← Back
Condo, residential tower (mixed-use, multi-family elevator) [derived]
Tower 85 Condominium
2066 85TH STREET · BIN 3165844
💬 Discuss this project
2020Year Built
4Stories
RMBuilding Class
R5Zoning
14,987 sfGross Floor Area
22Units
0 Open ViolationsFDNY Report ↗
Condo, residential tower (mixed-use, multi-family elevator) [derived] · Owner of record: 2066 85 ST BK LLC · 6,666 sf lot · 2.25 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingFire Protection
Roof2p · 1 filing · 8 docs
Floor 42p · 1 filing · 11 docs
Floor 32p · 2 filings · 19 docs
Floor 22p · 2 filings · 19 docs
Floor 12p · 2 filings · 20 docs
Cellar2p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SD DESIGN STUDIO807/08/2026
H & 2 BUILDING CONSULTING103/22/2026
H7 Z BUILDING CONSTRUCTIO103/22/2026
2066 85ST BK1903/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JIMENEZ BUILDING CONSULTING LLC1003/03/2023
BASIC GROUPS CORP208/13/2021
ASHRAF CORP105/28/2020
SD DESIGN STUDIO LLC107/08/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JRL SKYLINE2403/21/2026
EUROCELT EXPEDITING, INC203/21/2026
H Z BUILDING NY203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
H&Z BUILDING CONSULTING IGeneral Contractor507/08/2026
99 CONSTRUCTION INCGeneral Contractor303/21/2026
WINWAY DEVELOPMENT LLCGeneral Contractor307/08/2026
K & BH PLUMBING & HTG INCPlumbing207/08/2026
UNIVERSAL SYSTEMS INCGeneral Contractor107/08/2026
ACCURATE MECHANICAL INCFire Protection107/08/2026
PETER LIElectrical103/21/2026
FLUSHING PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SD TESTING & INSPECTION S7010503/03/2023
JIMENEZ BUILDING CONSULTI7944511/08/2021
NY ACOM ENGINEERING PLLC7061109/19/2020
Building Lifecycle
All (102)Filed (14)Permit Issued (10)Signed Off (8)Violation (23)Inspection (7)Objection (10)Special Inspection (30)
03/09/2023
Signed off — Alteration
PROPOSE FILE APPLICATION TO RENOVATION ON 001 FLOOR. FLOOR CEILING & PARTITION WORKS AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00723579-I1
03/09/2023
Signed off — Alteration
PROPOSED INTERIOR RENOVATION ON 1ST FLOOR. PLUMBING WORK AS PER PLAN. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
B00726718-I1
03/07/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
03/06/2023
Special inspection requirement — HVAC-R and service water heating equipment
XIUCHENG LI
03/06/2023
Special inspection requirement — Final
XIUCHENG LI
03/06/2023
Special inspection requirement — Energy Code Compliance Inspections
XIUCHENG LI
03/06/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
XIUCHENG LI
03/06/2023
Special inspection requirement — Fire-Resistance Rated Construction
XIUCHENG LI
03/06/2023
Special inspection requirement — Air barrier - visual inspection
XIUCHENG LI
03/06/2023
Special inspection requirement — Lighting controls
XIUCHENG LI
03/06/2023
Special inspection requirement — Maintenance information
XIUCHENG LI
03/06/2023
Special inspection requirement — Mechanical Systems
XIUCHENG LI
03/06/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
XIUCHENG LI
03/06/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
XIUCHENG LI
03/06/2023
Special inspection requirement — Shutoff dampers
XIUCHENG LI
03/06/2023
Special inspection requirement — HVAC-R and service water heating system controls
XIUCHENG LI
03/06/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIUCHENG LI
03/06/2023
Special inspection requirement — Fenestration air leakage
XIUCHENG LI
03/06/2023
Special inspection requirement — Duct leakage testing, insulation and design
XIUCHENG LI
03/06/2023
Special inspection requirement — Exterior lighting power
XIUCHENG LI
03/06/2023
Special inspection requirement — Fenestration areas
XIUCHENG LI
03/06/2023
Special inspection requirement — Interior lighting power
XIUCHENG LI
03/03/2023
Filed — Alteration
PROPOSE FILE APPLICATION TO RENOVATION ON 001 FLOOR. FLOOR CEILING & PARTITION WORKS AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00723579-P2
03/03/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
XIUCHENG LI
03/03/2023
Special inspection requirement — HVAC-R and service water heating system controls
XIUCHENG LI
03/03/2023
Special inspection requirement — Fenestration air leakage
XIUCHENG LI
03/03/2023
Special inspection requirement — Final
XIUCHENG LI
03/03/2023
Special inspection requirement — Fire-Resistance Rated Construction
XIUCHENG LI
03/03/2023
Special inspection requirement — Fenestration areas
XIUCHENG LI
03/03/2023
Special inspection requirement — Energy Code Compliance Inspections
XIUCHENG LI
03/03/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIUCHENG LI
03/03/2023
Special inspection requirement — Mechanical Systems
XIUCHENG LI
03/03/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
XIUCHENG LI
03/03/2023
Special inspection requirement — HVAC-R and service water heating equipment
XIUCHENG LI
12/29/2022
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
12/23/2022
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
12/16/2022
Filed — Alteration
PROPOSE FILE APPLICATION TO RENOVATION ON 001 FLOOR. FLOOR CEILING & PARTITION WORKS AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00723579-P1
10/26/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
07/05/2022
Filed — Alteration
PROPOSED INTERIOR RENOVATION ON 1ST FLOOR. PLUMBING WORK AS PER PLAN. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
B00726718-P1
06/29/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/10/2022
Permit issued — Plumbing
B00726718-I1-PL
05/02/2022
Permit issued — General Construction
B00723579-I1-GC-CX
04/27/2022
Filed — Alteration
PROPOSE FILE APPLICATION TO RENOVATION ON 001 FLOOR. FLOOR CEILING & PARTITION WORKS AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00723579-I1
04/27/2022
Filed — Alteration
PROPOSED INTERIOR RENOVATION ON 1ST FLOOR. PLUMBING WORK AS PER PLAN. NO CHANGE IN USE, BULK, EGRESS OR OCCUPANCY.
B00726718-I1
01/10/2022
Signed off — Alteration
FILED SPRINKLER WORK TYPE IN CONJUNCTION WITH ALT-1 APPLICATION#321387968
B00480636-I1
11/17/2021
Signed off — Alteration
INSTALL (11) COMBI-BOILERS ON 2ND, 3RD, AND 4TH FLOOR AS PER PLAN. CONSTRUCTION WORK UNDER SEPARATE APPLICATION #321387968.
B00594252-I1
11/15/2021
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
11/08/2021
Filed — Alteration
INSTALL (11) COMBI-BOILERS ON 2ND, 3RD, AND 4TH FLOOR AS PER PLAN. CONSTRUCTION WORK UNDER SEPARATE APPLICATION #321387968.
B00594252-P2
10/05/2021
Filed — Alteration
INSTALL (11) COMBI-BOILERS ON 2ND, 3RD, AND 4TH FLOOR AS PER PLAN. CONSTRUCTION WORK UNDER SEPARATE APPLICATION #321387968.
B00594252-P1
10/05/2021
Signed off — Alteration
install new curb cut
B00530397-I1
10/04/2021
Signed off — Alteration
B00190169-I1
09/30/2021
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
09/27/2021
Permit issued — Curb Cut
B00530397-I1-CC
09/27/2021
Permit issued — Boiler Equipment
B00594252-I1-BE
09/20/2021
Filed — Alteration
INSTALL (11) COMBI-BOILERS ON 2ND, 3RD, AND 4TH FLOOR AS PER PLAN. CONSTRUCTION WORK UNDER SEPARATE APPLICATION #321387968.
B00594252-I1
08/13/2021
Filed — Alteration
FILED SPRINKLER WORK TYPE IN CONJUNCTION WITH ALT-1 APPLICATION#321387968
B00480636-P1
06/23/2021
Signed off — Alteration
B00392344-I1
06/08/2021
Objection raised — Scope
06/08/2021
Objection resolved — Addressed
06/08/2021
Objection raised — Other
Latest 60 of 102 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offK & BH PLUMBING & HTG INC06/10/2022
DOB NOWGeneral ConstructionSigned-offWINWAY DEVELOPMENT LLC05/02/2022
DOB NOWCurb CutSigned-offSONG DONG09/27/2021
DOB NOWBoiler EquipmentSigned-offFLUSHING PLUMBING CORP09/27/2021
DOB NOWSprinklersSigned-offACCURATE MECHANICAL INC04/20/2021
DOB NOWConstruction FenceSigned-offH&Z BUILDING CONSULTING I01/11/2021
DOB NOWSupported ScaffoldSigned-offWINWAY DEVELOPMENT LLC09/24/2020
DOB NOWSidewalk ShedSigned-offUNIVERSAL SYSTEMS INC05/28/2020
DOB NOWConstruction FenceSigned-offH&Z BUILDING CONSULTING I01/02/2020
DOB NOWConstruction FenceSigned-offH&Z BUILDING CONSULTING I07/09/2019
BISPLISSUEDFLUSHING PLUMBING CORP06/30/2021
BIS—ISSUEDH&Z BUILDING CONSULTING I01/20/2021
BIS—ISSUEDH&Z BUILDING CONSULTING I09/23/2020
BISPLISSUEDSO PLUMBING & HEATING INC08/11/2020
BIS—ISSUEDH&Z BUILDING CONSULTING I06/09/2020
BIS—RE-ISSUEDH&Z BUILDING CONSULTING I11/25/2019
BIS—ISSUEDH&Z BUILDING CONSULTING I09/25/2019
BIS—ISSUEDH&Z BUILDING CONSULTING I09/25/2019
BISPLISSUEDL&J PLG & HTG CO OF NY IN06/25/2019
BISOTISSUEDWINWAY DEVELOPMENT LLC06/19/2019
BISOTISSUEDIHOME IMPROVEMENT & WINDO09/17/2013
BISPLISSUEDFIREBALL PIPING & HTG CORP11/16/2004
BISOTISSUEDAVA CONTRACTING INC09/23/2004
BISCCISSUEDN/A11/12/1997
5 projects · most recent 05/17/2022
General Wiring
FiledStatusContractorScope
05/17/2022Permit IssuedP.L. ELEC'L CONTR'G CORPGeneral Wiring
11/21/2021CompleteAERO ELECTRIC CORPGeneral Wiring
11/16/2021CompleteAL-LECTRIC ELECT'L CONTRG—
12/21/2020CompleteKWONG MING ELECTRIC INC—
05/26/2020CompleteTOP SHELF ELECTRIC CORP—
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
03/07/2023Pass-Final General Construction Non-Directive 14PassView ↗
12/29/2022Fail-Final General Construction Non-Directive 14FailView ↗
12/23/2022Fail-Final General Construction Non-Directive 14FailView ↗
10/26/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/29/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/15/2021Pass-Final Boiler Equipment InspectionPassView ↗
09/30/2021Pass-Final Curb Cut Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 75
DateRequirementInspectorRole
03/06/2023Fire-Resistant Penetrations and JointsXIUCHENG LIspecial
03/06/2023Mechanical SystemsXIUCHENG LIspecial
03/06/2023Structural Stability – Alterations of existing buildingsXIUCHENG LIspecial
03/06/2023Energy Code Compliance InspectionsXIUCHENG LIprogress
03/06/2023FinalXIUCHENG LIprogress
03/06/2023Fire-Resistance Rated ConstructionXIUCHENG LIprogress
03/06/2023HVAC-R and service water piping design and insulationXIUCHENG LIenergy_progress
03/06/2023Lighting controlsXIUCHENG LIenergy_progress
03/06/2023Maintenance informationXIUCHENG LIenergy_progress
03/06/2023Interior lighting powerXIUCHENG LIenergy_progress
03/06/2023Air barrier - visual inspectionXIUCHENG LIenergy_progress
03/06/2023HVAC-R and service water heating system controlsXIUCHENG LIenergy_progress
03/06/2023Shutoff dampersXIUCHENG LIenergy_progress
03/06/2023HVAC-R and service water heating equipmentXIUCHENG LIenergy_progress
03/06/2023Fenestration and door U-factor and product ratingsXIUCHENG LIenergy_progress
03/06/2023Fenestration air leakageXIUCHENG LIenergy_progress
03/06/2023Duct leakage testing, insulation and designXIUCHENG LIenergy_progress
03/06/2023Exterior lighting powerXIUCHENG LIenergy_progress
03/06/2023Fenestration areasXIUCHENG LIenergy_progress
03/03/2023HVAC-R and service water heating system controlsXIUCHENG LIenergy_progress
03/03/2023Fire-Resistant Penetrations and JointsXIUCHENG LIspecial
03/03/2023Mechanical SystemsXIUCHENG LIspecial
03/03/2023Structural Stability – Alterations of existing buildingsXIUCHENG LIspecial
03/03/2023Energy Code Compliance InspectionsXIUCHENG LIprogress
03/03/2023FinalXIUCHENG LIprogress
Latest 25 of 75.
▾Documents — 242 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch11
09/01/2026B00480636-I1Request digital key ↗
09/01/2026B00480636-P1Request digital key ↗
09/01/2026B00530397-I1Request digital key ↗
Showing 3 of 11 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence1
09/02/2026B00190169-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/02/2026B00352100-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
09/02/2026B00392344-I1Request digital key ↗
▸Applications & Permits47
▸BISPLAN / WORK APPROVAL APPLICATION36
04/11/2022321387968Open ↗
03/09/2022321387968Open ↗
03/08/2022321387968Open ↗
Showing 3 of 36 on file for this type
▸BISWORK PERMIT APPLICATION8
07/01/2021321387968Open ↗
08/11/2020321387968Open ↗
06/11/2020321387968Open ↗
Showing 3 of 8 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation2
01/15/2021340800994Open ↗
01/04/2021340800994Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
07/02/2021321387968Open ↗
▸Zoning, Tax Lot & Property Records12
▸BISZONING EXHIBIT I: CERTIFICATION3
07/21/2021321969713Open ↗
07/01/2019321387968Open ↗
06/21/2019321953196Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT2
07/21/2021321969713Open ↗
06/21/2019321953196Open ↗
▸BISVERIFY TAX LOT1
09/17/2021321387968Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
09/17/2021321387968Open ↗
▸BISZONING DIAGRAM1
07/01/2019321387968Open ↗
▸BISZONING APPEAL1
06/21/2019321953196Open ↗
▸BISDOB - ZONING DIAGRAM (ZD1)1
07/06/2020321387968Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
07/01/2019321387968Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
07/01/2019321387968Open ↗
▸Seals & Professional Certifications43
▸DOB NOWDPL-1: Design Professional Seal & Signature14
09/01/2026B00480636-I1Open ↗
09/01/2026B00480636-P1Open ↗
09/01/2026B00530397-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature10
08/31/2026B00723579-P1Open ↗
08/31/2026B00723579-P1Open ↗
08/29/2026B00726718-P1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
08/31/2026B00480636-P1Open ↗
08/31/2026B00723579-P1Open ↗
08/29/2026B00726718-P1Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION7
04/28/2021321958716Open ↗
03/05/2020321387968Open ↗
11/26/2019321958690Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
11/26/2019321958690Open ↗
06/24/2019321928072Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
01/04/2021340800994Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
06/24/2019321928072Open ↗
▸Trade Schedules & Equipment14
▸BISSCHEDULE B - PLUMBING8
11/30/2021321387968Open ↗
11/29/2021321387968Open ↗
12/04/2020321387968Open ↗
Showing 3 of 8 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
04/28/2021321958716Open ↗
06/24/2019321928072Open ↗
▸BISSPRINKLER (SP) SIGNOFF1
02/11/2022321387968Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
09/17/2021321387968Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
04/04/2022321387968Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
12/02/2021321387968Open ↗
▸Safety & Tenant Protection12
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE3
10/01/2019321387968Open ↗
10/01/2019321387968Open ↗
06/21/2019321953196Open ↗
▸BISTenant Protection Plan and Notes3
11/26/2019321958690Open ↗
07/01/2019321387968Open ↗
06/24/2019321928072Open ↗
▸BISSTREET TREE CHECKLIST2
01/13/2021340800994Open ↗
07/01/2019321387968Open ↗
▸BISBPP: STREET TREES SITE PLAN1
01/13/2021340800994Open ↗
▸BISSTREET TREE SIGNOFF1
11/05/2021321387968Open ↗
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
10/01/2019321387968Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
10/01/2019321387968Open ↗
▸Environmental & Asbestos12
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
09/01/2026B00480636-P1Open ↗
09/01/2026B00480636-I1Open ↗
08/28/2026B00723579-I1Open ↗
Showing 3 of 7 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
04/28/2021321958716Open ↗
11/26/2019321958690Open ↗
06/24/2019321928072Open ↗
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)2
07/08/2013320478906Open ↗
06/20/2013320478906Open ↗
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
11/18/2021321387968Open ↗
11/05/2021321387968Open ↗
07/02/2019321387968Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
03/05/2020321387968Open ↗
06/24/2019321928072Open ↗
06/24/2014320478906Open ↗
▸DOB NOWEN2: As Built Energy Analysis3
08/13/2026B00723579-I1Open ↗
08/13/2026B00726718-I1Open ↗
08/13/2026B00594252-I1Open ↗
▸BISTR8: Energy Code Progress Inspections2
07/08/2013320478906Open ↗
06/20/2013320478906Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
11/05/2021321387968Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
06/24/2014320478906Open ↗
▸Inspections & Test Reports10
▸BISTECHNICAL REPORT: RESPONSIBILITY5
11/05/2021321387968Open ↗
07/02/2019321387968Open ↗
07/02/2019321387968Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
12/07/2021321387968Open ↗
10/01/2019321387968Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX2
10/01/2019321387968Open ↗
10/01/2019321387968Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
07/02/2019321387968Open ↗
▸Approvals, Objections & Sign-offs14
▸BISSCHEDULE A - OCCUPANCY / USE11
03/09/2022321387968Open ↗
03/08/2022321387968Open ↗
02/22/2022321387968Open ↗
Showing 3 of 11 on file for this type
▸BISADMINISTRATIVE OBJECTIONS1
06/20/2013320478906Open ↗
▸BISTRANSIT AUTHORITY/MTA/PANYNJ APPROVAL1
09/17/2021321387968Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION1
06/24/2014320478906Open ↗
▸Cost, Insurance & Ownership14
▸BISCOST AFFIDAVIT10
11/05/2021321387968Open ↗
11/05/2021321387968Open ↗
04/28/2021321958716Open ↗
Showing 3 of 10 on file for this type
▸BISDEPT OF FINANCE VERIFICATION1
08/02/2021321969713Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
10/01/2019321387968Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE1
10/01/2019321387968Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
11/18/2021321387968Open ↗
▸Filing & Intake Forms30
▸BISADDITIONAL INFORMATION17
04/13/2022321387968Open ↗
03/15/2022321387968Open ↗
12/10/2021321387968Open ↗
Showing 3 of 17 on file for this type
▸BISEFILING COVER SHEET8
07/21/2021321969713Open ↗
04/28/2021321958716Open ↗
06/28/2019321958690Open ↗
Showing 3 of 8 on file for this type
▸BISBOROUGH INTAKE FORM3
08/12/2021321958716Open ↗
04/28/2021321958716Open ↗
04/16/2021321968634Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
01/04/2021340800994Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
01/04/2021340800994Open ↗
▸Other Documents4
▸BISPLOT DIAGRAM1
07/01/2019321387968Open ↗
▸BISUnknown1
07/01/2021321387968Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
05/17/2019321953196Open ↗
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
01/14/2021340800994Open ↗