| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/24/2021 | $1.8M | — | Private party → Private party | $532/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Nic 88 | 3 | 01/27/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| Basic Groups | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Cube Builders Group NY | General Contractor | 2 | 04/09/2026 |
| Pipestylists | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Nic Design | 9758 | 2 | 01/27/2026 |
| Aaron McDonald Architect | 5118 | 1 | 11/01/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | T & T Plumbing | 06/04/2025 |
| DOB NOW | General Construction | Signed-off | Cube Builders Group NY | 03/28/2025 |
| DOB NOW | Plumbing | Signed-off | T & T Plumbing | 11/04/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Cube Builders Group NY | 10/02/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/31/2026 | Permit Issued | KJK Electric | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/28/2026 | Mechanical Systems | Eric Sun | special |
| 01/28/2026 | Fire-Resistant Penetrations and Joints | Eric Sun | special |
| 01/28/2026 | Final | Eric Sun | progress |
| 01/28/2026 | Energy Code Compliance Inspections | Eric Sun | progress |
| 01/28/2026 | Fire-Resistance Rated Construction | Eric Sun | progress |
| 01/28/2026 | Fenestration and door U-factor and product ratings | Eric Sun | energy_progress |
| 01/28/2026 | Interior lighting power | Eric Sun | energy_progress |
| 01/28/2026 | Insulation placement and R values | Eric Sun | energy_progress |
| 01/28/2026 | HVAC-R and service water piping design and insulation | Eric Sun | energy_progress |
| 01/28/2026 | HVAC-R and service water heating equipment | Eric Sun | energy_progress |
| 01/28/2026 | Air barrier - visual inspection | Eric Sun | energy_progress |
| 01/28/2026 | Fenestration areas | Eric Sun | energy_progress |
| 01/28/2026 | Masonry | Eric Sun | special |
| 01/28/2026 | Fenestration air leakage | Eric Sun | energy_progress |
| 01/28/2026 | Duct leakage testing, insulation and design | Eric Sun | energy_progress |
| 01/28/2026 | Ventilation and air distribution system | Eric Sun | energy_progress |
| 01/28/2026 | HVAC-R and service water heating system controls | Eric Sun | energy_progress |
| 01/28/2026 | Maintenance information | Eric Sun | energy_progress |
| 01/27/2026 | HVAC-R and service water piping design and insulation | Eric Sun | energy_progress |
| 01/27/2026 | Fire-Resistant Penetrations and Joints | Eric Sun | special |
| 01/27/2026 | Masonry | Eric Sun | special |
| 01/27/2026 | Mechanical Systems | Eric Sun | special |
| 01/27/2026 | Energy Code Compliance Inspections | Eric Sun | progress |
| 01/27/2026 | Final | Eric Sun | progress |
| 01/27/2026 | Fire-Resistance Rated Construction | Eric Sun | progress |