← Back
Training school
Democracy Prep Harlem Charter High School
207 WEST 119 STREET · BIN 1058447
💬 Discuss this project
1930Year Built
4Stories
W4Building Class
R7AZoning
76,794 sfGross Floor Area
1Units
LL97 Covered9 Open Violations 1 unresolved · 8 paperwork only ▸
Training school · Owner of record: NYC DEPARTMENT OF EDUCATION · 30,275 sf lot · 2.54 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Floor 410p · 1 filing · 19 docs
Floor 34p · 1 filing · 19 docs
Floor 2
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DEMOCRACY PREP HARLEM MIDDLE SCHOOL903/22/2026
NYC DEPARTMENT OF EDUCATION103/22/2026
DOE ADULT TRAINING CT040403/22/2026
DOE 040303/22/2026
DOE M 081 040203/22/2026
DEPARTMENT OF EDUCATION403/22/2026
DOE 0 040203/22/2026
DEPARTMENT OF EDUCATION 0203/22/2026
DEPT OF EDUCATION M081 0103/22/2026
PS 81 DEPT OF EDUCATION04203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
EME CONSULTING ENGINEERING GROUP503/16/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JM ZONING, LLC.603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TRULINE CONSTRUCTION SERVGeneral Contractor1503/21/2026
JOSEPH FERGUSONElectrical803/21/2026
DIA GENERAL CONTRUCTION IGeneral Contractor603/21/2026
WILLIAM NIEVESElectrical103/21/2026
DH EAGLE PLBG & HTG INCPlumbing107/08/2026
GEMINI ELECTRIC CO., INC.Electrical103/22/2026
RAPTOR MECHANICAL,INCPlumbing107/08/2026
NIEVES WILLIAMElectrical103/21/2026
STANCO SYSTEM ELEC'L CONTElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AK ENGINEERING PC678303/16/2023
JPC LOGISTICS DBA JPCL EN351207/14/2022
Building Lifecycle
All (111)Filed (5)Permit Issued (9)Signed Off (1)Violation (60)Inspection (4)Objection (2)Special Inspection (30)
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
08/03/2026
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
09/02/2025
Violation issued (ECB, open)
Construction
02/07/2025
Permit issued — Plumbing
M00772634-S1-PL
02/07/2025
Permit issued — General Construction
M00772634-I1-GC-CX
09/19/2024
Violation issued (ECB, open)
Construction
09/19/2024
Violation issued (ECB, open)
Construction
09/19/2024
Violation issued (ECB, closed)
Construction
02/14/2024
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
01/29/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/11/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/31/2023
Permit issued — Plumbing
M00772634-S1-PL
08/29/2023
Signed off — Alteration
FILING FOR GENERAL CONSTRUCTION WORK & INSTALLATION OF A NEW HVAC SYSTEM AS PER PLANS FILED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00749562-I1
08/25/2023
Permit issued — Mechanical Systems
M00772634-I1-GC-CX
08/24/2023
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/30/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/20/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/02/2023
Permit issued — General Construction
M00749562-I1-GC
03/22/2023
Special inspection requirement — Mechanical Systems
Ari Kamo
03/22/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
03/22/2023
Special inspection requirement — Post-installed Anchors
Ari Kamo
03/22/2023
Special inspection requirement — Final
Ari Kamo
03/22/2023
Special inspection requirement — HVAC-R and service water heating system controls
Ari Kamo
03/22/2023
Special inspection requirement — Lighting controls
Ari Kamo
03/22/2023
Special inspection requirement — Interior lighting power
Ari Kamo
03/22/2023
Special inspection requirement — HVAC-R and service water heating equipment
Ari Kamo
03/22/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Ari Kamo
03/22/2023
Special inspection requirement — Maintenance information
Ari Kamo
03/16/2023
Filed — Alteration
FILING FOR GENERAL CONSTRUCTION WORK & INSTALLATION OF A NEW HVAC SYSTEM AS PER PLANS FILED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00749562-P2
03/15/2023
Permit issued — General Construction
M00749562-I1-GC
03/09/2023
Permit issued — Mechanical Systems
M00749562-I1-MS
03/07/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
03/07/2023
Special inspection requirement — Mechanical Systems
Ari Kamo
03/07/2023
Special inspection requirement — Post-installed Anchors
Ari Kamo
03/07/2023
Special inspection requirement — Final
Ari Kamo
03/07/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
Ari Kamo
03/07/2023
Special inspection requirement — HVAC-R and service water heating system controls
Ari Kamo
03/07/2023
Special inspection requirement — HVAC-R and service water heating equipment
Ari Kamo
03/07/2023
Special inspection requirement — Maintenance information
Ari Kamo
03/07/2023
Special inspection requirement — Lighting controls
Ari Kamo
03/07/2023
Special inspection requirement — Interior lighting power
Ari Kamo
08/16/2022
Permit issued — Mechanical Systems
M00749562-I1-GC
08/16/2022
Permit issued — Mechanical Systems
M00749562-I1-MS
08/15/2022
Filed — Alteration
FILING FOR GENERAL CONSTRUCTION WORK & INSTALLATION OF A NEW HVAC SYSTEM AS PER PLANS FILED. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00749562-P1
08/15/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
08/15/2022
Special inspection requirement — Mechanical Systems
Ari Kamo
08/15/2022
Special inspection requirement — Post-installed Anchors
Ari Kamo
08/15/2022
Special inspection requirement — Final
Ari Kamo
08/15/2022
Special inspection requirement — Interior lighting power
Ari Kamo
08/15/2022
Special inspection requirement — HVAC-R and service water heating equipment
Ari Kamo
08/15/2022
Special inspection requirement — Lighting controls
Ari Kamo
08/15/2022
Special inspection requirement — Maintenance information
Ari Kamo
08/15/2022
Special inspection requirement — HVAC-R and service water heating system controls
Ari Kamo
08/15/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
Ari Kamo
07/14/2022
Filed — Alteration
M00772634-S1
Latest 60 of 111 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedL.SPINA PLUMB & HTG INC02/07/2025
DOB NOWGeneral ConstructionPermit IssuedDIA GENERAL CONTRUCTION I02/07/2025
DOB NOWPlumbingPermit IssuedRAPTOR MECHANICAL, INC08/31/2023
DOB NOWMechanical SystemsPermit IssuedDIA GENERAL CONTRUCTION I08/25/2023
DOB NOWGeneral ConstructionSigned-offTRULINE CONSTRUCTION SERV05/02/2023
DOB NOWGeneral ConstructionSigned-offTRULINE CONSTRUCTION SERV03/15/2023
DOB NOWMechanical SystemsSigned-offTRULINE CONSTRUCTION SERV03/09/2023
DOB NOWMechanical SystemsSigned-offTRULINE CONSTRUCTION SERV08/16/2022
DOB NOWMechanical SystemsSigned-offTRULINE CONSTRUCTION SERV08/16/2022
BISMHISSUEDKW TECH CORP01/23/2025
BISOTISSUEDSKYLINE INDUSTRIES LLC03/13/2024
BISMHISSUEDKW TECH CORP01/24/2024
BISOTISSUEDKG CONSTRUCTION SERVICES01/04/2024
BISOTISSUEDSKYLINE INDUSTRIES LLC04/07/2023
BISOTISSUEDKG CONSTRUCTION SERVICES02/23/2023
BISOTISSUEDKG CONSTRUCTION SERVICES02/23/2023
BISOTISSUEDKG CONSTRUCTION SERVICES02/23/2023
BISMHISSUEDKW TECH CORP02/01/2023
BISPLISSUEDFORSYTHE P&H CORP10/07/2022
BISMHISSUEDR.A.M.S. MECHANICAL INC10/07/2022
BISOTISSUEDSKYLINE INDUSTRIES LLC04/06/2022
BISOTISSUEDKG CONSTRUCTION SERVICES02/23/2022
BISOTISSUEDKG CONSTRUCTION SERVICES02/23/2022
BISOTISSUEDKG CONSTRUCTION SERVICES02/23/2022
BISMHISSUEDKW TECH CORP02/03/2022
BISEQISSUEDKG CONSTRUCTION SERVICES12/20/2021
BISMHISSUEDR.A.M.S. MECHANICAL INC10/05/2021
BISOTISSUEDKG CONSTRUCTION SERVICES02/26/2021
BISOTISSUEDSKYLINE INDUSTRIES LLC02/24/2021
BISOTISSUEDKG CONSTRUCTION SERVICES02/23/2021
BISOTISSUEDKG CONSTRUCTION SERVICES02/23/2021
BISPLISSUEDFORSYTHE P&H CORP02/03/2021
BISEQISSUEDROMA SCAFFOLDING INC01/11/2021
BISOTISSUEDKG CONSTRUCTION SERVICES12/11/2020
BISEQISSUEDKG CONSTRUCTION SERVICES12/02/2020
BISEQISSUEDROMA SCAFFOLDING INC12/02/2020
BISEQISSUEDKG CONSTRUCTION SERVICES12/02/2020
BISMHISSUEDR.A.M.S. MECHANICAL INC03/24/2020
BISOTISSUEDKG CONSTRUCTION SERVICES02/24/2020
BISOTISSUEDKG CONSTRUCTION SERVICES02/24/2020
+ 19 more permits on file
12 projects · most recent 06/19/2026
General Wiring Lighting
FiledStatusContractorScope
06/19/2026Permit IssuedMETROPOLITAN ELEC OF NY IGeneral Wiring
10/16/2025CompleteVIAL ELECTRIC & COMPANYLighting
08/16/2024Permit IssuedC.FALCO ELETL CONT CORPGeneral Wiring
01/24/2024CompleteAVALON ELECTRIC CORP.General Wiring
11/22/2023CompleteANCO ELECTL CONTCTNG INCGeneral Wiring
10/25/2023Permit IssuedGEMINI ELECTRIC CO., INC.General Wiring
09/11/2023CompleteANCO ELECTL CONTCTNG INC—
03/27/2023CompleteMECHANICAL ELECTR'L CORP.—
12/02/2022CompleteGEMINI ELECTRIC CO., INC.General Wiring
10/03/2022Permit IssuedGEMINI ELECTRIC CO., INC.General Wiring
12/03/2019CompleteSTANCO SYSTEM ELEC'L CONT—
12/02/2019CompleteMECHANICAL ELECTR'L CORP.—
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
02/14/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
01/29/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/11/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/24/2023Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 34
DateRequirementInspectorRole
03/22/2023Mechanical SystemsAri Kamospecial
03/22/2023Fire-Resistant Penetrations and JointsAri Kamospecial
03/22/2023Post-installed AnchorsAri Kamospecial
03/22/2023FinalAri Kamoprogress
03/22/2023HVAC-R and service water heating system controlsAri Kamoenergy_progress
03/22/2023Lighting controlsAri Kamoenergy_progress
03/22/2023Interior lighting powerAri Kamoenergy_progress
03/22/2023HVAC-R and service water heating equipmentAri Kamoenergy_progress
03/22/2023HVAC-R and service water piping design and insulationAri Kamoenergy_progress
03/22/2023Maintenance informationAri Kamoenergy_progress
03/07/2023Fire-Resistant Penetrations and JointsAri Kamospecial
03/07/2023Mechanical SystemsAri Kamospecial
03/07/2023Post-installed AnchorsAri Kamospecial
03/07/2023FinalAri Kamoprogress
03/07/2023HVAC-R and service water piping design and insulationAri Kamoenergy_progress
03/07/2023HVAC-R and service water heating system controlsAri Kamoenergy_progress
03/07/2023HVAC-R and service water heating equipmentAri Kamoenergy_progress
03/07/2023Maintenance informationAri Kamoenergy_progress
03/07/2023Lighting controlsAri Kamoenergy_progress
03/07/2023Interior lighting powerAri Kamoenergy_progress
08/15/2022Fire-Resistant Penetrations and JointsAri Kamospecial
08/15/2022Mechanical SystemsAri Kamospecial
08/15/2022Post-installed AnchorsAri Kamospecial
08/15/2022FinalAri Kamoprogress
08/15/2022Interior lighting powerAri Kamoenergy_progress
Latest 25 of 34.
▾Documents — 39 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
09/02/2026M00749562-P1Request digital key ↗
09/02/2026M00749562-P2Request digital key ↗
09/02/2026M00772634-S1Request digital key ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications18
▸DOB NOWProgress Inspector Seal & Signature8
08/25/2026M00749562-P1Open ↗
08/25/2026M00749562-P1Open ↗
08/25/2026M00749562-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
08/25/2026M00749562-P1Open ↗
08/25/2026M00749562-I1Open ↗
08/24/2026M00749562-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature5
09/02/2026M00749562-P1Open ↗
09/02/2026M00749562-I1Open ↗
09/02/2026M00749562-P2Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
09/02/2026M00772634-S1Open ↗
08/14/2026M00749562-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis1
08/14/2026M00749562-I1Open ↗
▸Approvals, Objections & Sign-offs11
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter5
09/02/2026M00749562-P1Open ↗
09/02/2026M00749562-P2Open ↗
09/02/2026M00772634-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)2
08/13/2026M00772634-S1Open ↗
08/13/2026M00772634-I1Open ↗
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)2
08/13/2026M00772634-I1Open ↗
08/13/2026M00772634-S1Open ↗
▸DOB NOWDEP Variance (V5) letter2
09/02/2026M00772634-S1Open ↗
09/02/2026M00772634-I1Open ↗
▸Other Documents2
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal2
08/13/2026M00772634-I1Open ↗
08/13/2026M00772634-S1Open ↗