| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/21/2025 | Permit Issued | YAFE MEOD CORP | Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/17/2025 | Permit Issued | ARCO PLBG AND HTG INC | 51 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/21/2025 | Signed-off | NY PLUMBING PROS INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/23/2026 | Permit Issued | POWER SURGE ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/21/2025 | Permit Issued | YAFE MEOD CORP | 2 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/21/2025 | Permit Issued | YAFE MEOD CORP | Earthwork |
| Owner | Filings | Most Recent |
|---|---|---|
| NY DYNAMIC CONSTRUCTION | 17 | 08/27/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/23/2024 | $300K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| GERALD CALIENDO ARCHITECTS | 4 | 10/21/2025 |
| FABIAN CRUZ PE PLLC | 2 | 10/17/2025 |
| RAS PE CONSULTING ENGINEERS | 2 | 02/06/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| GERALD J. CALIENDO R.A., P.C. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| YAFE MEOD CORP | General Contractor | 5 | 08/27/2026 |
| ARCO PLBG AND HTG INC | Fire Protection | 1 | 07/08/2026 |
| BT'S PLUMBING AND HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AA BUILDING & INSPECTION | 1519 | 4 | 03/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | YAFE MEOD CORP | 08/26/2026 |
| DOB NOW | Sprinklers | Permit Issued | ARCO PLBG AND HTG INC | 02/26/2026 |
| DOB NOW | Plumbing | Signed-off | BT'S PLUMBING AND HEATING | 02/24/2026 |
| DOB NOW | Earth Work | Signed-off | YAFE MEOD CORP | 11/06/2025 |
| DOB NOW | Support of Excavation | Permit Issued | YAFE MEOD CORP | 11/05/2025 |
| DOB NOW | General Construction | Permit Issued | YAFE MEOD CORP | 10/31/2025 |
| DOB NOW | Construction Fence | Permit Issued | YAFE MEOD CORP | 08/11/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/17/2026 | Pass-Final Sign Permit Inspection | Pass | View ↗ |
| 04/08/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/08/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/06/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 03/23/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/13/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/29/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/29/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/05/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2025 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| 05/09/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 05/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/09/2024 | Pass-Final House Connection | Pass | View ↗ |
| 09/09/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/27/2025 | HVAC-R and service water heating system controls | Younes Abouyaala | energy_progress |
| 10/27/2025 | HVAC-R and service water heating equipment | Younes Abouyaala | energy_progress |
| 10/27/2025 | Permanent certificate | Younes Abouyaala | energy_progress |
| 10/27/2025 | Maintenance information | Younes Abouyaala | energy_progress |
| 10/27/2025 | HVAC-R and service water piping design and insulation | Younes Abouyaala | energy_progress |
| 10/21/2025 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 10/21/2025 | HVAC-R and service water heating equipment | — | energy_progress |
| 10/21/2025 | Permanent certificate | — | energy_progress |
| 10/21/2025 | HVAC-R and service water heating system controls | — | energy_progress |
| 10/21/2025 | Maintenance information | — | energy_progress |
| 10/20/2025 | Sprinkler Systems | Younes Abouyaala | special |
| 10/15/2025 | Sprinkler Systems | — | special |
| 01/30/2025 | Footing and Foundation | Younes Abouyaala | progress |
| 01/30/2025 | Final | NAVEEN KUMAR | progress |
| 01/30/2025 | Designated Seismic System | Younes Abouyaala | special |