAMPION COMBUSTION CORP05/09/2025
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/26/2025
DOB NOWBoiler EquipmentPermit IssuedCHAMPION COMBUSTION CORP03/25/2025
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/24/2025
DOB NOWPlumbingPermit IssuedV. C. VITANZA SONS INC03/20/2025
DOB NOWPlumbingPermit IssuedV. C. VITANZA SONS INC03/20/2025
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC03/20/2025
DOB NOWStructuralPermit IssuedSTALCO03/19/2025
DOB NOWEarth WorkPermit IssuedSTALCO03/19/2025
DOB NOWStructuralPermit IssuedSTALCO03/18/2025
DOB NOWGeneral ConstructionPermit IssuedSTALCO03/18/2025
DOB NOWMechanical SystemsPermit IssuedMARIC PLUMBING & HEATING03/06/2025
DOB NOWConstruction FencePermit IssuedMARIC PLUMBING & HEATING03/06/2025
DOB NOWMechanical SystemsPermit IssuedR.A.M.S. MECHANICAL INC02/05/2025
DOB NOWSupported ScaffoldPermit IssuedSTALCO01/31/2025
+ 33 more permits on file
2 projects · most recent 08/14/2026
Ventilation Systems Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/14/2026Permit IssuedR.A.M.S. MECHANICAL INCVentilation Systems
Ventilation
Greenheck GRSR-8 1 CFM · Exhaust Fan ×2
Cube -160 1,355 CFM · Exhaust Fan ×1
GRSI-10 Exhaust Fan ×1
WIH ×1
09/21/2023——Heating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric TPLFYP008EM140B 8,000 BTU · Vrf Indoor ×16
PCFY-P15NKMU-ER1 15,000 BTU · Vrf Indoor ×2
TPKFYP024KM142A 24,000 BTU · Vrf Indoor ×2
TUHYE0723AN40AN 72,000 BTU · Vrf Outdoor ×2
TUHYE1203AN40AN 120,000 BTU · Vrf Outdoor ×1
Ventilation
Systemair S26128P 5 tons · Heat Pump Outdoor ×35
Annexair ERP-E-07-EW03-HE-DHR-ASHP 7,500 CFM · Ahu ×3
Greenheck CUBE-100 900 CFM · Kitchen Exhaust ×1
Lg ARDE-112-36D-10A-1-A1 2,500 CFM · Ahu ×1
4 projects · most recent 08/14/2026
Storm Water/Sanitary Gas
FiledStatusContractorScope
08/14/2026Permit IssuedV. C. VITANZA SONS INCStorm
07/02/2026Permit IssuedV. C. VITANZA SONS INCStorm, Water/Sanitary
09/21/2023——Gas, Water/Sanitary
10/18/2022——Storm, Water/Sanitary
12 projects · most recent 04/22/2025
General Wiring Lighting
FiledStatusContractorScope
04/22/2025Permit IssuedSTANCO SYSTEM ELEC'L CONTGeneral Wiring
01/28/2025Permit IssuedLIT MODE ELECL CONTG INC—
03/10/2023CompleteCHARAN ELEC'L ENTERP'S IN—
08/29/2022CompleteHEXAGON CONST & ELECL GRP—
08/10/2021Permit IssuedGEMINI ELECTRIC CO., INC.General Wiring
07/26/2021Permit IssuedSTANCO SYSTEM ELEC'L CONT—
05/20/2021CompleteKLK ELECTRIC, INCGeneral Wiring, Lighting
11/27/2019CompleteCHARAN ELEC'L ENTERP'S INGeneral Wiring
11/06/2018CompleteCHARAN ELEC'L ENTERP'S IN—
10/08/2018CompleteE ELEC'L CONTR'G LLC—
08/13/2018CompleteENERGIZE ELC'L CNTRG CORPGeneral Wiring
05/17/2018CompleteCHARAN ELEC'L ENTERP'S IN—
4 projects · most recent 08/14/2026
Concrete Steel Masonry
FiledStatusContractorScope
08/14/2026Permit IssuedR.A.M.S. MECHANICAL INCConcrete, Masonry
07/02/2026Permit IssuedCHAMPION COMBUSTION CORPSteel, Concrete
09/21/2023——Steel, Concrete
10/18/2022——Steel, Concrete
3 projects · most recent 09/23/2025
Fence Scaffold
FiledStatusContractorScope
09/23/2025Permit IssuedR.A.M.S. MECHANICAL INCFence
12/18/2024Permit IssuedKG CONSTRUCTION SERVICESFence
12/18/2024Permit IssuedKG CONSTRUCTION SERVICESScaffold
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
06/24/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/15/2026Under Review Boiler Equipment InspectionUnder ReviewView ↗
05/01/2026Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
11/28/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/22/2021Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 114
DateRequirementInspectorRole
08/20/2026Masonry—special
08/13/2026Fire-Resistance Rated ConstructionSTEPHEN LATUSprogress
08/13/2026Post-installed AnchorsSTEPHEN LATUSspecial
08/13/2026Fire-Resistant Penetrations and JointsSTEPHEN LATUSspecial
08/13/2026MasonrySTEPHEN LATUSspecial
08/13/2026Structural Steel - WeldingSTEPHEN LATUSspecial
08/13/2026Structural Steel - High Strength BoltingSTEPHEN LATUSspecial
08/13/2026Structural Steel - DetailsSTEPHEN LATUSspecial
08/13/2026Structural Stability – Alterations of existing buildingsSTEPHEN LATUSspecial
08/13/2026FinalSTEPHEN LATUSprogress
08/13/2026Concrete - Cast-In-PlaceSTEPHEN LATUSspecial
07/10/2026Fire-Resistant Penetrations and JointsSTEPHEN LATUSspecial
07/10/2026Post-installed AnchorsSTEPHEN LATUSspecial
07/10/2026Sprinkler Systems—special
06/25/2026Fire-Resistant Penetrations and JointsSTEPHEN LATUSspecial
06/25/2026Structural Steel - High Strength BoltingSTEPHEN LATUSspecial
06/25/2026Fire-Resistance Rated ConstructionSTEPHEN LATUSprogress
06/25/2026Post-installed AnchorsSTEPHEN LATUSspecial
06/25/2026Concrete - Cast-In-PlaceSTEPHEN LATUSspecial
06/25/2026Structural Steel - WeldingSTEPHEN LATUSspecial
06/25/2026Structural Steel - DetailsSTEPHEN LATUSspecial
06/25/2026Structural Stability – Alterations of existing buildingsSTEPHEN LATUSspecial
06/25/2026FinalSTEPHEN LATUSprogress
06/22/2026Structural Steel - High Strength Bolting—special
06/22/2026Fire-Resistance Rated ConstructionSTEPHEN LATUSprogress
Latest 25 of 114.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
P.S. 041r The Stephanie A. Vierno SchoolEducation—
Project S07997085 Alteration · Filing Withdrawn · 10/06/2022
Read from each project’s drawing title blocks and cover sheets and checked twice; a name appears only when it is the occupant, never the owner, landlord or designer.
▾Documents — 282 on file (BIS + DOB NOW)
▸Plans & Drawings41
▸DOB NOWPlans/Sketch41
08/25/2026S00539124-P2Request digital key ↗
08/25/2026S00539124-P1Request digital key ↗
08/25/2026S00539124-P3Request digital key ↗
Showing 3 of 41 on file for this type
▸Seals & Professional Certifications82
▸DOB NOWDPL-1: Design Professional Seal & Signature40
08/25/2026S00539124-P1Open ↗
08/25/2026S00539124-P2Open ↗
08/25/2026S00539124-S2Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature26
09/29/2026S01016639-S5Open ↗
09/25/2026S00539124-P2Open ↗
09/23/2026S01016639-I1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWProgress Inspector Seal & Signature16
09/29/2026S01016639-S5Open ↗
09/06/2026S07997085-S2Open ↗
09/01/2026S00922659-P1Open ↗
Showing 3 of 16 on file for this type
▸Safety & Tenant Protection8
▸DOB NOWNYCSCA - Approved Site Safety Plans8
08/13/2026S00539124-P1Open ↗
08/13/2026S00539124-P4Open ↗
08/13/2026S01098967-P1Open ↗
Showing 3 of 8 on file for this type
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/25/2026S00539124-P2Open ↗
08/25/2026S00539124-S2Open ↗
08/25/2026S00539124-P3Open ↗
Showing 3 of 5 on file for this type
▸Approvals, Objections & Sign-offs95
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter40
08/25/2026S00539124-P3Open ↗
08/25/2026S00539124-P2Open ↗
08/25/2026S00539124-P1Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)40
08/17/2026S01016639-S4Open ↗
08/17/2026S01016639-P2Open ↗
08/17/2026S00922659-P5Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWDEP Variance (V5) letter10
08/13/2026S01016639-I1Open ↗
08/13/2026S01016639-S2Open ↗
08/13/2026S01016639-S7Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)5
08/13/2026S07997085-S4Open ↗
08/13/2026S07997085-S1Open ↗
08/13/2026S07997085-S2Open ↗
Showing 3 of 5 on file for this type
▸Other Documents51
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal40
08/17/2026S01016639-S4Open ↗
08/17/2026S01016639-P2Open ↗
08/17/2026S00922659-P4Open ↗
Showing 3 of 40 on file for this type
▸DOB NOWProof of Historic Building9
08/17/2026S00922659-P4Open ↗
08/17/2026S00922659-P5Open ↗
08/13/2026S00936685-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWNYCSCA Exhibit 21
08/13/2026S00936685-I1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026S01016639-S5Open ↗